Test 1 (Upi 2013)

Reviewed by Editorial Team
The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Tomislav92
T
Tomislav92
Community Contributor
Quizzes Created: 1 | Total Attempts: 252
| Attempts: 252
SettingsSettings
Please wait...
  • 1/10 Questions

    Podela projekta sa aspekta vremena trajanja, finansija i utroska resursa je na: 1.investicioni 2.biznis 3. _____________

Please wait...
Project Management Quizzes & Trivia
About This Quiz

TEST 1 (UPI 2013) assesses knowledge in project management, focusing on WBS diagrams, activity durations, and network models. It evaluates understanding of project division and time estimation under various conditions, relevant for professionals and students in project management.


Quiz Preview

  • 2. 

    Projekat predstavlja:

    • Odredjeni posao koji treba da se zavrski u buducnosti, ogranicen vremenom, resursima i troskovima.

    • Odredjeni posao koji treba da se zavrski u buducnosti, ogranicen vremenom i troskovima.

    • Odredjeni posao koji treba da se zavrski u buducnosti, ogranicen resursima i troskovima.

    Correct Answer
    A. Odredjeni posao koji treba da se zavrski u buducnosti, ogranicen vremenom, resursima i troskovima.
    Explanation
    The correct answer is "Odredjeni posao koji treba da se zavrski u buducnosti, ogranicen vremenom, resursima i troskovima." This option accurately describes a project as a specific task that needs to be completed in the future, with limitations on time, resources, and costs.

    Rate this question:

  • 3. 

    WBS Dijagram predstavlja?

    • Poslove i zadatke koje treba uraditi da bi se zavrsio veci deo projekta?

    • Poslove i zadatke koje treba uraditi da bi se zavrsio jedan deo projekta?

    • Poslove i zadatke koje treba uraditi da bi se zavrsio projekat u celini?

    Correct Answer
    A. Poslove i zadatke koje treba uraditi da bi se zavrsio projekat u celini?
    Explanation
    The correct answer is "Poslove i zadatke koje treba uraditi da bi se zavrsio projekat u celini." This answer accurately describes the purpose of a WBS Diagram, which is to outline and organize all the tasks and activities that need to be completed in order to finish the entire project. It helps to break down the project into smaller, manageable components, allowing for better planning, scheduling, and resource allocation.

    Rate this question:

  • 4. 

    Usiljeno vreme  trajanja aktivnosti je:

    • Najmanje vreme trajanja koje podrazumeva najbrzi rad i angazovanje sredstva.

    • Najduze vreme trajanja koje podrazumeva najbrzi rad i angazovanje sredstva u skladu sa tipom projekta.

    • Vreme trajanja jednako normalnom vremenju trajanja aktivnosti,koja podrazumeva najbrzi rad i angazovanje sredstva

    Correct Answer
    A. Najmanje vreme trajanja koje podrazumeva najbrzi rad i angazovanje sredstva.
    Explanation
    The correct answer is "Najmanje vreme trajanja koje podrazumeva najbrzi rad i angazovanje sredstva." This means that the activity will be completed in the shortest possible time, with the fastest work and resource utilization. This implies that no delays or inefficiencies are expected during the execution of the activity.

    Rate this question:

  • 5. 

    Dogadjaj se graficki predstavlja kao:

    • Isprekidana linija

    • Vektor

    • Krug

    Correct Answer
    A. Krug
    Explanation
    A događaj se graficki predstavlja kao krug jer krug predstavlja jedinstvenu i zatvorenu formu. Događaj se može smatrati kao nešto što se odvija u određenom vremenskom periodu, a krug može predstavljati taj period. Također, krug se često koristi kao simbol za ponavljanje ili cikličnost, što može biti relevantno za predstavljanje događaja.

    Rate this question:

  • 6. 

    Optimisticko vreme predstavlja?

    • Najkrace procenjeno vreme za realizaciju aktivnosti pod izuzetno lakim uslovima.

    • Najduze procenjeno vreme za realizaciju aktivnosti pod izuzetno teskim uslovima.

    • Najkrace procenjeno vreme za realizaciju aktivnosti pod izuzetno teskim uslovima.

    Correct Answer
    A. Najkrace procenjeno vreme za realizaciju aktivnosti pod izuzetno teskim uslovima.
    Explanation
    The correct answer is "Najkrace procenjeno vreme za realizaciju aktivnosti pod izuzetno teskim uslovima." This means that optimistic time represents the shortest estimated time for completing an activity under extremely difficult conditions.

    Rate this question:

  • 7. 

    Analiza strukture kod tehnike mreznog planiranja definise:

    • Medjuzavisnost odvijanja aktivnosti

    • Vremenske ogranicenosti projekta

    • Resursnu rasporedjenost u projektu

    Correct Answer
    A. Medjuzavisnost odvijanja aktivnosti
    Explanation
    The correct answer is "Medjuzavisnost odvijanja aktivnosti." This is because the analysis of the structure of the code in network planning technique involves determining the interdependencies between the activities. By understanding how the activities are related and dependent on each other, it becomes easier to plan and schedule the project effectively.

    Rate this question:

  • 8. 

    Mrezni modeli predstavljaju?

    • Graficki prikaz resursnog prikaza odvijanja poslovnog poduhvata koji cini jednu zaokruzenu celinu.

    • Graficki prikaz tehnoloskog i vremenskog odvijanja poslovnog poduhvata koji cini jednu zaokruzenu celinu.

    • Graficki prikaz troskovnog prikaza odvijanja poslovnog poduhvata koji cini jednu zaokruzenu celinu.

    Correct Answer
    A. Graficki prikaz tehnoloskog i vremenskog odvijanja poslovnog poduhvata koji cini jednu zaokruzenu celinu.
    Explanation
    The correct answer is "Graficki prikaz tehnoloskog i vremenskog odvijanja poslovnog poduhvata koji cini jednu zaokruzenu celinu." This answer explains that network models represent the graphical representation of the technological and temporal progress of a business endeavor that constitutes a complete entity.

    Rate this question:

  • 9. 

    Plan kvaliteta je:

    • Manje detaljan od programa kvaliteta

    • Isti kao i program kvaliteta

    • Detaljniji od programa kvaliteta

    Correct Answer
    A. Detaljniji od programa kvaliteta
    Explanation
    The correct answer is "Detaljniji od programa kvaliteta" (More detailed than the quality program). This means that the quality plan provides a more in-depth and comprehensive approach to ensuring and managing quality compared to the quality program. While the quality program may outline the overall objectives and strategies for quality management, the quality plan will provide specific details on how these objectives will be achieved, including specific processes, procedures, and metrics to be followed.

    Rate this question:

  • 10. 

    Normalno vreme trajanja aktivnosti je:

    • Proces odvijanja aktivnosti uz angazovanje maksimalnih troskova.

    • Proces odvijanja aktivnosti uz angazovanje optimalnih troskova.

    • Proces odvijanja aktivnosti uz angazovanje minimalnih troskova.

    Correct Answer
    A. Proces odvijanja aktivnosti uz angazovanje minimalnih troskova.
    Explanation
    The correct answer is "Proces odvijanja aktivnosti uz angazovanje minimalnih troskova." This means that the normal duration of an activity is the process of carrying out the activity with the minimum cost. In other words, it refers to completing the activity in the most cost-effective manner, minimizing expenses as much as possible.

    Rate this question:

Quiz Review Timeline (Updated): Mar 14, 2023 +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 14, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Apr 10, 2013
    Quiz Created by
    Tomislav92
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.