Are You Ready To Attempt The Project Management Exam Test?

Approved & Edited by ProProfs Editorial Team
The editorial team at ProProfs Quizzes consists of a select group of subject experts, trivia writers, and quiz masters who have authored over 10,000 quizzes taken by more than 100 million users. This team includes our in-house seasoned quiz moderators and subject matter experts. Our editorial experts, spread across the world, are rigorously trained using our comprehensive guidelines to ensure that you receive the highest quality quizzes.
Learn about Our Editorial Process
| By Rachna
R
Rachna
Community Contributor
Quizzes Created: 1 | Total Attempts: 492
Questions: 10 | Attempts: 507

SettingsSettingsSettings
Are You Ready To Attempt The Project Management Exam Test? - Quiz

Are you ready to attempt the project management exam test? Everyone gets unsure about their readiness for an exam once in a while, and to help you gauge how ready you are, we have compiled a quiz made up of some commonly asked questions. Do give it a shot and get to see if you need to find some more hours to study.


Questions and Answers
  • 1. 

    Slack is

    • A.

      The amount of time a non-critical task can be delayed without making the project late.

    • B.

      The amount of time the critical path of a project can be delayed without making the project late

    • C.

      The amount of time an activity on the critical path can be delayed without making the project late

    • D.

      The difference between how long the project would take if all tasks were completed based on their early start time

    • E.

      None of the above

    Correct Answer
    A. The amount of time a non-critical task can be delayed without making the project late.
    Explanation
    Slack refers to the amount of time that a non-critical task can be delayed without causing a delay in the overall project. It is the flexibility or buffer time available for non-critical tasks. This means that if a non-critical task takes longer than initially planned, it will not impact the project's completion date as long as it is completed within the slack time. Therefore, the correct answer is "The amount of time a non-critical task can be delayed without making the project late."

    Rate this question:

  • 2. 

    Which of the following is NOT one of the basic rules to follow when developing project networks?

    • A.

      An activity cannot begin until all preceding activities have been completed

    • B.

      An activity identification number must be larger than that of any preceding activities

    • C.

      Each activity must have a unique identification number

    • D.

      Networks flow from left to right

    • E.

      Complete backward pass first and then forward pass to calculate slack

    Correct Answer
    E. Complete backward pass first and then forward pass to calculate slack
    Explanation
    The correct answer is "Complete backward pass first and then forward pass to calculate slack". This is not one of the basic rules to follow when developing project networks. The basic rules include ensuring that an activity cannot begin until all preceding activities have been completed, assigning activity identification numbers in a way that they are larger than any preceding activities, and ensuring that each activity has a unique identification number. Additionally, project networks flow from left to right, which is another basic rule to follow.

    Rate this question:

  • 3. 

    A Term NOT used in the discussion of PERT/CPM analysis is

    • A.

      Activity

    • B.

      Critical Path

    • C.

      Networks

    • D.

      Slack

    • E.

      Feasibility 

    Correct Answer
    E. Feasibility 
    Explanation
    This question asks for a term that is not used in the discussion of PERT/CPM analysis. PERT/CPM analysis is a project management technique used to plan and control the scheduling of tasks in a project. The terms activity, critical path, networks, and slack are all commonly used in the discussion of PERT/CPM analysis as they are key concepts in this methodology. However, feasibility is not directly related to PERT/CPM analysis. Feasibility refers to the assessment of whether a project is technically and economically viable. While feasibility may be considered in the overall project management process, it is not a specific term used in the discussion of PERT/CPM analysis.

    Rate this question:

  • 4. 

    It is possible for a project network to have more than one critical path?

    • A.

      Yes

    • B.

      No

    Correct Answer
    A. Yes
    Explanation
    A critical path is the longest path in a project network that determines the minimum time required to complete the project. It consists of a series of dependent activities that must be completed in a specific order. In some cases, there may be multiple paths in the network that have the same duration and are equally critical. This means that if any activity on any of these paths is delayed, it will directly impact the project's overall completion time. Therefore, it is possible for a project network to have more than one critical path.

    Rate this question:

  • 5. 

    When it was originally developed, PERT used certain (deterministic) methods to estimate activity duration.

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    PERT (Program Evaluation and Review Technique) was developed to handle uncertain and unpredictable activity durations. It uses probabilistic methods, such as the three-point estimation technique, which takes into account optimistic, pessimistic, and most likely estimates for activity durations. This allows for a more realistic and flexible approach in estimating project timelines. Therefore, the statement that PERT used deterministic methods to estimate activity duration is false.

    Rate this question:

  • 6. 

    AON and AOA networks can both be used to depict any project network

    • A.

      True

    • B.

      False

    Correct Answer
    A. True
    Explanation
    Both AON (Activity on Node) and AOA (Activity on Arrow) networks are commonly used in project management to depict project networks. AON uses nodes to represent activities and arrows to represent dependencies between activities. AOA, on the other hand, uses arrows to represent activities and nodes to represent events. Both types of networks can effectively illustrate the sequence of activities and their relationships, making them suitable for representing any project network. Therefore, the statement that AON and AOA networks can both be used to depict any project network is true.

    Rate this question:

  • 7. 

    The shortest time to complete a network is equal to the duration of the longest path through the network

    • A.

      True

    • B.

      False

    Correct Answer
    A. True
    Explanation
    The statement is true because the longest path through a network represents the critical path, which is the sequence of activities that takes the longest time to complete. The duration of this critical path determines the shortest time required to complete the entire network. Therefore, the shortest time to complete a network is indeed equal to the duration of the longest path through the network.

    Rate this question:

  • 8. 

    Critical path tasks always have zero slack

    • A.

      True

    • B.

      False

    Correct Answer
    A. True
    Explanation
    The statement is true because critical path tasks are the tasks that must be completed in order to complete a project on time. These tasks have no flexibility in terms of time and any delay in their completion will directly impact the overall project timeline. Therefore, critical path tasks always have zero slack, meaning there is no room for delay or slack in their scheduling.

    Rate this question:

  • 9. 

    Reducing project duration 

    • A.

      Involves crashing all activities on critical path

    • B.

      Can only be done when resources are not constrained

    • C.

      Is always more expensive

    • D.

      Tends to increase network sensitivity

    • E.

      Should be considered for all projects

    Correct Answer
    C. Is always more expensive
    Explanation
    Reducing project duration is always more expensive because it usually requires additional resources, such as overtime pay, hiring extra staff, or utilizing expensive equipment to complete the project in a shorter time frame. This increased cost is necessary to speed up the project and meet the desired deadline. However, it is not the only factor to consider when deciding whether to reduce project duration, as other factors such as the project's importance, available resources, and potential risks should also be taken into account.

    Rate this question:

  • 10. 

    The delaying of any activity on the critical path will delay the completion of the project by the same amount

    • A.

      True

    • B.

      False

    Correct Answer
    A. True
    Explanation
    If an activity is on the critical path of a project, it means that it has zero float or slack time and any delay in its completion will directly impact the project's overall timeline. Therefore, if any activity on the critical path is delayed, the project's completion will be delayed by the same amount. This is because the critical path determines the minimum time required to complete the project, and any delay in the critical path activities will extend the project's duration.

    Rate this question:

Quiz Review Timeline +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 21, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Nov 06, 2019
    Quiz Created by
    Rachna
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.