Are You Ready To Attempt The Project Management Exam Test?

10 Questions | Attempts: 422
Share

SettingsSettingsSettings
Are You Ready To Attempt The Project Management Exam Test? - Quiz

Are you ready to attempt the project management exam test? Everyone gets unsure about their readiness for an exam once in a while, and to help you gauge how ready you are, we have compiled a quiz made up of some commonly asked questions. Do give it a shot and get to see if you need to find some more hours to study.


Questions and Answers
  • 1. 
    Slack is
    • A. 

      The amount of time a non-critical task can be delayed without making the project late.

    • B. 

      The amount of time the critical path of a project can be delayed without making the project late

    • C. 

      The amount of time an activity on the critical path can be delayed without making the project late

    • D. 

      The difference between how long the project would take if all tasks were completed based on their early start time

    • E. 

      None of the above

  • 2. 
    Which of the following is NOT one of the basic rules to follow when developing project networks?
    • A. 

      An activity cannot begin until all preceding activities have been completed

    • B. 

      An activity identification number must be larger than that of any preceding activities

    • C. 

      Each activity must have a unique identification number

    • D. 

      Networks flow from left to right

    • E. 

      Complete backward pass first and then forward pass to calculate slack

  • 3. 
    A Term NOT used in the discussion of PERT/CPM analysis is
    • A. 

      Activity

    • B. 

      Critical Path

    • C. 

      Networks

    • D. 

      Slack

    • E. 

      Feasibility 

  • 4. 
    It is possible for a project network to have more than one critical path?
    • A. 

      Yes

    • B. 

      No

  • 5. 
    When it was originally developed, PERT used certain (deterministic) methods to estimate activity duration.
    • A. 

      True

    • B. 

      False

  • 6. 
    AON and AOA networks can both be used to depict any project network
    • A. 

      True

    • B. 

      False

  • 7. 
    The shortest time to complete a network is equal to the duration of the longest path through the network
    • A. 

      True

    • B. 

      False

  • 8. 
    Critical path tasks always have zero slack
    • A. 

      True

    • B. 

      False

  • 9. 
    Reducing project duration 
    • A. 

      Involves crashing all activities on critical path

    • B. 

      Can only be done when resources are not constrained

    • C. 

      Is always more expensive

    • D. 

      Tends to increase network sensitivity

    • E. 

      Should be considered for all projects

  • 10. 
    The delaying of any activity on the critical path will delay the completion of the project by the same amount
    • A. 

      True

    • B. 

      False