Are You Ready To Attempt The Project Management Exam Test?

  • PMP
  • CAPM
  • PRINCE2
Reviewed by Editorial Team
The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Rachna
R
Rachna
Community Contributor
Quizzes Created: 1 | Total Attempts: 554
| Attempts: 554 | Questions: 10
Please wait...
Question 1 / 10
0 %
0/100
Score 0/100
1. The delaying of any activity on the critical path will delay the completion of the project by the same amount

Explanation

If an activity is on the critical path of a project, it means that it has zero float or slack time and any delay in its completion will directly impact the project's overall timeline. Therefore, if any activity on the critical path is delayed, the project's completion will be delayed by the same amount. This is because the critical path determines the minimum time required to complete the project, and any delay in the critical path activities will extend the project's duration.

Submit
Please wait...
About This Quiz
Are You Ready To Attempt The Project Management Exam Test? - Quiz

Are you ready to attempt the project management exam test? Everyone gets unsure about their readiness for an exam once in a while, and to help you gauge how ready you are, we have compiled a quiz made up of some commonly asked questions. Do give it a shot and... see moreget to see if you need to find some more hours to study. see less

Tell us your name to personalize your report, certificate & get on the leaderboard!
2. A Term NOT used in the discussion of PERT/CPM analysis is

Explanation

This question asks for a term that is not used in the discussion of PERT/CPM analysis. PERT/CPM analysis is a project management technique used to plan and control the scheduling of tasks in a project. The terms activity, critical path, networks, and slack are all commonly used in the discussion of PERT/CPM analysis as they are key concepts in this methodology. However, feasibility is not directly related to PERT/CPM analysis. Feasibility refers to the assessment of whether a project is technically and economically viable. While feasibility may be considered in the overall project management process, it is not a specific term used in the discussion of PERT/CPM analysis.

Submit
3. Critical path tasks always have zero slack

Explanation

The statement is true because critical path tasks are the tasks that must be completed in order to complete a project on time. These tasks have no flexibility in terms of time and any delay in their completion will directly impact the overall project timeline. Therefore, critical path tasks always have zero slack, meaning there is no room for delay or slack in their scheduling.

Submit
4. It is possible for a project network to have more than one critical path?

Explanation

A critical path is the longest path in a project network that determines the minimum time required to complete the project. It consists of a series of dependent activities that must be completed in a specific order. In some cases, there may be multiple paths in the network that have the same duration and are equally critical. This means that if any activity on any of these paths is delayed, it will directly impact the project's overall completion time. Therefore, it is possible for a project network to have more than one critical path.

Submit
5. AON and AOA networks can both be used to depict any project network

Explanation

Both AON (Activity on Node) and AOA (Activity on Arrow) networks are commonly used in project management to depict project networks. AON uses nodes to represent activities and arrows to represent dependencies between activities. AOA, on the other hand, uses arrows to represent activities and nodes to represent events. Both types of networks can effectively illustrate the sequence of activities and their relationships, making them suitable for representing any project network. Therefore, the statement that AON and AOA networks can both be used to depict any project network is true.

Submit
6. The shortest time to complete a network is equal to the duration of the longest path through the network

Explanation

The statement is true because the longest path through a network represents the critical path, which is the sequence of activities that takes the longest time to complete. The duration of this critical path determines the shortest time required to complete the entire network. Therefore, the shortest time to complete a network is indeed equal to the duration of the longest path through the network.

Submit
7. Slack is

Explanation

Slack refers to the amount of time that a non-critical task can be delayed without causing a delay in the overall project. It is the flexibility or buffer time available for non-critical tasks. This means that if a non-critical task takes longer than initially planned, it will not impact the project's completion date as long as it is completed within the slack time. Therefore, the correct answer is "The amount of time a non-critical task can be delayed without making the project late."

Submit
8. Which of the following is NOT one of the basic rules to follow when developing project networks?

Explanation

The correct answer is "Complete backward pass first and then forward pass to calculate slack". This is not one of the basic rules to follow when developing project networks. The basic rules include ensuring that an activity cannot begin until all preceding activities have been completed, assigning activity identification numbers in a way that they are larger than any preceding activities, and ensuring that each activity has a unique identification number. Additionally, project networks flow from left to right, which is another basic rule to follow.

Submit
9. Reducing project duration 

Explanation

Reducing project duration is always more expensive because it usually requires additional resources, such as overtime pay, hiring extra staff, or utilizing expensive equipment to complete the project in a shorter time frame. This increased cost is necessary to speed up the project and meet the desired deadline. However, it is not the only factor to consider when deciding whether to reduce project duration, as other factors such as the project's importance, available resources, and potential risks should also be taken into account.

Submit
10. When it was originally developed, PERT used certain (deterministic) methods to estimate activity duration.

Explanation

PERT (Program Evaluation and Review Technique) was developed to handle uncertain and unpredictable activity durations. It uses probabilistic methods, such as the three-point estimation technique, which takes into account optimistic, pessimistic, and most likely estimates for activity durations. This allows for a more realistic and flexible approach in estimating project timelines. Therefore, the statement that PERT used deterministic methods to estimate activity duration is false.

Submit
View My Results

Quiz Review Timeline (Updated): Mar 21, 2023 +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 21, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Nov 06, 2019
    Quiz Created by
    Rachna
Cancel
  • All
    All (10)
  • Unanswered
    Unanswered ()
  • Answered
    Answered ()
The delaying of any activity on the critical path will delay the...
A Term NOT used in the discussion of PERT/CPM analysis is
Critical path tasks always have zero slack
It is possible for a project network to have more than one critical...
AON and AOA networks can both be used to depict any project network
The shortest time to complete a network is equal to the duration of...
Slack is
Which of the following is NOT one of the basic rules to follow when...
Reducing project duration 
When it was originally developed, PERT used certain (deterministic)...
Alert!

Advertisement