It is possible to estimate a project accurately be it when it comes to time, costs, and other resources. What do you know about project management? Do you have what it takes to be a good project manager? Well take up the quiz below and get to see just how much you know about it by taking up this great See morequiz. All the best!
Work-around
Change request for a corrective action
Transference
Risk assessment
Rate this question:
A change due to an error and omission in the initiation phase
A change due to an external event
A change due to an error or omission in the planning phase
A change due to a legal issue
Rate this question:
The project sponsor
The contractual agreement
Vendor(s)
The cause of the change request
Rate this question:
Defines the scope baseline for the project
Defines the requirements for each project within the organization
Defines the roles and responsibilities of each project team member
Defines the project deliverables and the work needed to create those deliverables
Rate this question:
It is mandatory to consult the plan before authorizing any change.
Project managers must document any changes before approving or declining them.
The project scope helps the project manager determine if a change is within or outside of scope.
The project plan and earned value management (EVM) work together to assess the risk involved with proposed changes.
Rate this question:
Project specifications
Approval requirements
Project constraints
Initially defined risks
Rate this question:
What is and is not included in the project
What is and is not included in the product
Changes to the project scope
Changes to the configuration management system
Rate this question:
Rolling Wave Planning
Analogous estimating
A template
Expert judgment
Rate this question:
Using expert judgement for the current project
Using a portion of the activity list from a previous project
Breaking down of project scope
Planning the immediate portions of the project in detail and the future project portions at a higher level
Rate this question:
Project Scope
Work packages
Planning packages
Product scope
Rate this question:
Activities that are not part of the project scope
Quality control activities
Activities to create the work packages
Physical terms, such as linear feet of pipe to be installed
Rate this question:
Scope verification process
Predecessor activities
Leads and lags
Geographic are where the work must take place
Rate this question:
Hard logic
Soft logic
Start-to-start relationship
Finish-to-finish relationship
Rate this question:
Lag
Lead
Finish-to-start
Start-to-finish
Rate this question:
Monday
Tuesday
Wednesday
Thursday
Rate this question:
Adding lag time between all project activities.
Adding lead time between all project activities
Adding additional project resources to the project work
Removing all unneeded project deliverables
Rate this question:
Analogous estimating
Parametric estimating
Organizational process assets
Bottom-up estimating
Rate this question:
You won't know until Howard actually does the work
105 hours
24 hours
35 hours
Rate this question:
Hard logic
Lag time
Lead time
Finish-to-start relationship
Rate this question:
Change control
Cost Control
WBS refinements
. Integrated change control
Rate this question:
Change control system
Schedule change control system
Integrated change control
Change control board
Rate this question:
Critical path method
Critical chain method
Schedule compression
Arrow on the node method
Rate this question:
Project ends early
Project ends on time
Project costs will increase
Project team morale will decrease
Rate this question:
Regression analysis
Bottom up estimating
Organizational process assets
Enterprise environmental factors
Rate this question:
Top-down estimating
Top-down budgeting
Bottom-up estimating
Parametric modeling
Rate this question:
A. It defines the methods to change the cost baseline.
It defines the methods to create the cost baseline.
It evaluates changes to the project costs based on changes to the project scope.
This is not a valid change control system.
Rate this question:
10 percent
$75,000
$25,000
Not enough information to know
Rate this question:
People doing the work create the estimates
Creates a more accurate estimate
More expensive to do than other methods
Less expensive to do than other methods
Rate this question:
$12,000
$217,000
$229,000
Zero, because project LB is worth more than WQQ
Rate this question:
Fixed costs
Parametric costs
Variable costs
Indirect costs
Rate this question:
Fixed costs
Parametric costs
Variable costs
Indirect costs
Rate this question:
100
89
.89
.79
Rate this question:
Project scope statement
Work breakdown structure
Project team
Expert judgement
Rate this question:
Constraint
Single source
Sole source
Oligopoly
Rate this question:
Team member recollections
Historical information
Project files
Cost-estimating templates
Rate this question:
Parametric
Analogous
Bottom-up
Top-down
Rate this question:
Analogous estimating
Bottom-up estimating
Commercial database
Procurement bid analysis
Rate this question:
Description of the schedule activity's project scope of work
Assumptions made
Constraints
Team members the project will utilize
Rate this question:
$192,500
$241,000
$309,000
$275,000
Rate this question:
Impossible to know-not enough information
$112,500
$637,500
$750,000
Rate this question:
Impossible to know-not enough information
$112,500
$637,500
$750,000
Rate this question:
Status report
Exceptions report
Forecast report
Lessons learned
Rate this question:
Cost of quality
Cost of poor quality
Sunk costs
Contingency allowance
Rate this question:
Quiz Review Timeline (Updated): Mar 21, 2023 +
Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.
Wait!
Here's an interesting quiz for you.