1.
Which one is not a type of constrain under Resource
Constrained schedule?
Correct Answer
A. Money
Explanation
In a resource-constrained schedule, the constraints typically refer to limitations on the availability or capacity of resources required for the project. Money is not considered a type of constraint in this context as it does not directly relate to the availability or capacity of resources. The constraints are usually related to the availability of people, materials, and equipment, which are essential for completing the project tasks.
2.
What is not used when creating Time-Phased budget?
Correct Answer
C. PBS
Explanation
When creating a Time-Phased budget, the PBS (Product Breakdown Structure) is not used. The OBS (Organizational Breakdown Structure) is used to define the organizational structure, the WBS (Work Breakdown Structure) is used to break down the project into manageable tasks, and the PBS is used to break down the project into deliverable products or components. Therefore, the correct answer is PBS.
3.
What are the impacts of Resource-Constrained
scheduling?
Correct Answer
A. Reduces Slack
Explanation
Resource-Constrained scheduling refers to a scheduling technique where the availability of resources is taken into consideration while creating a schedule. In this context, "slack" refers to the amount of time that a task can be delayed without affecting the overall project schedule. When resources are constrained, it means that there is limited availability of resources, which can lead to a reduction in slack. This is because tasks may need to be scheduled more tightly or closely together to accommodate the limited availability of resources. Therefore, the correct answer is that Resource-Constrained scheduling reduces slack.
4.
When splitting activities is a preferred technique?
Correct Answer
D. Both B and C
Explanation
When splitting activities is a preferred technique, it is because both B and C are true. Splitting activities helps in getting a better project schedule by breaking down complex tasks into smaller, more manageable ones. This allows for better planning, tracking, and resource allocation. Additionally, splitting activities can also help increase resource utilization by distributing workload more evenly among team members and maximizing their efficiency.
5.
What is not the limiting assumption when we engage in resource
allocation technique?
Correct Answer
C. Resources can easily be transferred from one activity to another
Explanation
The correct answer is "Resources can easily be transferred from one activity to another." This means that when engaging in resource allocation technique, it is not assumed that resources can be easily moved or shifted from one activity to another.
6.
What is the main function of Time-Phased Budget?
Correct Answer
B. To evaluate performance of the project
Explanation
The main function of a Time-Phased Budget is to evaluate the performance of the project. This type of budget allows for the tracking and monitoring of project expenses over time, comparing the actual costs with the planned budget. By evaluating the performance of the project through the Time-Phased Budget, project managers can identify any variances or deviations from the planned budget and take necessary actions to address them. This helps in ensuring that the project stays on track and meets its financial objectives.
7.
Which one is the correct assumption?
Correct Answer
C. Resource constrains can alter technical constrains
Explanation
The correct assumption is that resource constraints can alter technical constraints. This means that if there are limitations or restrictions on the available resources for a project, such as budget, manpower, or equipment, it can have an impact on the technical aspects of the project. For example, if there is a shortage of skilled workers or a limited budget, it may require the project manager to find alternative solutions or make adjustments to the technical requirements of the project in order to work within the resource constraints.
8.
What is the main focus of the time-constrained
project?
Correct Answer
A. Resource utilization
Explanation
The main focus of a time-constrained project is resource utilization. This means that the project team needs to effectively allocate and manage resources such as manpower, materials, and equipment to ensure that they are being used efficiently and effectively to meet project deadlines and objectives. By optimizing resource utilization, the project can maximize productivity and minimize waste, ultimately leading to successful project completion within the given time constraints.
9.
What is the main focus of the
resource-constrained project?
Correct Answer
B. Minimize time delay
Explanation
The main focus of a resource-constrained project is to minimize time delay. This means that the project is primarily concerned with completing tasks and achieving milestones within the allocated time frame. The project managers and team members will prioritize efficient time management and strive to eliminate any unnecessary delays or bottlenecks that could hinder progress. By minimizing time delay, the project can stay on schedule and meet its objectives in a timely manner.
10.
What is the default time that is used in resource
smoothing process?
Correct Answer
A. Earliest Start
Explanation
The default time used in the resource smoothing process is the earliest start time. This refers to the earliest possible time that a task can begin without causing any delays or conflicts with other tasks or resources. It helps in optimizing the scheduling of resources and ensuring that tasks are completed efficiently.