Below is a project management professional test. It is expected that every manager in an organization has some information on project management and just to ensure that they can complete tasks using available resources and deliver as planned. How about you go through each question and get to see how knowledgeable you are on project management as a whole.
Facilitated workshops
Focus Groups
Meetings
Group decision making techniques
Rate this question:
Reviewing the risk Register
Clarifying the role and responsibilities of all team members
Reviewing the project status
Identifying the remaining resource requirements
Rate this question:
Formal Acceptance
Archiving Project Records
Analysis of Project Success
Performing Cost Benefit Analysis
Rate this question:
Risk
Change Request
Scope Creep
Work Performance data
Rate this question:
To provide quality control
To ensure quality planning
To create a benchmark
To perform quality assurance
Rate this question:
Keep quiet about the situation since you know you can make objective decisions.
Do not participate in the decision of awarding the contract.
Notify the group awarding the contract of a possible conflict.
Document all decisions you make in relation to this agency's part of the project.
Rate this question:
Product review
Audit
Walkthrough
Stage-gate
Rate this question:
Stakeholder influence, risk, and uncertainty are highest at the start of IT Infrastructure Project
Ability of the stakeholders to influence final characteristics of IT Infrastructure Project increases as the project progresses.
The project life cycle determines which transitional actions at the beginning and end of the project are included, so that the project can be linked to the ongoing operations of the performing organization.
Stakeholder influence, risk, and uncertainty decrease as the IT Infrastructure Project progresses.
Rate this question:
Analogous estimating
Three point estimate
Historical relationships
Parametric estimating
Rate this question:
Loyalty to the project
Home for the team members after the project is completed
Effective communication
Team is only reported to Project Manager
Rate this question:
Create Human Resource Plan
Create Project Management Plan
Create Communications Management Plan
Create Stakeholder Register
Rate this question:
Default of the buyer
Default of the seller
Mutual agreement of the parties
Any of the above reasons
Rate this question:
Closed procurements.
Formal confirmation of deliverable acceptance.
The request for proposal (RFP) or request for quotation(RFQ), and the seller's working proposal.
Lessons learned documentation.
Rate this question:
Project manager creates the project management plan based on inputs from the sponsor and the functional manager.
Sponsor creates the project management plan based on inputs from the project manager and the functional manager.
Project manager creates the project management plan based on inputs from the team.
Sponsor creates the project management plan based on inputs from all the stakeholders.
Rate this question:
Finish-to-finish
Start-to start
Finish-to-start
Start-to-finish
Rate this question:
Total float can affect the calculated early start and finish dates
The flexibility of schedule is facilitated by activity total float
Networks can have only one critical path
Networks may have multiple near critical paths
Rate this question:
Staffing pool description
Staffing management plan
Responsibility assignment matrix (RAM)
Organization matrix
Rate this question:
Corrective Action
Defect repair
Preventive action
Deliverable
Rate this question:
Project Sponsor
Project team
PMO Manager
Project Manager
Rate this question:
Execution
Controlling
Coordination
Monitoring
Rate this question:
Reduction or deletion of travel expenses
Ability to add experts to the project team regardless of geographical location
Forming project teams of resources who work different shifts
Ability to make use of local HR policies
Rate this question:
Penalty
Referent
Expert
Legitimate
Rate this question:
PMO manages major program scope changs
PMO manages the methodologies, and standards
PMO manages the interdependencies among projects at the enterprise level
PMO controls the assigned project resources to best meet project objectives
Rate this question:
Finalizing Open Claims
Project Document Archiving
Lesson Learned Documentation
Obtain formal acceptance of the project scope from the customer
Rate this question:
Sellers / Business partners
Customers / Users
Portfolio managers / Portfolio review board
Project Teams
Rate this question:
Time and Material Price
Vendor Bid Analysis Price
Fixed Price
Independent Estimate.
Rate this question:
Configuration management system
Variance Analysis
Re-planning
Earned Value Spreadsheets
Rate this question:
Project A with an opportunity cost of $ 200,000
Project B with a benefit-cost ratio of 0.50
Project C with an IRR of -5%
Project D with NPV of $ 150,000
Rate this question:
Plan Quality
Plan Risk Responses
Perform Qualitative Analysis
Define Activities
Rate this question:
$400,000
$600,000
$450,000
$200,000
Rate this question:
Manage Project Team process handles the conflicts if they arise
Develop Project Team process improves the trust and agreement among team members
Manage Project Team process tracks the team member performance
Develop Project Team process analyze the impact of unavailability of key team member
Rate this question:
Project Sponsor
Project management team
Project Manager
Project Team
Rate this question:
Disparate tools and technologies
Cultural differences
Local HR policies
Different time zones
Rate this question:
Weak Matrix
Balanced Matrix
Projectized
String Matrix
Rate this question:
Sponsor is responsible for the funding for a new project's conceptual study
Sponsor champions the project
Sponsor can authorize changes in scope
Sponsor is the only person who can write the Project Charter
Rate this question:
It is the document that formally authorizes a project.
Provides authority to the project manager.
It is issued by a project initiator or sponsor external to the project organization, at a level that is appropriate to funding the project
It is used primarily to request bids for different phases of a project.
Rate this question:
Checklist
Operational definition
Quality management plan
Quality metrics
Rate this question:
15
23
36
Cannot be determined from the given information
Rate this question:
Monte Carlo simulations are not a standard methodology used in the company for risk quantification.
The quantitative value of identified risks is too high.
You have not performed risk audits as part of your project.
You have not conducted an interview with the project stakeholders and subject matter experts.
Rate this question:
In a fixed-price, incentive-fee contract, there is no incentive for the seller to decrease costs.
In a fixed-price contract, there is highest risk to the seller and lowest risk to the buyer.
Fixed price with redetermination retroactive contracts allow for adjusting of contract price after performance has been completed.
Fixed price with economic price adjustment allows for price increases if the contract is for multiple years.
Rate this question:
Project Management Information System
Critical Path Method
Work Authorization System
Work Breakdown Structure
Rate this question:
Run Chart
Cause an Effect Diagram
Control Chart
Ishikawa diagram
Rate this question:
Devil`s Advocate
Dominator
Challenger
Aggressor
Rate this question:
Forcing
Withdrawal
Compromise
Confrontations
Rate this question:
Project Status Presentation
Risk Auditing
Calculating Earned Value Management
Performance appraisals
Rate this question:
Bidder conference
Independent estimates
Inspections and Audits
Proposal evaluation technique
Rate this question:
Fast track the project to ensure that the project schedule is not delayed.
Determine how much float is available in that task.
Try to get additional supplies from an alternate location as soon as possible.
Take corrective action to minimize the impact of delay.
Rate this question:
Develop Project Management Plan
Identify a project manager for the project
Document Business Need
Identify the stakeholders
Rate this question:
Quiz Review Timeline (Updated): Mar 20, 2023 +
Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.
Wait!
Here's an interesting quiz for you.