1.
You have received an order confirmation from a vendor.What do you have to do before you can enter the confirmed delivery date and confirmedquantity in a purchase order item?p.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}
Correct Answer
C. Use a confirmation control key in the relevant purchase order item.
Explanation
Before entering the confirmed delivery date and confirmed quantity in a purchase order item, you need to use a confirmation control key in the relevant purchase order item. This control key helps in managing the confirmation process and ensures that the vendor's confirmation is received and recorded accurately. It allows for better tracking and monitoring of the order fulfillment and helps in maintaining accurate inventory records.
2.
Where do you define a fixed vendor for a specific period in time?p.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}
Correct Answer
C. In the source list at plant level
Explanation
In the source list at plant level, you define a fixed vendor for a specific period in time. The source list is a list of approved vendors for a particular material at a specific plant. By specifying a vendor in the source list, you ensure that procurement of the material from that vendor is prioritized during the specified period. This allows for better control and management of the supply chain by ensuring a consistent and reliable source of materials from a specific vendor for a specific period of time.
3.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}What are characteristics of material valuation at the moving average price? (Choose two)
Correct Answer(s)
A. If you book a subsequent debit for a quantity higher than the total quantity of valuated
stock then a price difference posting is generated.
C. The moving average price is equal to the total value divided by total quantity of valuated
stock.
Explanation
If a subsequent debit is booked for a quantity higher than the total quantity of valuated stock, a price difference posting is generated. This means that if there is an increase in the quantity of stock beyond what was initially valued, there will be a price difference between the moving average price and the new price. The moving average price is calculated by dividing the total value of the stock by the total quantity of valuated stock. This ensures that the average price is adjusted based on the value and quantity of the stock.
4.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}Which value of the creation indicator is shown in the tab Contact person when you create apurchase requisition manually?
Correct Answer
C. Realtime
Explanation
When creating a purchase requisition manually, the value of the creation indicator shown in the tab Contact person is "Realtime". This indicates that the purchase requisition is being generated in real-time, meaning that it is immediately processed and sent to the appropriate contact person for further action. This allows for efficient and timely communication and ensures that the purchase requisition is handled promptly.
5.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}What does an account group control when you create vendor master records?(Choosethree)
Correct Answer(s)
A. The partner determination procedure
B. The definition whether the vendor master record is a one-time account or not
C. The possible data retention levels
Explanation
When creating vendor master records, an account group controls the partner determination procedure, which determines the partners involved in business transactions with the vendor. It also controls whether the vendor master record is a one-time account or not, allowing for different treatment of one-time vendors. Additionally, the account group determines the possible data retention levels, specifying the length of time for which data is stored.
6.
Which procurement elements can be created in Purchasing with automatic purchase order generation? (Choose two)p.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}
Correct Answer(s)
B. Contract release orders
C. Purchase orders
7.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}Which are the configuration options that can be defined to post unplanned deliverycosts? (Choose three)
Correct Answer(s)
A. The unplanned delivery costs are to be posted to separate G/L accounts
B. The unplanned delivery costs are to be distributed prorated to calculated invoice items
C. The unplanned delivery costs can be posted by rules defined within a BAdI
Explanation
The correct answer is that the configuration options that can be defined to post unplanned delivery costs are:
1) The unplanned delivery costs are to be posted to separate G/L accounts. This means that the costs will be recorded in different general ledger accounts for better tracking and analysis.
2) The unplanned delivery costs are to be distributed prorated to calculated invoice items. This means that the costs will be allocated proportionally to the different invoice items based on their calculated values.
3) The unplanned delivery costs can be posted by rules defined within a BAdI. This means that specific rules can be defined using Business Add-Ins (BAdIs) to determine how the costs should be posted.
8.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}What can you define for a movement type in Customizing? (Choose three)
Correct Answer(s)
A. The movement type short text and the reasons for movement
B. The indicator for automatic creation of storage location data in the material master
record at the time of the first goods receipt
E. The account modification for transactions and events with active account grouping in the
table of account keys
Explanation
The movement type short text and the reasons for movement are defined in Customizing to provide a clear description and explanation of the purpose of each movement type. The indicator for automatic creation of storage location data in the material master record at the time of the first goods receipt is also defined in Customizing to automate the process of creating storage location data when goods are received. The account modification for transactions and events with active account grouping in the table of account keys is defined in Customizing to determine how financial accounts are modified based on the movement type.
9.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}Which of the following are SAP Solution Manager usage scenarios? (Choose two)
Correct Answer(s)
B. Implementation of SAP solutions
D. Service desk
Explanation
The correct answer is "Implementation of SAP solutions" and "Service desk". These are two of the main usage scenarios of SAP Solution Manager. The Solution Manager is used to manage and implement SAP solutions, ensuring a smooth and efficient implementation process. It also includes a service desk functionality, which allows users to log and track issues, incidents, and service requests. This helps to improve user productivity and provide support and assistance to users.
10.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}In a vendor master record, you enter a different vendor as a partner with the partner role(partner function) of Invoicing Party.p.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}What is the function of this partner role in Materials Management?
Correct Answer
B. This partner is proposed when you enter an invoice with reference to purchase orders.
Explanation
The partner role of Invoicing Party in the vendor master record is proposed when entering an invoice with reference to purchase orders. This means that when creating an invoice, the system suggests this partner as the invoicing party based on the purchase order information. This helps streamline the invoicing process and ensures that the correct partner is selected for invoicing purposes.
11.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}Which criteria can you select to create the invoices automatically for invoicingplans? (Choose three)
Correct Answer(s)
A. Company code
B. Vendor
D. Plant
Explanation
The criteria that can be selected to create the invoices automatically for invoicing plans are Company code, Vendor, and Plant. These three factors are important in determining the specific details and requirements for invoicing. The company code helps identify the specific company or organization for which the invoices are being created. The vendor refers to the specific supplier or vendor from whom the goods or services were purchased. The plant represents the specific location or facility where the goods or services were received or used. By selecting these criteria, the system can generate invoices automatically based on the relevant information for each transaction.
12.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}During net requirements calculation of a material planned with reorder point planning, the warehouse stock available for MRP is the sum of the plant stock and the on-order stock.Which of the following documents belong to the on-order stock? (Choose three)
Correct Answer(s)
A. Purchase orders
C. Fixed purchase requisitions
D. Firm planned orders
Explanation
The on-order stock includes purchase orders, fixed purchase requisitions, and firm planned orders. Purchase orders are documents that are created to request the purchase of materials from suppliers. Fixed purchase requisitions are requests for materials that have been predetermined and are not subject to change. Firm planned orders are orders that have been confirmed and are in the process of being executed. These three documents represent materials that have been ordered but have not yet been received or fulfilled, making them part of the on-order stock.
13.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}You have an open purchase order for a valuated material.What changes can you make to the master data here? (Choose two)
Correct Answer(s)
B. Material group in the material master from material group 1 to material group 2
C. Fixed vendor in the source list from vendor A to vendor B
Explanation
You can change the material group in the material master from material group 1 to material group 2. This change will affect how the material is classified and grouped within the system. Additionally, you can change the fixed vendor in the source list from vendor A to vendor B. This change will update the vendor information for the purchase order, specifying a different vendor from whom to procure the material.
14.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}When you use the collective release, which indicators do you have to set to select allpurchase requisitions that you can release if you do not know if the purchase requisitionsrequire overall release or per item release? (Choose three)
Correct Answer(s)
A. Requisitions for overall release
D. Requisitions for item wise release
E. Release prerequisite fulfilled
Explanation
To select all purchase requisitions that can be released using the collective release, regardless of whether they require an overall release or per item release, you need to set the indicators for "Requisitions for overall release," "Requisitions for item wise release," and "Release prerequisite fulfilled." These indicators ensure that all types of purchase requisitions are included in the selection process, allowing for a comprehensive release of requisitions.
15.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}What information does the purchasing info record contain? (Choose three)
Correct Answer(s)
A. The planned delivery time
B. The vendor material number
E. The tolerance limits for underdelivery and overdelivery
Explanation
The purchasing info record contains information such as the planned delivery time, which specifies the expected time for the material to be delivered. It also includes the vendor material number, which is a unique identifier assigned by the vendor to the material. Additionally, the purchasing info record includes the tolerance limits for underdelivery and overdelivery, which define the acceptable range of variation in the quantity of the material that can be delivered.
16.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}What happens when you cancel invoices in Logistics Invoice Verification? (Choose two)
Correct Answer(s)
A. The system generates a credit memo.
C. The system creates an accounting document.
Explanation
When you cancel invoices in Logistics Invoice Verification, the system generates a credit memo and creates an accounting document. Cancelling an invoice means reversing the previously recorded invoice, and this process involves generating a credit memo to offset the original invoice. Additionally, cancelling an invoice also requires creating an accounting document to reflect the reversal of the financial transaction.
17.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}Which of the following are characteristics of a service purchase order? (Choose three)
Correct Answer(s)
B. A limit value for unplanned services can be specified.
C. An account assignment is mandatory.
E. The item category is D (service).
Explanation
The characteristics of a service purchase order include the ability to specify a limit value for unplanned services, mandatory account assignment, and the item category being designated as D for service. These features ensure that the purchase order accurately reflects the required service specifications, allows for budget control by setting a limit for unplanned services, and ensures proper financial tracking and accountability through mandatory account assignment. The item category being designated as D distinguishes the purchase order as specifically related to a service rather than a physical product.
18.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}You make transfer postings for valuated materials.For which postings are no accounting documents generated?
Correct Answer
C. Transfer posting to stock with subcontractor
Explanation
Transfer posting to stock with subcontractor does not generate accounting documents because it involves transferring materials to a subcontractor for further processing or assembly. The subcontractor is responsible for the cost accounting and financial postings associated with the subcontracting process, so no accounting documents are generated during the transfer posting.
19.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}Which of the following are provided by enhancement packages?(Choose two)
Correct Answer(s)
B. Functionality
C. Simplification
Explanation
Enhancement packages provide additional functionality and simplify processes in a software system. They are designed to enhance the existing features and capabilities of the software, making it more efficient and user-friendly. Support packages, on the other hand, are used to fix bugs and provide technical support for the software. Accelerators are tools or templates that help speed up the implementation process. Therefore, the correct answer is functionality and simplification, as these are the two main benefits provided by enhancement packages.
20.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}Which of the following elements must you consider for calculating the reorder point inplanning? (Choose three)
Correct Answer(s)
A. Replenishment lead time
B. Previous consumption
D. Safety stock
Explanation
To calculate the reorder point in planning, three elements that must be considered are replenishment lead time, previous consumption, and safety stock. Replenishment lead time refers to the time it takes for an order to be delivered after it has been placed. Previous consumption helps in determining the average rate at which the inventory is being used. Safety stock is the extra stock held to mitigate any unexpected fluctuations in demand or delays in replenishment. Considering these three elements is crucial for ensuring that sufficient inventory is available to meet customer demand and avoid stockouts.
21.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}Which of the following statements apply to the SAP Enterprise Portal? (Choose two)
Correct Answer(s)
A. The portal enables you to access SAP ERP without having the SAP GUI installed on
your computer
B. The portal is a uniform framework for accessing company data from different systems.
Explanation
The first statement is correct because the SAP Enterprise Portal allows users to access SAP ERP without needing to install the SAP GUI on their computer. This provides flexibility and convenience for users.
The second statement is also correct because the SAP Enterprise Portal serves as a uniform framework for accessing company data from different systems. It provides a centralized platform for users to access and manage data from various sources, improving efficiency and productivity.
22.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}How can you clear a balance on the GR/IR clearing account if the invoiced quantity ishigher than the delivered quantity? (Choose three)
Correct Answer(s)
B. You can cancel the invoice and post an invoice with the delivered quantity.
C. You can clear the GR/IR clearing account manually.
D. You can return the extra goods to the vendor.
Explanation
If the invoiced quantity is higher than the delivered quantity, one possible solution is to cancel the invoice and post a new invoice with the correct delivered quantity. This will ensure that the invoiced quantity matches the actual quantity received. Additionally, the GR/IR clearing account can be cleared manually to reconcile the balance. Finally, returning the extra goods to the vendor can also help to clear the balance on the GR/IR clearing account.
23.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}What can you specify when you assign a message schema to an application inPurchasing?
Correct Answer
C. That a new message determination process is initiated for change messages
Explanation
When you assign a message schema to an application in Purchasing, it means that a new message determination process is initiated for change messages. This implies that when there are changes in the purchasing process, a new message determination process is triggered to determine the appropriate messages to be sent. This ensures that the correct messages are generated and sent based on the changes made in the purchasing process.
24.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}At which of the following organizational levels can you set the valuation area? (Choose two)
Correct Answer(s)
B. Plant
D. Company code
Explanation
You can set the valuation area at the plant and company code levels. The valuation area is a key organizational level in SAP that determines how inventory is valued. At the plant level, you can define valuation areas specific to each physical location or production facility. At the company code level, you can define valuation areas that apply to the entire company. Both levels allow for separate valuation settings and reporting, providing flexibility in managing inventory valuation.
25.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}What is the status of an inventory document item for which a recount has been initiated?
Correct Answer
B. Counted, Recounted
Explanation
When a recount is initiated for an inventory document item, the status of the item is changed to "Counted, Recounted". This means that the item has been counted initially and then recounted to ensure accuracy. By including both "Counted" and "Recounted" in the status, it indicates that the item has gone through the counting process twice. This helps to ensure that any discrepancies or errors in the initial count are identified and corrected.
26.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}Which assignments can be made for the organizational object PurchasingOrganization? (Choose two)
Correct Answer(s)
A. Purchasing Organization can be assigned to only one company code.
B. Purchasing Organization must be assigned to one or more plants.
Explanation
The correct answer is that the Purchasing Organization can be assigned to only one company code and must be assigned to one or more plants. This means that a purchasing organization can only be associated with one company code, indicating that it is responsible for procurement activities within that specific company. Additionally, it must be assigned to one or more plants, indicating that it is responsible for procurement activities within those specific manufacturing or production facilities.
27.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica} p.p2 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica; color: #ff2600} p.p3 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica; color: #29618d} p.p4 {margin: 0.0px 0.0px 0.0px 0.0px; font: 11.0px Helvetica; color: #cf1c00} span.s1 {color: #8d1000} span.s2 {font: 12.0px Helvetica; color: #000000}Your vendors don't always send the exact order quantities. You therefore allow tolerances for underdeliveries and overdeliveries. Where can you define defaults for these tolerances?
Correct Answer
A. Purchasing value keys
Explanation
Purchasing value keys are used to define defaults for various purchasing parameters, including tolerances for underdeliveries and overdeliveries. These keys allow you to set specific values for different vendors or materials, ensuring that the system automatically applies the correct tolerances based on the specific purchasing scenario. By defining these defaults in the purchasing value keys, you can streamline the procurement process and ensure consistency in handling underdeliveries and overdeliveries.
28.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}What can be triggered by a goods receipt posting? (Choose two)
Correct Answer(s)
B. The value of the stock account is updated in the G/L account
C. Stock quantity is updated
Explanation
When a goods receipt posting is made, two things can be triggered. Firstly, the value of the stock account is updated in the G/L account. This means that the accounting records are updated to reflect the increase in the value of the stock. Secondly, the stock quantity is updated. This means that the system is updated with the new quantity of stock that has been received. These two actions ensure that the inventory records are accurate and up to date.
29.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}Which functions are provided by the Service Desk in SAP Solution Manager? (Choosethree)
Correct Answer(s)
A. Search and import of SAP Notes
C. Interface to SAP Support
E. Central management of support messages
Explanation
The Service Desk in SAP Solution Manager provides three functions: search and import of SAP Notes, interface to SAP Support, and central management of support messages. These functions allow users to search for and import SAP Notes for issue resolution, communicate with SAP Support for assistance, and centrally manage support messages for efficient tracking and resolution of issues.
30.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}You want to change the valuation class of a material. The system does not permit thischange.Which of the following answers describe possible reasons? (Choose three)
Correct Answer(s)
B. Outstanding purchase orders that have not been deleted still exist for the material
C. Outstanding production orders that have not been deleted still exist for the material
E. There is valuated stock for the material in the current period
Explanation
Possible reasons for not being able to change the valuation class of a material include the existence of outstanding purchase orders and production orders that have not been deleted for the material. Additionally, if there is valuated stock for the material in the current period, it may prevent the change from being made.
31.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}You post a goods receipt into stock for a purchase order item for which the indicator Freeitem is set. The material has a material master record and a material type for which thequantity and value are updated. The price control parameter has the value Standard pricefor the material.To which general ledger accounts are the postings made? (Choose two)
Correct Answer(s)
B. Price difference account
D. Stock account
Explanation
The postings are made to the Price difference account and the Stock account. When a goods receipt is posted for a purchase order item with the Freeitem indicator set, the system updates the quantity and value of the material in the material master record. The Price difference account is used to record any differences between the standard price of the material and the actual price at which it was received. The Stock account is used to record the increase in the quantity of the material in stock.
32.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}Which entries are mandatory in a purchase order item for service? (Choose two)
Correct Answer(s)
A. Account assignment category
D. Item category Service
Explanation
The two mandatory entries in a purchase order item for service are the account assignment category and the item category service. The account assignment category is necessary to determine how the costs of the service will be allocated, such as to a cost center or a project. The item category service is required to indicate that the purchase order item is for a service rather than a physical material. The material number and storage location are not mandatory for service items.
33.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}You transfer material between two plants. The goods issue in the delivering plant is alreadybooked. During the transport process, some parts are damaged and the delivering plant isresponsible for the transportation.How can you post this scrapping?
Correct Answer
D. You reverse the stock removal in the issuing plant and post the scrapping there.
34.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}Which of the following are characteristics of an invoice plan? (Choose two)
Correct Answer(s)
B. An account assignment is required
D. Only a non-valuated goods receipt is possible
Explanation
An invoice plan requires an account assignment, which means that each line item on the invoice needs to be assigned to a specific cost center or general ledger account. Additionally, an invoice plan only allows for a non-valuated goods receipt, meaning that the goods are not assigned a value until the invoice is received and processed.
35.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}A release strategy for purchase requisition is defined as follows:p.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}1 Account Assignment Category (blank)1 Plant 1000 or 11001 Purchasing Group 0011 Item value > EUR 400p.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}For which purchase requisition items (see attached graphic) will this strategy bedetermined? (Choose two)
Correct Answer(s)
B. 10
D. 20
Explanation
The release strategy for purchase requisition is determined based on certain criteria such as account assignment category, plant, purchasing group, and item value. In this case, the account assignment category is blank, the plant is either 1000 or 1100, the purchasing group is 001, and the item value is greater than EUR 400. Based on these criteria, the purchase requisition items that meet this strategy are 10 and 20.
36.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}Which of the following influence the field selection for the material master? (Choose three)
Correct Answer(s)
A. Material type
C. Industry sector
D. Plant
Explanation
The field selection for the material master is influenced by the material type, industry sector, and plant. The material type determines the basic attributes and behavior of the material, such as whether it is a finished product or a raw material. The industry sector determines the specific requirements and regulations for materials in a particular industry. The plant determines the specific location or facility where the material is stored or produced. These three factors play a crucial role in determining the field selection for the material master.
37.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}How can you simplify and accelerate the material master data maintenance? (Choosethree)
Correct Answer(s)
B. You can use a special mass change function to change several material master records
at the same time.
C. You can let the system automatically add the storage location data to the material
master record with the first goods receipt posting.
D. You can preset the views that you are responsible for in the dialog box Select Views in
the transactions you use to maintain the material master data.
Explanation
The correct answer options explain three ways to simplify and accelerate material master data maintenance. First, using a special mass change function allows for simultaneous changes to multiple material master records. Second, the system can automatically add storage location data to the material master record when the first goods receipt is posted. Lastly, presetting the views in the Select Views dialog box allows for a more efficient maintenance process by only displaying the relevant views for the user responsible for maintaining the material master data.
38.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}You post a goods receipt for a purchase order item. The material has the material typeNLAG (non-stock material).What are the effects? (Choose two)
Correct Answer(s)
C. The value is posted to a consumption account.
D. The quantity is posted to consumption.
Explanation
When you post a goods receipt for a purchase order item with a material type of NLAG (non-stock material), the effects are that the value is posted to a consumption account and the quantity is posted to consumption. This means that the value of the non-stock material is recorded in the consumption account, and the quantity of the material is also recorded as consumed. This helps in tracking the usage and cost of non-stock materials in the inventory management system.
39.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}Which control parameters can you set on the initial screen of the planning run? (Choosetwo)
Correct Answer(s)
B. Planning mode
C. Processing key
Explanation
On the initial screen of the planning run, you can set the control parameters for the planning mode and the processing key. The planning mode determines how the planning run will be executed, such as net requirements calculation or regenerative planning. The processing key defines the type of planning run to be performed, such as creating planned orders or purchase requisitions. The MRP controller and firming horizon are not control parameters that can be set on the initial screen of the planning run.
40.
P.p1 {margin: 0.0px 0.0px 0.0px 0.0px; font: 12.0px Helvetica}In Customizing for Logistics Invoice Verification, the following values are defined for thestochastic block: Thresholdvalue:10000Percentage:40You enter an invoice with a value of 7500.What is the probability that the invoice will be blocked stochastically?
Correct Answer
A. 30%
Explanation
The probability that the invoice will be blocked stochastically can be calculated by comparing the invoice value (7500) to the threshold value (10000) defined in the stochastic block. Since the invoice value is less than the threshold value, the invoice will not be blocked stochastically. Therefore, the probability is 0%, which is not one of the given answer choices. Hence, the correct answer is not provided.