Project Scheduling Questions And Answers

Approved & Edited by ProProfs Editorial Team
The editorial team at ProProfs Quizzes consists of a select group of subject experts, trivia writers, and quiz masters who have authored over 10,000 quizzes taken by more than 100 million users. This team includes our in-house seasoned quiz moderators and subject matter experts. Our editorial experts, spread across the world, are rigorously trained using our comprehensive guidelines to ensure that you receive the highest quality quizzes.
Learn about Our Editorial Process
| By Team418b
T
Team418b
Community Contributor
Quizzes Created: 2 | Total Attempts: 18,829
Questions: 10 | Attempts: 10,809

SettingsSettingsSettings
Project Scheduling Questions And Answers - Quiz

How well do you know about project scheduling? Take this quiz on project scheduling questions and answers. Here is a practice test on project scheduling in project management, which will help you analyze yourself. When you develop a project, you must allocate resources to meet your targets and the timeframe you want to accomplish. With this quiz, you will learn how to schedule your activities when it comes to carrying out a successful project. Don't forget to share the quiz with your friends. All the best!


Questions and Answers
  • 1. 

    How is float calculated?

    • A.

      Latest finish date – duration

    • B.

      Latest start date – earliest start date

    • C.

      Earliest start date + duration

    • D.

      None of the above

    Correct Answer
    B. Latest start date – earliest start date
    Explanation
    The correct answer is "Latest start date - earliest start date". This calculation determines the amount of time between the earliest possible start date and the latest possible start date for a task. By subtracting the earliest start date from the latest start date, we can determine the flexibility or float in the schedule. This float represents the amount of time that a task can be delayed without affecting the overall project timeline.

    Rate this question:

  • 2. 

    What does Goldratt’s theory of constraints focus on?

    • A.

      Pouring resources into minimizing the major constraints facing a project.

    • B.

      Pouring resources into activities on the critical path.

    • C.

      Estimating the duration of tasks.

    • D.

      None of the above

    Correct Answer
    A. Pouring resources into minimizing the major constraints facing a project.
    Explanation
    Goldratt's theory of constraints focuses on identifying and addressing the major constraints that limit the overall performance of a project. By pouring resources into minimizing these constraints, the theory aims to optimize the project's efficiency and effectiveness. This approach helps to ensure that the project's critical path is not hindered by bottlenecks or limitations, ultimately leading to improved project outcomes.

    Rate this question:

  • 3. 

    What are the limitations of using software to help plan projects?

    • A.

      It might add to the confusion of the project team and waste time, particularly in multi-national teams.

    • B.

      Improves visibility of planning among the project team.

    • C.

      More difficult to use when there are large numbers of tasks and resources.

    • D.

      None of the above

    Correct Answer
    A. It might add to the confusion of the project team and waste time, particularly in multi-national teams.
    Explanation
    Using software to help plan projects can have limitations, such as adding to the confusion of the project team and wasting time, especially in multi-national teams. This is because different team members may have varying levels of familiarity and comfort with the software, leading to miscommunication and inefficiencies. Additionally, the complexity of managing large numbers of tasks and resources can make it more difficult to effectively use the software for planning purposes.

    Rate this question:

  • 4. 

    Which of the following is the preferred way of ‘chunking’ a project to create a work breakdown structure?

    • A.

      Activity breakdown.

    • B.

      Functional breakdown.

    • C.

      Physical breakdown.

    • D.

      All of the above are acceptable ways of chunking any project.

    • E.

      None of the above are acceptable breakdowns in every case; the best way will depend on the project.

    Correct Answer
    E. None of the above are acceptable breakdowns in every case; the best way will depend on the project.
    Explanation
    The correct answer states that none of the given options are acceptable breakdowns in every case, and the best way to chunk a project and create a work breakdown structure will depend on the specific project. This means that there is no one-size-fits-all approach to project chunking, and the preferred method will vary based on the unique requirements and characteristics of each project.

    Rate this question:

  • 5. 

    In which sort of project is the use of a Gantt chart most appropriate?

    • A.

      Projects in which the use of resources must be carefully monitored.

    • B.

      Projects with few activities and resources involved.

    • C.

      Projects where the time periods involved are very short.

    • D.

      Projects with many activities involved.

    Correct Answer
    B. Projects with few activities and resources involved.
    Explanation
    A Gantt chart is a visual representation of a project schedule, displaying the start and end dates of tasks and their dependencies. It is most appropriate for projects with few activities and resources involved because it allows for a clear and simple overview of the project timeline. With fewer activities and resources, the chart can be easily understood and managed, making it an effective tool for monitoring and tracking progress. However, for projects with many activities or complex resource allocation, a more detailed project management tool may be needed.

    Rate this question:

  • 6. 

    In a network diagram, if the activity in question has several preceding activities on which it is dependent, which earliest start time should be used for the activity in question?

    • A.

      The earliest of the earliest start times applicable should be used.

    • B.

      The latest of the earliest start times applicable should be used.

    • C.

      The mean of all of the possible earliest start times applicable should be used.

    • D.

      None of the above

    Correct Answer
    B. The latest of the earliest start times applicable should be used.
    Explanation
    When an activity in a network diagram has several preceding activities on which it is dependent, the earliest start time for each of these activities is calculated. The earliest start time for the activity in question should be determined by considering the latest of these earliest start times. This ensures that the activity can start as soon as all the preceding activities are completed, allowing for maximum efficiency in the project schedule.

    Rate this question:

  • 7. 

    Only delays in tasks on the critical path can delay a project as a whole.

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    Delays in tasks on the critical path can certainly have a significant impact on the project timeline, but they are not the only factor that can delay a project as a whole. Other factors such as resource constraints, unexpected events, dependencies between non-critical tasks, and poor project management can also contribute to project delays. Therefore, it is not accurate to say that only delays in tasks on the critical path can delay a project as a whole.

    Rate this question:

  • 8. 

    Which explanation best describes what the term ‘crashing’ a project means?

    • A.

      Abandoning a project when using a stage-gate approach.

    • B.

      Injecting further funds into a project.

    • C.

      Reducing the time spans on critical activities to complete the project in less time.

    • D.

      Failure of a project due to the incompetence of the project manager.

    Correct Answer
    C. Reducing the time spans on critical activities to complete the project in less time.
    Explanation
    Crashing a project refers to the practice of reducing the time spans on critical activities in order to complete the project in less time. This involves allocating additional resources or increasing the intensity of work to expedite the completion of the project. It is a technique used to compress the project schedule and meet tight deadlines.

    Rate this question:

  • 9. 

    What is a critical path?

    • A.

      The longest path on a network diagram.

    • B.

      The shortest path on a network diagram.

    • C.

      The path that represents the shortest time in which a project could be finished.

    • D.

      None of the above

    Correct Answer(s)
    A. The longest path on a network diagram.
    C. The path that represents the shortest time in which a project could be finished.
    Explanation
    A critical path is the longest path on a network diagram and represents the shortest time in which a project could be finished. It is the sequence of activities that must be completed on time in order to ensure that the project is completed within the specified timeframe. The critical path helps to identify the activities that have the least amount of flexibility in terms of scheduling and are crucial for the successful completion of the project.

    Rate this question:

  • 10. 

    What is designated as a node in PERT?

    • A.

      Network

    • B.

      Event

    • C.

      Activity

    • D.

      Dummy Activity

    Correct Answer
    B. Event
    Explanation
    In PERT (Program Evaluation and Review Technique), a node is designated as an event. In PERT, events represent significant points or milestones in a project, such as the start or completion of an activity. Nodes, or events, are used to depict the sequence of activities and the logical relationships between them in a PERT network diagram. Therefore, the correct answer is Event.

    Rate this question:

Quiz Review Timeline +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Jan 24, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Nov 24, 2011
    Quiz Created by
    Team418b
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.