PERT And CPM Quiz Questions With Answers

Reviewed by Editorial Team
The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Shamshida Taharin
S
Shamshida Taharin
Community Contributor
Quizzes Created: 1 | Total Attempts: 28,995
| Attempts: 28,995 | Questions: 10
Please wait...
Question 1 / 10
0 %
0/100
Score 0/100
1. What is PERT analysis based on?

Explanation

PERT analysis is based on all of the above factors, which include the most likely time, pessimistic time, and optimistic time. PERT (Program Evaluation and Review Technique) is a project management tool used to analyze and estimate the time required to complete a project. By considering these different time estimates, PERT analysis allows for a more comprehensive and realistic assessment of the project timeline, taking into account both best-case and worst-case scenarios, as well as the most likely outcome.

Submit
Please wait...
About This Quiz
PERT And CPM Quiz Questions With Answers - Quiz

Welcome to the PERT and CPM Quiz! This quiz delves into two essential project management techniques: Program Evaluation and Review Technique and Critical Path Method. With 180 words,... see moreyou'll embark on a journey to explore these methodologies crucial for effective project planning and scheduling.

Challenge yourself with questions covering topics such as activity sequencing, network diagrams, slack time, critical activities, and project variance. Gain insights into how these tools aid in resource allocation, risk management, and decision-making throughout project execution.

This quiz offers an engaging platform to assess your comprehension and refine your skills in PERT and CPM methodologies. Prepare to unravel the complexities of project scheduling and optimization, and see how well you fare in navigating the intricate paths of PERT and CPM! see less

2. Which of the following statements is not correct regarding CPM and PERT?

Explanation

The correct answer is "CPM is probabilistic in nature." This statement is not correct because CPM (Critical Path Method) is a deterministic project management technique that focuses on identifying the critical path and determining the minimum time required to complete a project. Unlike PERT (Program Evaluation and Review Technique), which incorporates probabilistic time estimates, CPM assumes fixed durations for activities. Therefore, CPM is not probabilistic in nature.

Submit
3. Mark the wrong statement:

Explanation

The correct answer is "An activity cannot be represented by more than one arrow, but an arrow can represent one or more activities." This statement is incorrect because an activity can be represented by more than one arrow in a project network diagram. This can occur when an activity has multiple predecessors or multiple successors. However, an arrow can indeed represent one or more activities, as it can depict the logical flow between different activities in a project.

Submit
4. Mark the wrong statement:

Explanation

The statement "A project network may have none, one, or more critical paths" is incorrect. A project network can have only one critical path, which is the longest path in the network and determines the minimum time required to complete the project. All activities on the critical path are critical activities, and a delay in any of these activities will delay the completion of the project. Each critical activity has identical earliest and latest start times, as they cannot be delayed without delaying the project.

Submit
5. Given, expected duration of the project = 47 days, variance = 9 days. Expected Time for Project Completion: 50 days Z:  0.33  1.0 Area:  0.1293  0.3413 What is the probability of completing the project within three days, more or less than the expected time?

Explanation

The answer is 0.6826 because the given information provides the expected duration of the project and the variance. With this information, we can calculate the standard deviation by taking the square root of the variance, which is 3 days. We can then use the Z-score formula to find the probability of completing the project within three days of the expected time. The Z-score is calculated by taking the difference between the desired time (3 days) and the expected time (50 days) and dividing it by the standard deviation (3 days). The Z-score of -15 gives us a probability of 0.6826, which means there is a 68.26% chance of completing the project within three days of the expected time.

Submit
6. Mark the wrong statement:

Explanation



The backward pass in project management calculates the latest start and finish times for activities, identifying the latest possible point they can begin and end without delaying the project. This information is crucial for scheduling and resource allocation, ensuring efficient project execution. By determining these timings, project managers can effectively manage dependencies and optimize the project's timeline to meet deadlines.
Submit
7. Which of the following is not a rule of network construction?

Explanation

The rule of network construction states that each defined activity should be represented by one and only one arrow. This means that each activity in the network should have a unique representation and should not be duplicated. The given answer states that identical initial and final nodes can identify two activities, which contradicts this rule. Therefore, the answer is not a rule of network construction.

Submit
8. Which of the following is not correct in respect of PERT calculations?

Explanation

The completion of the project using the PERT method does not follow a normal distribution. PERT calculations use a weighted average of three time estimates to determine the expected time of an activity, and the target time minus the expected time divided by the standard deviation gives the z value. The sum total of variances of critical activity times gives the variance of the overall project completion time. However, the completion of the project itself does not follow a normal distribution.

Submit
9. Given, expected duration of the project = 47 days, variance = 9 days. What is the probability of not completing the project in 50 days? Z: 0.33  1.0 Area  : 0.1293  0.3413

Explanation

The answer is 0.1587 because the question is asking for the probability of not completing the project in 50 days. To calculate this probability, we need to use the concept of standard deviation and Z-scores. The Z-score of 0.33 corresponds to a probability of 0.3707, which represents the area to the left of the Z-score on a standard normal distribution table. Since we want to find the probability of not completing the project in 50 days, we subtract the probability (0.3707) from 1. This gives us 0.6293, which represents the probability of completing the project in 50 days. However, the question is asking for the probability of not completing the project, so we subtract this probability from 1 again. This gives us the final answer of 0.1587, which represents the probability of not completing the project in 50 days.

Submit
10. Mark the wrong statement:

Explanation

The correct answer is "The longest path of a given project gives the maximum duration, while its shortest path indicates the shortest duration." This statement is incorrect because the longest path in a project network diagram represents the critical path, which is the path that determines the minimum duration of the project. The shortest path, on the other hand, represents the path with the least duration.

Submit
View My Results

Quiz Review Timeline (Updated): Apr 1, 2024 +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Apr 01, 2024
    Quiz Edited by
    ProProfs Editorial Team
  • Dec 16, 2014
    Quiz Created by
    Shamshida Taharin
Cancel
  • All
    All (10)
  • Unanswered
    Unanswered ()
  • Answered
    Answered ()
What is PERT analysis based on?
Which of the following statements is not correct regarding CPM and...
Mark the wrong statement:
Mark the wrong statement:
Given, expected duration of the project = 47 days, variance = 9 days....
Mark the wrong statement:
Which of the following is not a rule of network construction?
Which of the following is not correct in respect of PERT calculations?
Given, expected duration of the project = 47 days, variance = 9 days....
Mark the wrong statement:
Alert!

Advertisement