PERT CPM- Operations Research Quiz

10 Questions | Attempts: 8178
Share

SettingsSettingsSettings
PERT CPM- Operations Research Quiz - Quiz

Get ready for this wonderful PERT CPM- Operations Research Quiz. This test is on the topic PERT CPM, subject Operations Research. Are you sure you will be able to pass this test? If yes, then try your luck here. This test will not only give you an idea of your understanding of the subject, but it will also provide you with some extra knowledge. Before you start, we wish you the best of luck!


Questions and Answers
  • 1. 
    CPM is:
    • A. 

      Critical Project Management

    • B. 

      Critical Path Management

    • C. 

      Critical Path Method

    • D. 

      Crash Project Method

  • 2. 
    Which of these is not correct
    • A. 

      PERT is probabilistic in nature.

    • B. 

      CPM is deterministic in nature.

    • C. 

      CPM is event-oriented.

    • D. 

      CPM and PERT use similar terminology but were developed independently.

  • 3. 
    Mark the incorrect statement:
    • A. 

      A project can be called a set of activities that can be performed in a particular logical sequence.

    • B. 

      An activity cannot be represented by more than one arrow, but an arrow can represent one or more activities.

    • C. 

      An arrow which is representing an activity may have any kind of length and shape.

    • D. 

      All are correct

  • 4. 
    Point out which of these is not required in Precedence relationships.
    • A. 

      All the predecessor(s) of an activity should be focused on.

    • B. 

      Should only focus on immediate predecessor(s).

    • C. 

      Should drop redundant predecessors.

    • D. 

      All of these

  • 5. 
    _________ is not a rule of network construction.
    • A. 

      Only one arrow defines each activity.

    • B. 

      A network must have only an initial and only one terminal node.

    • C. 

      Final nodes and identical initial can identify two activities.

    • D. 

      None

  • 6. 
    It is known that in a project, activity 4-6 has a duration of six days and a total float of three days. The E and L times at node 4 are 8 and 11, respectively, while, at node 6, both are equal to 17.Which of the following is not a true statement about 4-6?
    • A. 

      Its free float is three days.

    • B. 

      Its independent float is 0.

    • C. 

      It is a critical activity.

    • D. 

      The ES of this activity is 8.

  • 7. 
    Pick the wrong relationship:
    • A. 

      Interfering float = Total float – Free float

    • B. 

      Total float =Free float + Independent float

    • C. 

      Total float ≥ Free float ≥ Independent float

    • D. 

      Free float = Total float – Head event slack

  • 8. 
    Given, expected duration of the project = 47 days, variance = 9 days. What is the probability of not completing the project in 50 days? Z       :   0.33           1.0Area  :   0.1293       0.3413
    • A. 

      0.6293

    • B. 

      0.8413

    • C. 

      0.1587

    • D. 

      0.3707

  • 9. 
    Given, expected duration of the project = 47 days, variance = 9 days. Expected Time for Project Completion: 50 days Z       :   0.33           1.0Area  :   0.1293       0.3413 What is the probability of completing the project within three days, more or less than the expected time?  
    • A. 

      0.5000

    • B. 

      0.6826

    • C. 

      0.2586

    • D. 

      0.3174

  • 10. 
    ________ is not true about crashing?
    • A. 

      Always pay attention to the critical path and select between critical activities only.

    • B. 

      Crashing cost per day = (Crash cost – Normal cost) / (Normal time – Crash time).

    • C. 

      Always choose the activity with the least crashing cost.

    • D. 

      All are true

Back to Top Back to top
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.