PERT CPM- Operations Research Quiz

Approved & Edited by ProProfs Editorial Team
The editorial team at ProProfs Quizzes consists of a select group of subject experts, trivia writers, and quiz masters who have authored over 10,000 quizzes taken by more than 100 million users. This team includes our in-house seasoned quiz moderators and subject matter experts. Our editorial experts, spread across the world, are rigorously trained using our comprehensive guidelines to ensure that you receive the highest quality quizzes.
Learn about Our Editorial Process
| By Dmmarathe
D
Dmmarathe
Community Contributor
Quizzes Created: 3 | Total Attempts: 17,334
Questions: 10 | Attempts: 8,223

SettingsSettingsSettings
PERT CPM- Operations Research Quiz - Quiz

Get ready for this wonderful PERT CPM- Operations Research Quiz. This test is on the topic PERT CPM, subject Operations Research. Are you sure you will be able to pass this test? If yes, then try your luck here. This test will not only give you an idea of your understanding of the subject, but it will also provide you with some extra knowledge. Before you start, we wish you the best of luck!


Questions and Answers
  • 1. 

    CPM is:

    • A.

      Critical Project Management

    • B.

      Critical Path Management

    • C.

      Critical Path Method

    • D.

      Crash Project Method

    Correct Answer
    C. Critical Path Method
    Explanation
    The correct answer is Critical Path Method (CPM). CPM is a project management technique used to identify the longest sequence of dependent activities in a project, known as the critical path. It helps in determining the minimum time required to complete a project and identifies the activities that cannot be delayed without delaying the entire project. CPM is widely used in project planning and scheduling to optimize resources and ensure timely completion of projects.

    Rate this question:

  • 2. 

    Which of these is not correct

    • A.

      PERT is probabilistic in nature.

    • B.

      CPM is deterministic in nature.

    • C.

      CPM is event-oriented.

    • D.

      CPM and PERT use similar terminology but were developed independently.

    Correct Answer
    C. CPM is event-oriented.
    Explanation
    The given answer states that CPM is event-oriented. This means that CPM focuses on identifying and sequencing specific events or activities that need to occur in a project. CPM does not consider the probabilistic nature of activities and does not involve calculating the expected time or probability of completion for each activity. Instead, it focuses on determining the critical path, which is the sequence of activities that takes the longest time to complete and determines the overall project duration. Therefore, the statement that CPM is event-oriented is correct.

    Rate this question:

  • 3. 

    Mark the incorrect statement:

    • A.

      A project can be called a set of activities that can be performed in a particular logical sequence.

    • B.

      An activity cannot be represented by more than one arrow, but an arrow can represent one or more activities.

    • C.

      An arrow which is representing an activity may have any kind of length and shape.

    • D.

      All are correct

    Correct Answer
    B. An activity cannot be represented by more than one arrow, but an arrow can represent one or more activities.
    Explanation
    The given answer is incorrect because it states that an activity cannot be represented by more than one arrow. In reality, an activity can be represented by multiple arrows, but an arrow can only represent one activity.

    Rate this question:

  • 4. 

    Point out which of these is not required in Precedence relationships.

    • A.

      All the predecessor(s) of an activity should be focused on.

    • B.

      Should only focus on immediate predecessor(s).

    • C.

      Should drop redundant predecessors.

    • D.

      All of these

    Correct Answer
    A. All the predecessor(s) of an activity should be focused on.
    Explanation
    The correct answer is "All of these." This means that all the options mentioned in the question are not required in Precedence relationships. The question is asking which option is not necessary when considering the predecessors of an activity. The correct answer implies that it is not necessary to focus on all the predecessors of an activity, but rather only the immediate ones. Additionally, any redundant predecessors should be dropped, meaning they are not required to be considered in the Precedence relationships.

    Rate this question:

  • 5. 

    _________ is not a rule of network construction.

    • A.

      Only one arrow defines each activity.

    • B.

      A network must have only an initial and only one terminal node.

    • C.

      Final nodes and identical initial can identify two activities.

    • D.

      None

    Correct Answer
    C. Final nodes and identical initial can identify two activities.
    Explanation
    The rule of network construction states that only one arrow should define each activity. This means that each activity should have a clear and unambiguous starting and ending point. The statement "Final nodes and identical initial can identify two activities" contradicts this rule, as it suggests that multiple activities can be identified by the same starting or ending point. Therefore, this statement is not a rule of network construction.

    Rate this question:

  • 6. 

    It is known that in a project, activity 4-6 has a duration of six days and a total float of three days. The E and L times at node 4 are 8 and 11, respectively, while, at node 6, both are equal to 17.Which of the following is not a true statement about 4-6?

    • A.

      Its free float is three days.

    • B.

      Its independent float is 0.

    • C.

      It is a critical activity.

    • D.

      The ES of this activity is 8.

    Correct Answer
    C. It is a critical activity.
    Explanation
    The given answer states that "It is a critical activity" is not a true statement about activity 4-6. This means that activity 4-6 is not a critical activity. A critical activity is one that has zero float, meaning any delay in its completion will cause a delay in the overall project. Since the activity 4-6 has a total float of three days, it means that it can be delayed by up to three days without affecting the project's overall timeline. Therefore, it is not a critical activity.

    Rate this question:

  • 7. 

    Pick the wrong relationship:

    • A.

      Interfering float = Total float – Free float

    • B.

      Total float =Free float + Independent float

    • C.

      Total float ≥ Free float ≥ Independent float

    • D.

      Free float = Total float – Head event slack

    Correct Answer
    A. Interfering float = Total float – Free float
    Explanation
    The given relationship "Interfering float = Total float – Free float" is incorrect. Interfering float refers to the amount of float that affects the project's critical path, while total float represents the total amount of time a task can be delayed without delaying the project. Free float, on the other hand, refers to the amount of time a task can be delayed without delaying the start of any successor tasks. Therefore, the correct relationship should be "Interfering float = Total float + Free float".

    Rate this question:

  • 8. 

    Given, expected duration of the project = 47 days, variance = 9 days. What is the probability of not completing the project in 50 days? Z       :   0.33           1.0Area  :   0.1293       0.3413

    • A.

      0.6293

    • B.

      0.8413

    • C.

      0.1587

    • D.

      0.3707

    Correct Answer
    C. 0.1587
    Explanation
    The answer of 0.1587 represents the probability of not completing the project in 50 days. This probability is calculated using the Z-score and the standard normal distribution table. The Z-score is calculated by taking the difference between the expected duration of the project (47 days) and the given duration (50 days), and dividing it by the square root of the variance (9 days). The Z-score of 0.33 corresponds to an area of 0.1293 in the standard normal distribution table. Since the probability of not completing the project in 50 days is the area to the left of the Z-score, the answer is 0.1587.

    Rate this question:

  • 9. 

    Given, expected duration of the project = 47 days, variance = 9 days. Expected Time for Project Completion: 50 days Z       :   0.33           1.0Area  :   0.1293       0.3413 What is the probability of completing the project within three days, more or less than the expected time?  

    • A.

      0.5000

    • B.

      0.6826

    • C.

      0.2586

    • D.

      0.3174

    Correct Answer
    B. 0.6826
    Explanation
    The answer is 0.6826 because the expected duration of the project is 47 days with a variance of 9 days. The expected time for project completion is 50 days. By using the Z-score formula, we can calculate the probability of completing the project within three days of the expected time. The Z-score for three days is (3 - 50) / √9 = -47 / 3 = -15.67. Looking up this Z-score in the Z-table, we find that the corresponding probability is 0.6826. Therefore, there is a 68.26% chance of completing the project within three days, more or less than the expected time.

    Rate this question:

  • 10. 

    ________ is not true about crashing?

    • A.

      Always pay attention to the critical path and select between critical activities only.

    • B.

      Crashing cost per day = (Crash cost – Normal cost) / (Normal time – Crash time).

    • C.

      Always choose the activity with the least crashing cost.

    • D.

      All are true

    Correct Answer
    C. Always choose the activity with the least crashing cost.
    Explanation
    The statement "Always choose the activity with the least crashing cost" is not true about crashing. While it may seem intuitive to choose the activity with the least crashing cost, it is not always the most effective strategy. The decision of which activity to crash should be based on a variety of factors, such as the impact on the critical path, the time saved, and the cost involved. It is important to carefully analyze these factors and make a strategic decision rather than simply choosing the activity with the lowest crashing cost.

    Rate this question:

Quiz Review Timeline +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 22, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Sep 28, 2009
    Quiz Created by
    Dmmarathe
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.