Network & Project Management Quiz Mc1492

Reviewed by Editorial Team
The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Varun_jurwall
V
Varun_jurwall
Community Contributor
Quizzes Created: 2 | Total Attempts: 2,025
| Attempts: 476 | Questions: 10
Please wait...
Question 1 / 10
0 %
0/100
Score 0/100
1. CPM is:        

Explanation

The correct answer is "Critical Path Method." The Critical Path Method (CPM) is a project management technique used to plan and schedule activities in a project. It identifies the critical path, which is the longest sequence of dependent activities that determine the project's duration. By analyzing the critical path, project managers can prioritize tasks, allocate resources, and identify potential bottlenecks or delays. CPM is widely used in project management to ensure efficient and timely completion of projects.

Submit
Please wait...
About This Quiz
Network & Project Management Quiz Mc1492 - Quiz

This quiz, titled 'Network & Project Management Quiz MC1492', assesses knowledge on Project Management methodologies like CPM and PERT, focusing on concepts such as critical paths, activity representation, and time distributions.

Personalize your quiz and earn a certificate with your name on it!
2. In PERT, if the pessimistic time were 14 weeks, the optimistic time were 8 weeks, and the most likely time were 11 weeks,

Explanation

The expected time in PERT is calculated using a weighted average of the optimistic, pessimistic, and most likely times. The formula for calculating the expected time is (optimistic time + 4 * most likely time + pessimistic time) / 6. In this case, the optimistic time is 8 weeks, the most likely time is 11 weeks, and the pessimistic time is 14 weeks. Plugging these values into the formula, we get (8 + 4 * 11 + 14) / 6 = 11 weeks. Therefore, the expected time would be 11 weeks.

Submit
3. Mark the wrong statement:          

Explanation

not-available-via-ai

Submit
4. The distribution that is used to represent path times is the

Explanation

The beta distribution is commonly used to represent path times because it is a flexible distribution that can take on a wide range of shapes. It is defined on the interval [0,1] which makes it suitable for representing probabilities. Additionally, it has two shape parameters that allow it to be adjusted to fit different data patterns. This makes the beta distribution a suitable choice for modeling path times, where the values are typically bounded and can vary in shape.

Submit
5. The critical path is

Explanation

The correct answer is "the longest time path through the network." The critical path in project management refers to the sequence of activities that determines the total duration of the project. It is the longest path through the network diagram, meaning that any delay in activities along this path will directly impact the project's timeline. Therefore, it is crucial to closely monitor and manage the activities on the critical path to ensure the project stays on schedule.

Submit
6. Which of the following statements is not correct          

Explanation

not-available-via-ai

Submit
7. Mark the wrong statement.    

Explanation

The statement "Each critical activity has identical earliest and the latest start times" is incorrect. In a project network, each critical activity has identical earliest start times and latest finish times, but their latest start times may vary depending on the project schedule.

Submit
8. The crash cost per week

Explanation

The correct answer is "needs to be determined so that the smallest values on the critical path may be considered for time reduction first." This means that the crash cost per week needs to be determined in order to prioritize the activities on the critical path that will lead to the greatest reduction in time. By determining the crash cost per week, the project manager can identify which activities should be accelerated first in order to minimize the overall project duration. This allows for efficient allocation of resources and ensures that the most critical tasks are addressed promptly.

Submit
9. Which of these may require the use of a dummy activity?

Explanation

Both the activity-on-arrow network and the activity-on-node network may require the use of a dummy activity. A dummy activity is a simulated activity that is added to the network to maintain the logical sequence and dependencies between other activities. It is used when there is a need to represent a dependency between two activities that cannot be directly connected. In both types of networks, the use of dummy activities helps to accurately represent the relationships and dependencies between activities.

Submit
10. Which is not a feature of PERT/CPM?

Explanation

The given answer states that all of the options mentioned are features of PERT/CPM. PERT/CPM is a project management technique used to analyze and plan the activities involved in completing a project. The features mentioned in the options are all relevant to PERT/CPM. An estimate of how long a project will take is necessary for planning and scheduling. A graphical display of project activities helps in visualizing the project flow. An indication of critical activities helps in identifying tasks that could delay the project. And an indication of slack time helps in identifying tasks that can be delayed without affecting the project timeline. Therefore, all of these features are indeed part of PERT/CPM.

Submit
View My Results

Quiz Review Timeline (Updated): Apr 25, 2023 +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Apr 25, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Apr 24, 2018
    Quiz Created by
    Varun_jurwall
Cancel
  • All
    All (10)
  • Unanswered
    Unanswered ()
  • Answered
    Answered ()
CPM is:        
In PERT, if the pessimistic time were 14 weeks, the optimistic time...
Mark the wrong statement: ...
The distribution that is used to represent path times is the
The critical path is
Which of the following statements is not correct ...
Mark the wrong statement.    
The crash cost per week
Which of these may require the use of a dummy activity?
Which is not a feature of PERT/CPM?
Alert!

Advertisement