Cost Estimation Trivia: Product Management

Approved & Edited by ProProfs Editorial Team
The editorial team at ProProfs Quizzes consists of a select group of subject experts, trivia writers, and quiz masters who have authored over 10,000 quizzes taken by more than 100 million users. This team includes our in-house seasoned quiz moderators and subject matter experts. Our editorial experts, spread across the world, are rigorously trained using our comprehensive guidelines to ensure that you receive the highest quality quizzes.
Learn about Our Editorial Process
| By Roadman19771
R
Roadman19771
Community Contributor
Quizzes Created: 37 | Total Attempts: 24,053
Questions: 17 | Attempts: 174

SettingsSettingsSettings
Cost Estimation Trivia: Product Management - Quiz

Are you looking for a quiz that will test your understanding when it comes to cost estimation when it comes to product management? The quiz below is perfect for that as it not only helps you dive deeper into the course, but it also helps you to remember all that you have learned in your classes. Do give it a try and keep an eye out for others like it!


Questions and Answers
  • 1. 

    Provides an accurate estimate of project costs

    • A.

      Rough Order of Magnitude (ROM) Estimate

    • B.

      Definitive Estimate

    • C.

      Budgetary Estimate

    Correct Answer
    B. Definitive Estimate
    Explanation
    A definitive estimate provides an accurate estimate of project costs. This type of estimate is based on a detailed analysis of the project requirements, scope, and resources needed. It takes into account specific quantities, labor rates, material costs, and other factors that contribute to the overall cost of the project. A definitive estimate is typically prepared when the project scope and requirements are well-defined and there is a high level of certainty in the project's execution. It provides a reliable basis for budgeting and financial planning.

    Rate this question:

  • 2. 

    A document that describes how the organization will manage cost 

    • A.

      Cost Management Plan

    • B.

      Bottom-Up Estimates

    • C.

      Parametric Modeling

    Correct Answer
    A. Cost Management Plan
    Explanation
    A cost management plan is a document that outlines how an organization will handle and control costs. It includes strategies, processes, and procedures for estimating, budgeting, and monitoring expenses throughout a project or operation. This plan helps ensure that costs are effectively managed and controlled, allowing the organization to stay within budget and achieve its financial goals.

    Rate this question:

  • 3. 

    Use the actual cost of a previous, similar project as the basis for estimating the cost of the current project 

    • A.

      Parametric Modeling

    • B.

      Analogous Estimates (Top-Down Estimates)

    • C.

      Cost Management Plan

    Correct Answer
    B. Analogous Estimates (Top-Down Estimates)
    Explanation
    Analogous Estimates, also known as Top-Down Estimates, involve using the actual cost of a previous, similar project as a basis for estimating the cost of the current project. This method relies on the assumption that the current project will have similar cost drivers and characteristics as the previous project. By comparing the two projects, the estimator can make an educated guess about the cost of the current project. This approach is useful when there is limited information available or when there is not enough time or resources to conduct a detailed bottom-up estimation.

    Rate this question:

  • 4. 

    Estimating individual work items or activities and summing them up to get a project total 

    • A.

      Cost Management Plan

    • B.

      Analogous Estimates (Top-Down Estimates)

    • C.

      Bottom-Up Estimates

    Correct Answer
    C. Bottom-Up Estimates
    Explanation
    Bottom-Up Estimates involve estimating individual work items or activities and then summing them up to get a project total. This approach is considered more accurate and detailed as it takes into account the specific requirements and characteristics of each task. It requires a thorough understanding of the project scope and involves breaking down the project into smaller components for estimation. This method is often time-consuming but provides a more precise estimation of project costs.

    Rate this question:

  • 5. 

    Uses project characteristics (parameters) in a mathematical model to estimate project costs 

    • A.

      Analogous Estimates (Top-Down Estimates)

    • B.

      Bottom-Up Estimates

    • C.

      Parametric Modeling

    Correct Answer
    C. Parametric Modeling
    Explanation
    Parametric modeling is a technique that uses project characteristics or parameters to estimate project costs. It involves creating a mathematical model that relates these project characteristics to the associated costs. By inputting the relevant project parameters into the model, an estimate of the project costs can be generated. This approach is often used when there is limited data available or when there is a need for quick and approximate cost estimates.

    Rate this question:

  • 6. 

    A time-phased budget that project managers use to measure and monitor cost performance. 

    • A.

      Parametric Modeling

    • B.

      Cost Baseline

    • C.

      Earned Value Management (EVM)

    Correct Answer
    B. Cost Baseline
    Explanation
    A cost baseline is a time-phased budget that project managers use to measure and monitor cost performance. It serves as a reference point against which actual costs can be compared, allowing project managers to identify any deviations or variances. By comparing the actual costs incurred during the project with the cost baseline, project managers can assess the project's financial performance and take necessary actions to control costs and ensure the project stays within budget.

    Rate this question:

  • 7. 

    A project performance measurement technique that integrates scope, time, and cost data 

    • A.

      Earned Value Management (EVM)

    • B.

      Cost Baseline

    • C.

      Cost Variance (CV)

    Correct Answer
    A. Earned Value Management (EVM)
    Explanation
    Earned Value Management (EVM) is a project performance measurement technique that integrates scope, time, and cost data. It provides a comprehensive and objective way to measure and track project progress and performance. By comparing the planned value (PV), actual cost (AC), and earned value (EV), EVM allows project managers to determine if a project is on schedule and within budget. It provides valuable insights into cost and schedule variances, allowing for proactive adjustments to be made to keep the project on track. Overall, EVM is a powerful tool for project control and performance evaluation.

    Rate this question:

  • 8. 

    Portion of the approved total cost estimate planned to be spent on an activity during a given period 

    • A.

      Estimate At Completion

    • B.

      Planned Value (PV)

    • C.

      Earned Value (EV)

    Correct Answer
    B. Planned Value (PV)
    Explanation
    Planned Value (PV) refers to the portion of the approved total cost estimate that is planned to be spent on an activity during a given period. It represents the budgeted cost for the work scheduled to be completed up to a specific point in time. PV helps in measuring the progress of a project by comparing the actual cost spent (EV) with the planned cost (PV). It provides insights into whether a project is on track, behind schedule, or ahead of schedule in terms of cost.

    Rate this question:

  • 9. 

    The total direct and indirect costs incurred in accomplishing work on an activity during a given period 

    • A.

      Actual Cost (AC)

    • B.

      Planned Value (PV)

    • C.

      Budget At Completion (BAC)

    Correct Answer
    A. Actual Cost (AC)
    Explanation
    Actual Cost (AC) refers to the total direct and indirect costs that have been incurred in completing work on an activity during a specific period. It includes all the expenses associated with the activity, such as labor costs, material costs, equipment costs, and any other overhead costs. AC is an important metric in project management as it helps in tracking the actual expenditure and comparing it with the planned budget. By comparing AC with Planned Value (PV) and Budget At Completion (BAC), project managers can assess the project's cost performance and make necessary adjustments to stay within the budget.

    Rate this question:

  • 10. 

    An estimate of the value of the physical work actually completed

    • A.

      Schedule Performance Index (SPI)

    • B.

      Planned Value (PV)

    • C.

      Earned Value (EV)

    Correct Answer
    C. Earned Value (EV)
    Explanation
    Earned Value (EV) is the correct answer because it represents an estimate of the value of the physical work actually completed. EV is a project management metric that measures the progress of a project by comparing the budgeted cost of work performed to the actual cost of work performed. It helps in determining whether the project is on track, over budget, or under budget. By calculating the EV, project managers can assess the value of the work completed and compare it to the planned value (PV) and actual cost (AC) to evaluate the project's performance.

    Rate this question:

  • 11. 

    The ratio of actual work completed to the percentage of work planned to have been completed at any given time during the life of the project or activity 

    • A.

      Budget At Completion (BAC)

    • B.

      Rate of Performance (RP)

    • C.

      Schedule Performance Index (SPI)

    Correct Answer
    B. Rate of Performance (RP)
    Explanation
    The Rate of Performance (RP) is the correct answer because it measures the ratio of actual work completed to the percentage of work planned to have been completed at any given time during the project or activity. This metric helps to evaluate the efficiency and productivity of the project by comparing the actual progress to the planned progress. A higher RP indicates that the project is ahead of schedule, while a lower RP suggests that the project is behind schedule.

    Rate this question:

  • 12. 

    The earned value minus the actual cost

    • A.

      Budget At Completion (BAC)

    • B.

      Cost Variance (CV)

    • C.

      Estimate At Completion

    Correct Answer
    B. Cost Variance (CV)
    Explanation
    Cost Variance (CV) is a measure used in project management to determine the cost performance of a project. It is calculated by subtracting the actual cost from the earned value. The earned value represents the value of work that has been completed, while the actual cost represents the actual amount spent on the project. By subtracting the actual cost from the earned value, the cost variance can be determined. A positive cost variance indicates that the project is under budget, while a negative cost variance indicates that the project is over budget. Therefore, the given correct answer is Cost Variance (CV).

    Rate this question:

  • 13. 

    The earned value minus the planned value

    • A.

      Schedule Variance (SV)

    • B.

      Cost Variance (CV)

    • C.

      Schedule Performance Index (SPI)

    Correct Answer
    A. Schedule Variance (SV)
    Explanation
    The earned value minus the planned value is used to calculate the Schedule Variance (SV). Schedule Variance measures the deviation between the planned schedule and the actual progress of a project. By subtracting the planned value from the earned value, the SV indicates whether the project is ahead or behind schedule. A positive SV indicates that the project is ahead of schedule, while a negative SV indicates that the project is behind schedule.

    Rate this question:

  • 14. 

    The ratio of earned value to actual cost and can be used to estimate the projected cost of completing the project 

    • A.

      Schedule Performance Index (SPI)

    • B.

      Rate of Performance (RP)

    • C.

      Cost Performance Index (CPI)

    Correct Answer
    C. Cost Performance Index (CPI)
    Explanation
    The Cost Performance Index (CPI) is the ratio of earned value to actual cost and can be used to estimate the projected cost of completing the project. This means that the CPI shows how efficiently the project is using its budget. If the CPI is greater than 1, it indicates that the project is performing better than expected in terms of cost. On the other hand, if the CPI is less than 1, it indicates that the project is over budget. Therefore, the CPI is a useful metric for project managers to assess the cost performance of a project.

    Rate this question:

  • 15. 

    The ratio of earned value to planned value and can be used to estimate the projected time to complete the project 

    • A.

      Schedule Performance Index (SPI)

    • B.

      Schedule Variance (SV)

    • C.

      Cost Variance (CV)

    Correct Answer
    A. Schedule Performance Index (SPI)
    Explanation
    The Schedule Performance Index (SPI) is a ratio that compares the earned value (the value of work actually performed) to the planned value (the value of work planned to be performed) in order to assess the project's schedule performance. A SPI value greater than 1 indicates that the project is ahead of schedule, while a value less than 1 indicates that the project is behind schedule. Therefore, by calculating the SPI, one can estimate the projected time to complete the project based on its current schedule performance.

    Rate this question:

  • 16. 

    An estimate of what it will cost to complete the project based on performance to date 

    • A.

      Budget At Completion (BAC)

    • B.

      Schedule Variance (SV)

    • C.

      Estimate At Completion

    Correct Answer
    C. Estimate At Completion
    Explanation
    The estimate at completion refers to the projected total cost of completing a project based on the performance and costs incurred to date. It takes into account the actual costs incurred and the projected costs for the remaining work. This estimate helps in determining if the project will be completed within the budget or if there will be a cost overrun.

    Rate this question:

  • 17. 

    The original total budget for the project

    • A.

      Earned Value (EV)

    • B.

      Budget At Completion (BAC)

    • C.

      Rate of Performance (RP)

    Correct Answer
    B. Budget At Completion (BAC)
    Explanation
    The Budget At Completion (BAC) refers to the original total budget allocated for the project. It represents the total cost that was estimated for the project at its completion. BAC is an important metric in project management as it helps in tracking and controlling the project's financial performance. It serves as a baseline against which the actual costs and earned value can be compared to determine the project's progress and performance.

    Rate this question:

Quiz Review Timeline +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 19, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Nov 20, 2009
    Quiz Created by
    Roadman19771
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.