When it comes to project management, a manager needs to ensure that what was planned was achieved at the desired time. The earned value management concept best explains this rule. Think that you understood the concept entirely? The best way to test yourself is by using this challenging quiz. Try it out and see what more you might learn!
EV/PE
EV/PN
EV/AC
EV/PV
PV/EV
Rate this question:
True
False
Rate this question:
Lost Over Estimate
Level Over Effort
Level Of Effort
Last Of Effort
Rate this question:
Critical Path Method
Critical Path Measure
Cost Per Measure
Cost Per Method
Rate this question:
Major (High Risk)
Minor (Low Risk)
Routine
Semi-Routine
Almost-Routine
Rate this question:
Continue Scope defintion to inclcude make or buy analysis
Time phase a project procurement baseline
Place all procurements into four generic categories
Forcast final costs (EAC)
Measuare actual earned value performance, estimate actual costs
Rate this question:
The authorized budget is too high.
Not enough tasks.
The authorized budget is too low.
The authorized work does not exist.
Rate this question:
EAC - BAC
CPI
VAC
BAC - EAC
SPI
Rate this question:
Estimate At Completion (EAC)
Overrun-to-Date
CPI time PMI
Rate this question:
6
7
8
9
Rate this question:
Price: -$24, Usage -$48
Price: $48, Usage: -$24
Price: -$48, Usage: $24
Price: -$48, Usage: -$24
Price: $24, Usage: $48
Rate this question:
Work Remaining (BAC - EV)/ Funds Remaining (BAC - AD)
Work Remaining (BAC - EV)/ Funds Remaining (BAC - AC)
Work Remaining (BAC - PV)/ Funds Remaining (BAC - AC)
Rate this question:
Quiz Review Timeline (Updated): Mar 21, 2023 +
Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.
Wait!
Here's an interesting quiz for you.