Trivia Quiz On Earned Value Management!

Reviewed by Editorial Team
The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Btriplett2002
B
Btriplett2002
Community Contributor
Quizzes Created: 2 | Total Attempts: 1,399
| Attempts: 122 | Questions: 13
Please wait...
Question 1 / 13
0 %
0/100
Score 0/100
1. Can a budget be frontloaded?

Explanation

A budget can be frontloaded, meaning that a larger portion of the budget is allocated or spent at the beginning of the budget period. This allows for more resources to be allocated to priority projects or expenses early on, while potentially reducing spending later in the budget period. Frontloading a budget can help ensure that important initiatives are adequately funded and implemented in a timely manner.

Submit
Please wait...
About This Quiz
Trivia Quiz On Earned Value Management! - Quiz

When it comes to project management, a manager needs to ensure that what was planned was achieved at the desired time. The earned value management concept best explains this rule. Think that you understood the concept entirely? The best way to test yourself is by using this challenging quiz. Try... see moreit out and see what more you might learn! see less

Personalize your quiz and earn a certificate with your name on it!
2. SPI is calculated how?

Explanation

SPI stands for Schedule Performance Index, which is a measure used in project management to assess the efficiency of schedule performance. It is calculated by dividing the Earned Value (EV) by the Planned Value (PV). EV represents the value of the work actually accomplished, while PV represents the planned value of the work scheduled to be done. By dividing EV by PV, we can determine whether a project is ahead or behind schedule. A value greater than 1 indicates that the project is ahead of schedule, while a value less than 1 indicates that the project is behind schedule. Therefore, the correct answer is EV/PV.

Submit
3. Can Earned Value Management be used in Procurements?

Explanation

Earned Value Management (EVM) can indeed be used in procurements. EVM is a project management technique that helps measure project performance and progress in terms of cost and schedule. It allows for the integration of project scope, schedule, and cost objectives, making it applicable to various aspects of project management, including procurements. By using EVM, project managers can effectively track and evaluate the performance of procurement activities, ensuring that they are meeting cost and schedule targets. This helps in identifying any deviations or issues early on, allowing for timely corrective actions to be taken.

Submit
4. LOE stands for what

Explanation

LOE stands for Level Of Effort. This term is commonly used in project management to refer to the amount of work required to complete a task or project. It represents the overall time, resources, and energy needed to accomplish a specific goal. The other options, Lost Over Estimate, Level Over Effort, and Last Of Effort, are not commonly used or recognized acronyms in this context.

Submit
5. CPM stands for what?

Explanation

CPM stands for Critical Path Method, which is a project management technique used to determine the longest sequence of activities in a project. It helps in identifying the critical activities that must be completed on time to avoid delays in the project. The Critical Path Method involves analyzing the dependencies between activities, estimating the duration of each activity, and creating a network diagram to visualize the project schedule. By calculating the critical path, project managers can effectively allocate resources, prioritize tasks, and ensure timely project completion.

Submit
6. The Three Categories are:

Explanation

The given answer categorizes the activities into three categories based on their level of risk. Major activities are considered high risk, indicating that they involve significant potential hazards or consequences. Minor activities are classified as low risk, suggesting that they involve minimal hazards or consequences. Routine activities are those that are performed regularly and are considered to have a moderate level of risk.

Submit
7. Which of these steps is not used for employing earned value on project procurements?

Explanation

The step "Place all procurements into four generic categories" is not used for employing earned value on project procurements. Earned value management focuses on measuring and forecasting project performance based on the budgeted cost of work performed (BCWP), actual cost of work performed (ACWP), and budgeted cost of work scheduled (BCWS). Categorizing procurements into generic categories is not a specific step in this process.

Submit
8. One fundamental problem with project baselines is what?

Explanation

The explanation for the correct answer is that one fundamental problem with project baselines is that the authorized budget is too low. This means that the allocated funds for the project are insufficient to cover all the necessary expenses and tasks. This can lead to delays, compromises in quality, and overall project failure if not addressed and adjusted accordingly.

Submit
9. Variance at Completion.  Is it also know as to what?

Explanation

The correct answer, BAC - EAC, refers to the Variance at Completion (VAC). VAC is a measure used in project management to determine the difference between the budgeted cost of work scheduled (BAC) and the estimated cost to complete (EAC) the project. It helps to assess whether the project is under or over budget. A positive VAC indicates that the project is under budget, while a negative VAC suggests that the project is over budget.

Submit
10. Mark all that apply for forecasting.

Explanation

Estimate At Completion (EAC) and Overrun-to-Date are both methods used in forecasting. EAC is used to estimate the total cost of a project based on the current performance and the remaining work. Overrun-to-Date, on the other hand, is used to calculate the amount by which the actual cost of a project has exceeded the planned cost up to a certain point in time. Both of these methods are important for forecasting and can help in predicting the final outcome of a project.

Submit
11. Control Account Plan (CAP) has how many Elements?

Explanation

See page 104

Submit
12. What went wrong: Budget:$120 - 10 units x $12/unit Actuals:$192 - 12 unit x $16/unit What caused the overrun?

Explanation

The overrun was caused by a decrease in price and an increase in usage. The budgeted price was $12 per unit, but the actual price was $16 per unit, resulting in a decrease of $4 per unit. The budgeted usage was 10 units, but the actual usage was 12 units, resulting in an increase of 2 units. Multiplying the price decrease by the actual usage increase, we get $4 * 2 = $8. Therefore, the total overrun is $8.

Submit
13. TCPI (BAC)

Explanation

The correct answer is "Work Remaining (BAC - PV)/ Funds Remaining (BAC - AC)". This formula calculates the TCPI (To-Complete Performance Index) by dividing the work remaining (BAC - PV) by the funds remaining (BAC - AC). TCPI is a measure of the efficiency required to complete the remaining work within the remaining budget. By using the work remaining and funds remaining, this formula provides a more accurate indication of the performance needed to meet the project's goals.

Submit
View My Results

Quiz Review Timeline (Updated): Mar 21, 2023 +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 21, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Mar 14, 2009
    Quiz Created by
    Btriplett2002
Cancel
  • All
    All (13)
  • Unanswered
    Unanswered ()
  • Answered
    Answered ()
Can a budget be frontloaded?
SPI is calculated how?
Can Earned Value Management be used in Procurements?
LOE stands for what
CPM stands for what?
The Three Categories are:
Which of these steps is not used for employing earned value on project...
One fundamental problem with project baselines is what?
Variance at Completion.  Is it also know as to what?
Mark all that apply for forecasting.
Control Account Plan (CAP) has how many Elements?
What went wrong:...
TCPI (BAC)
Alert!

Advertisement