The editorial team at ProProfs Quizzes consists of a select group of subject experts, trivia writers, and quiz masters who have authored over 10,000 quizzes taken by more than 100 million users. This team includes our in-house seasoned quiz moderators and subject matter experts. Our editorial experts, spread across the world, are rigorously trained using our comprehensive guidelines to ensure that you receive the highest quality quizzes.
Learn about Our Editorial Process
| By Gregorynaomi
G
Gregorynaomi
Community Contributor
Quizzes Created: 1463 | Total Attempts: 756,371
Questions: 10 | Attempts: 132

SettingsSettingsSettings
Projects In Contolled Environments Foundation Practice Test - Quiz

Project management could both be fulfilling as well as tasking. The best approach to reduce the stress is to segment it into parts which can be easily handled. Controlled environments having experienced pragmatic change of ownership and name over the years has principles and management products which make a project worth the time. How much do you know about this?


Questions and Answers
  • 1. 

    How many stages does it divides business into?

    • A.

      Four stages

    • B.

      Three stages

    • C.

      Three stages

    • D.

      Two stages

    Correct Answer
    D. Two stages
    Explanation
    This question is asking about the number of stages that business is divided into. The correct answer is "Two stages."

    Rate this question:

  • 2. 

    When was its ownership transferred to AXELOS Ltd?

    • A.

      February 2013

    • B.

      July 2013

    • C.

      January 2013

    • D.

      September 2013

    Correct Answer
    B. July 2013
    Explanation
    Ownership of the entity in question was transferred to AXELOS Ltd in July 2013.

    Rate this question:

  • 3. 

    What year saw the release of the second edition?

    • A.

      1999

    • B.

      1996

    • C.

      2000

    • D.

      1998

    Correct Answer
    B. 1996
    Explanation
    The second edition was released in 1996, as stated in the answer.

    Rate this question:

  • 4. 

    How many editions of PRINCE2 was made?

    • A.

      Three editions

    • B.

      Five editions

    • C.

      Four editions

    • D.

      Two editions

    Correct Answer
    D. Two editions
    Explanation
    PRINCE2 has been revised twice, resulting in two editions.

    Rate this question:

  • 5. 

    How many principles form the basis of PRINCE2?

    • A.

      Five principles

    • B.

      Six principles

    • C.

      Nine principles

    • D.

      Seven principles

    Correct Answer
    D. Seven principles
    Explanation
    PRINCE2, which stands for PRojects IN Controlled Environments, is a project management method widely used in various industries. It is based on seven principles that form the foundation of the approach. These principles include continued business justification, learning from experience, defined roles and responsibilities, managing by stages, managing by exception, focusing on products, and tailoring to suit the project's needs. These principles provide a framework for effective project management and ensure that projects are aligned with organizational objectives and best practices.

    Rate this question:

  • 6. 

    How many themes are relevant in PRINCE2?

    • A.

      Five themesĀ 

    • B.

      Four themes

    • C.

      Six themes

    • D.

      Seven themes

    Correct Answer
    D. Seven themes
    Explanation
    PRINCE2, which stands for Projects IN Controlled Environments, is a project management methodology that consists of seven themes. These themes are essential aspects that need to be considered and addressed throughout the project lifecycle. They include Business Case, Organization, Quality, Plans, Risk, Change, and Progress. Each theme plays a crucial role in ensuring project success by providing a comprehensive framework for managing different aspects of the project. Therefore, the correct answer is seven themes.

    Rate this question:

  • 7. 

    Which of these is irrelevant in this subject?

    • A.

      Quality

    • B.

      Budget

    • C.

      Organization

    • D.

      Business case

    Correct Answer
    B. Budget
    Explanation
    In this subject, which is not specified, the relevance of quality, organization, and business case is emphasized. However, the budget is considered irrelevant. This suggests that the subject may be focused on aspects such as quality management, organizational structure, and business justification, where budgeting is not a key factor or does not hold much significance.

    Rate this question:

  • 8. 

    How many templates are in the PRINCE2 manual?

    • A.

      21 templates

    • B.

      18 templates

    • C.

      15 templates

    • D.

      26 templates

    Correct Answer
    D. 26 templates
    Explanation
    The correct answer is 26 templates. This means that there are a total of 26 templates included in the PRINCE2 manual. These templates are likely to be used for various project management purposes and can provide a structured approach to managing projects effectively.

    Rate this question:

  • 9. 

    Which of these is used to record informal issues?

    • A.

      Lessons Log

    • B.

      End Project Report

    • C.

      Issues Register

    • D.

      Daily Log

    Correct Answer
    D. Daily Log
    Explanation
    The Daily Log is used to record informal issues. This log is a tool used in project management to document daily activities, events, and issues that occur during the project. It serves as a journal or diary, providing a record of what happened on a particular day. The Daily Log is typically used to record informal issues that arise during the project, such as unexpected problems, concerns, or observations. It helps to keep track of these issues and ensures that they are addressed and resolved in a timely manner.

    Rate this question:

  • 10. 

    Which of these is not a PRINCE2 management product?

    • A.

      Checkpoint Record

    • B.

      Business case

    • C.

      Benefits Review Plan

    • D.

      Task Record

    Correct Answer
    D. Task Record
    Explanation
    The PRINCE2 methodology includes various management products that are used throughout the project lifecycle. These management products help in the planning, monitoring, and control of the project. The Business case, Benefits Review Plan, and Checkpoint Record are all examples of PRINCE2 management products. However, the Task Record is not a recognized management product in PRINCE2. It is not mentioned or defined in the PRINCE2 methodology, making it the correct answer.

    Rate this question:

Quiz Review Timeline +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 21, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Oct 14, 2018
    Quiz Created by
    Gregorynaomi
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.