The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Lnperez
L
Lnperez
Community Contributor
Quizzes Created: 1 | Total Attempts: 64
| Attempts: 64
SettingsSettings
Please wait...
  • 1/57 Questions

    In case of official Master Schedule revision - ECI DIR C/O schedule has to be re-studied.

    • True
    • False
Please wait...
About This Quiz


Quiz Topics:
1. Drawing Coordination
2. Reflection
3. PPO/ILA
4. Drawing Follow-up
5. ECI C/O

Ppm Prep Quiz #3 - Quiz

Quiz Preview

  • 2. 

    After off-tool target date (parts due date) is determined, designer will provide drawing issuance __________.

    • Plan Date

    • Requested Date

    • Actual Date

    Correct Answer
    A. Plan Date
    Explanation
    After the off-tool target date (parts due date) is determined, the designer will provide drawing issuance on the plan date. This means that the designer will release the drawings on the scheduled date as per the plan. This allows for proper coordination and ensures that the necessary drawings are provided in a timely manner for further production processes.

    Rate this question:

  • 3. 

    The main purpose of drawing coordination is to determine drawing release date in which supplier will have sufficient time to:

    • Evaluate proposals for cost reduction

    • Build a bank of parts for tool changeover

    • Provide quote information to purchasing

    • Supply Off-tool parts for target trial

    Correct Answer
    A. Supply Off-tool parts for target trial
    Explanation
    The main purpose of drawing coordination is to determine the release date of the drawing when the supplier will have enough time to supply off-tool parts for target trial. This means that the supplier needs to have the necessary parts ready for testing and evaluation before the target trial takes place. Drawing coordination also involves evaluating proposals for cost reduction, building a bank of parts for tool changeover, and providing quote information to purchasing, but the primary focus is on supplying off-tool parts for target trial.

    Rate this question:

  • 4. 

    Which of the following is based on a measure of historical lead times for a particular part type?

    • Standard lead time data from SED

    • Actual off-tool %

    • Standard off-tool %

    Correct Answer
    A. Standard lead time data from SED
    Explanation
    Standard lead time data from SED is based on a measure of historical lead times for a particular part type. This means that the standard lead time data is derived from past data and provides an estimate of the time it takes to complete the production of a specific part. It is a reliable measure as it takes into account the actual time it has taken in the past to produce similar parts, allowing for better planning and scheduling of production activities.

    Rate this question:

  • 5. 

    What methodology should each group be using to find true root cause for reflection?

    • Six Sigma

    • Trial and Error

    • Each department utilizes own methodology

    • TBP

    Correct Answer
    A. TBP
  • 6. 

    PPM is the group responsible to create draft top items list for Reflection.

    • True

    • False

    Correct Answer
    A. True
    Explanation
    The explanation for the given correct answer is that PPM, which stands for Product Portfolio Management, is the group responsible for creating a draft top items list for Reflection. This means that PPM is in charge of compiling a list of the most important or significant items that require reflection or review. Therefore, the statement "PPM is the group responsible to create draft top items list for Reflection" is true.

    Rate this question:

  • 7. 

    ILA parts contain the digits "YY" (e.g.: 67918-YY050).

    • True

    • False

    Correct Answer
    A. True
    Explanation
    The statement is true because it states that ILA parts contain the digits "YY" in their code. This implies that any ILA part will have a code that includes the "YY" digits.

    Rate this question:

  • 8. 

    Select the install location for a DIO part.

    • Plant

    • Dealer Location

    • Hub/Yard near plant

    Correct Answer
    A. Dealer Location
    Explanation
    The correct answer is "Dealer Location" because when selecting an install location for a DIO part, it is most commonly done at the dealer location. This is where the DIO part is typically stored and where the installation process takes place. The plant and hub/yard near the plant are not typically involved in the installation of DIO parts.

    Rate this question:

  • 9. 

     _______________ is an assembly instruction issued by Design to Manufacturing to instruct sequence of assembly.

    • RDDP

    • TIS

    • RAD

    • ASA

    Correct Answer
    A. TIS
    Explanation
    TIS is the correct answer because it stands for "Test Instruction Sheet," which is a document issued by Design to Manufacturing to provide instructions for the sequence of assembly. This sheet outlines the specific tests that need to be conducted during the assembly process to ensure the quality and functionality of the final product.

    Rate this question:

  • 10. 

    Major ECI C/O date considers plant PC order date.

    • True

    • False

    Correct Answer
    A. True
    Explanation
    The statement is explaining that the Major ECI C/O (Engineering Change Implementation Change Order) date takes into account the plant PC (Production Control) order date. This means that when implementing an engineering change, the date of the change order is determined based on the date the production order was placed. Therefore, the statement is true as it confirms that the Major ECI C/O date considers the plant PC order date.

    Rate this question:

  • 11. 

    There is no ECI Cut-off date coordination for QCS, because it is not an ECI confirmation stage.

    • True

    • False

    Correct Answer
    A. True
    Explanation
    The explanation for the given correct answer is that ECI Cut-off date coordination is not applicable for QCS because QCS is not a stage where ECI confirmation takes place. Therefore, there is no need for any coordination or cut-off date for QCS.

    Rate this question:

  • 12. 

    A Major ECI issued after ECI Cut-off date & after plant order date and implementing at the immediate trial will have an impact to the Plant trial order.

    • True

    • False

    Correct Answer
    A. True
    Explanation
    If a Major ECI (Engineering Change Instruction) is issued after the ECI Cut-off date and after the plant order date, implementing it immediately during the trial will have an impact on the plant trial order. This means that the change will affect the order for testing or evaluating the plant's performance.

    Rate this question:

  • 13. 

    Who leads Star 4 reflection, "Initial Field Quality Results"?

    • PPM

    • Z

    • QD

    • Plant PC

    Correct Answer
    A. QD
    Explanation
    QD leads the Star 4 reflection, "Initial Field Quality Results."

    Rate this question:

  • 14. 

    "Yokoten to future projects" is one of the main purposes for reflection.

    • True

    • False

    Correct Answer
    A. True
    Explanation
    The statement suggests that one of the main purposes of reflection is to apply the concept of "Yokoten" to future projects. Yokoten refers to the practice of sharing knowledge and best practices across different projects or teams within an organization. By reflecting on past experiences and identifying successful strategies, individuals and teams can apply these learnings to future projects, improving efficiency and effectiveness. Therefore, the statement is true.

    Rate this question:

  • 15. 

    When a Division Leads a reflection activity, they are not required to perform internal reflection.

    • True

    • False

    Correct Answer
    A. False
    Explanation
    When a Division Leads a reflection activity, they are required to perform internal reflection. This means that they need to assess their own performance, actions, and decisions during the activity. Internal reflection helps the division to identify areas of improvement, learn from mistakes, and make necessary adjustments for future activities. By engaging in internal reflection, the division can enhance their effectiveness and ensure continuous growth and development. Therefore, the statement that they are not required to perform internal reflection is incorrect.

    Rate this question:

  • 16. 

    PPO parts are in SMS.

    • True

    • False

    Correct Answer
    A. False
    Explanation
    The statement "PPO parts are in SMS" is false. PPO stands for "Polyphenylene oxide," which is a high-performance engineering plastic. SMS, on the other hand, stands for "Short Message Service," which is a text messaging service. These two terms are unrelated and do not have any connection or association with each other. Hence, the correct answer is false.

    Rate this question:

  • 17. 

    The purpose of Drawing F/U is to ensure that agreed drawing issue dates are met and in case they are not, develop recovery plan to ensure meeting __________ .

    • Cost target

    • Kick-off meeting target

    • Off-Process target

    • Off-Tool target

    Correct Answer
    A. Off-Tool target
    Explanation
    The purpose of Drawing F/U is to ensure that agreed drawing issue dates are met and in case they are not, develop recovery plan to ensure meeting Off-Tool target. This means that the Drawing F/U process is necessary to ensure that the drawings are issued on time and if there are any delays, a plan is developed to meet the Off-Tool target, which refers to the target date for completing the tooling process. This ensures that the production of the required tools is not delayed and the project stays on track.

    Rate this question:

  • 18. 

    KVC vanning timing should be considered during ECI/DIR C/O schedule coordination.

    • True

    • False

    Correct Answer
    A. True
    Explanation
    The statement suggests that the timing of KVC vanning (the process of loading cargo into a container) should be taken into account when coordinating the ECI/DIR C/O schedule. This implies that the timing of the vanning process can have an impact on the overall schedule, and therefore, it is important to consider it during coordination. Therefore, the answer "True" indicates that the statement is correct.

    Rate this question:

  • 19. 

     Late ECI issuance (after C/O date) is possible, but requires special coordination led by PPM.

    • True

    • False

    Correct Answer
    A. True
    Explanation
    Late ECI issuance refers to the issuance of an Engineering Change Instruction after the Change Order (C/O) date. This is possible, but it requires special coordination led by the Project Portfolio Management (PPM) team. In other words, if there is a need for an engineering change after the C/O date, it can still be issued, but it will require additional coordination and management by the PPM team to ensure that the change is implemented effectively. Therefore, the statement "Late ECI issuance (after C/O date) is possible, but requires special coordination led by PPM" is true.

    Rate this question:

  • 20. 

     It ______ Design responsibility to coordinate agreed on TIS release plan with PE and Mfg Plant.

    • Is

    • Is not

    Correct Answer
    A. Is
    Explanation
    The correct answer is "is". This is because the sentence is stating that it is the responsibility of Design to coordinate the agreed-on TIS release plan with PE and Mfg Plant. Using "is" indicates that this statement is true and accurate.

    Rate this question:

  • 21. 

    Which group is responsible for sending out coordination results surveys through SPIMS?

    • PE

    • PPM

    • SED

    • Z/Design

    Correct Answer
    A. SED
    Explanation
    The group responsible for sending out coordination results surveys through SPIMS is SED.

    Rate this question:

  • 22. 

    PPM is responsible to ensure that projects reflections are yokotened to future projects.

    • True

    • False

    Correct Answer
    A. True
    Explanation
    PPM stands for Project Portfolio Management, which involves the management and oversight of multiple projects within an organization. One of the responsibilities of PPM is to ensure that the lessons learned and reflections from past projects are incorporated into future projects. This helps to avoid repeating mistakes, improve efficiency, and increase the chances of project success. Therefore, the statement that PPM is responsible for ensuring that project reflections are yokotened (i.e., carried forward) to future projects is true.

    Rate this question:

  • 23. 

    Select the install location for a PPO part. 

    • Dealer Location

    • On-line in plant

    • Off-line near plant or in Hub/Yard

    Correct Answer
    A. Off-line near plant or in Hub/Yard
    Explanation
    The correct answer is "Off-line near plant or in Hub/Yard". This option suggests that the PPO part should be installed in a location that is separate from the main plant or factory, but still in close proximity to it. This could be a hub or yard near the plant. Installing the part off-line helps to streamline the production process and ensures that the main plant is not disrupted during installation. Additionally, having the part near the plant or in a hub/yard allows for easy access and efficient transportation of the part when needed.

    Rate this question:

  • 24. 

    OE parts are potentially scrapped during PPO installation.

    • True

    • False

    Correct Answer
    A. True
    Explanation
    During the installation of PPO (Pre-Production Operations), OE (Original Equipment) parts have the potential to be scrapped. This means that these parts may no longer be used or considered valuable after the installation process. It implies that the PPO installation might involve replacing or discarding the existing OE parts, making them potentially useless or waste. Hence, the statement "OE parts are potentially scrapped during PPO installation" is true.

    Rate this question:

  • 25. 

    If Designer cannot meet the original/agreed drawing issuance plan date, they should issue a Survey Sheet ________________.

    • After the original plan date (target at most 2 weeks after)

    • Never

    • Before the original plan date (target at least 2 weeks before)

    Correct Answer
    A. Before the original plan date (target at least 2 weeks before)
    Explanation
    If the designer is unable to meet the original/agreed drawing issuance plan date, they should issue a Survey Sheet before the original plan date, with a target of at least 2 weeks before. This suggests that the designer should provide the Survey Sheet ahead of time, allowing for ample time for review and adjustments before the original plan date. This proactive approach ensures that any potential issues or changes can be addressed in a timely manner, avoiding delays in the overall project timeline.

    Rate this question:

  • 26. 

    PPM is responsible to update revised drawing issue date in ______________.

    • TENIS

    • DCSI/Excel tracking file

    • SMS BR

    • N-SMS

    Correct Answer
    A. DCSI/Excel tracking file
    Explanation
    The correct answer is DCSI/Excel tracking file because it is the document or system where the revised drawing issue date needs to be updated. This file is responsible for keeping track of all the drawings and their respective issue dates, ensuring that the most recent version is always referenced. By updating the revised drawing issue date in the DCSI/Excel tracking file, the PPM (Project/Program Manager) ensures that all stakeholders have access to the latest information and can make informed decisions based on the most up-to-date drawings.

    Rate this question:

  • 27. 

    What is the correct definition of Static Evaluation?

    • Includes items from the assembly team such as workability, and QC items such as fit and finish.

    • Refers to durability tests / NVH. It is done by moving the vehicle, such as with a long distance drive.

    Correct Answer
    A. Includes items from the assembly team such as workability, and QC items such as fit and finish.
    Explanation
    Static Evaluation refers to the assessment of various aspects of a product or vehicle that do not involve movement or operation. It includes evaluating items from the assembly team, such as workability, and quality control (QC) items, such as fit and finish. This type of evaluation focuses on the physical characteristics and functionality of the product while stationary, rather than its durability or performance during movement or operation.

    Rate this question:

  • 28. 

    Which of the following is not an input into the Drawing Coordination activity?

    • Tooling Kick-off Meeting result

    • Design drawing plan date

    • Target to have off-tool parts available

    • All new delivery part numbers and specific QE/PUR coordinated direct supply parts

    Correct Answer
    A. Tooling Kick-off Meeting result
    Explanation
    The Tooling Kick-off Meeting result is not an input into the Drawing Coordination activity. The other options listed (Design drawing plan date, Target to have off-tool parts available, All new delivery part numbers and specific QE/PUR coordinated direct supply parts) are inputs that are necessary for the Drawing Coordination activity.

    Rate this question:

  • 29. 

    What is the scope of reflection activity?

    • Major, Minor/Model (if significant problem exist)

    • All projects

    • Only major

    • None of the above

    Correct Answer
    A. Major, Minor/Model (if significant problem exist)
    Explanation
    The scope of reflection activity includes both major and minor/model problems, but only if significant problems exist. This means that the reflection activity is not limited to just major problems, but also includes identifying and addressing minor or model issues as long as they are significant.

    Rate this question:

  • 30. 

    When is the expected completion timing for Star 3?

    • Finish before MPTA K/O

    • Finish before CV K/O

    •  

    Correct Answer
    A.  
    Explanation
    The expected completion timing for Star 3 is to finish before MPTA K/O and before CV K/O.

    Rate this question:

  • 31. 

    Which group is a division of TMS specifically responsible for actual vehicle transportation to dealerships and PPO installations?

    • PPD

    • TCI

    • TLS

    • CAOD

    Correct Answer
    A. TLS
    Explanation
    TLS is the correct answer because it is a division of TMS that is specifically responsible for actual vehicle transportation to dealerships and PPO installations. PPD, TCI, and CAOD are not mentioned as divisions responsible for vehicle transportation in the question.

    Rate this question:

  • 32. 

    PPM co-chairs the Drawing Follow Up meeting together with _________.

    • PUR

    • ED leaders

    • PE

    • Z division

    Correct Answer
    A. Z division
    Explanation
    PPM co-chairs the Drawing Follow Up meeting together with Z division. This suggests that the Z division is responsible for collaborating with PPM in organizing and leading the Drawing Follow Up meeting. The Z division likely has expertise or authority in the subject matter of the meeting and plays a crucial role in ensuring its success.

    Rate this question:

  • 33. 

    Which of the following is the final supplier drawing approved by Toyota?

    • ASA

    • EDM

    • RDDP

    • RAD

    Correct Answer
    A. RAD
    Explanation
    The final supplier drawing approved by Toyota is RAD.

    Rate this question:

  • 34. 

    Which of the following items are not needed to begin ECI DIR schedule coordination?

    • Potential ECI list

    • Official Master Schedule

    • Plant PC ordering lead times/ordering schedule

    Correct Answer
    A. Potential ECI list
    Explanation
    The potential ECI list is not needed to begin ECI DIR schedule coordination. This list contains potential engineering change instructions (ECIs) that may be implemented in the future. However, to begin ECI DIR schedule coordination, the official master schedule and the plant PC ordering lead times/ordering schedule are required. These documents provide information on the current schedule and ordering timelines, which are essential for coordinating the implementation of ECIs.

    Rate this question:

  • 35. 

    When is DIR-ECI Cut-off targeted issue timing?

    • Project Kick-off

    • Tooling Kick-off

    • Genzu Kick=off

    • Master Schedule approval

    Correct Answer
    A. Tooling Kick-off
    Explanation
    The correct answer is Tooling Kick-off. This is because the question is asking about the timing of the DIR-ECI Cut-off, and out of the given options, the Tooling Kick-off is most likely to be the time when the cut-off is targeted. The other options, such as Project Kick-off, Genzu Kick-off, and Master Schedule approval, are not directly related to the timing of the DIR-ECI Cut-off.

    Rate this question:

  • 36. 

    What level should the reflection leaders be?

    • Analyst

    • Manager or above

    • No less than VP

    • None of the above

    Correct Answer
    A. Manager or above
    Explanation
    The reflection leaders should be at the Manager or above level because they need to have the necessary authority and influence to lead and guide the reflection process effectively. Managers and above have the experience, knowledge, and decision-making capabilities required to facilitate meaningful reflection and drive change within the organization. Analysts may not have the necessary leadership skills, while VP level may be too high and may not have the time or focus required for reflection leadership.

    Rate this question:

  • 37. 

    What is the final output of the full ILA selection process?

    • Total Accessories List

    • Global ILA Candidate Sheet

    • ADRF

    • Study List

    Correct Answer
    A. Global ILA Candidate Sheet
    Explanation
    The final output of the full ILA selection process is the Global ILA Candidate Sheet. This sheet contains a comprehensive list of all the candidates who have been selected for the ILA program. It includes their names, contact information, qualifications, and other relevant details. This sheet is used for further evaluation and decision-making in the ILA selection process.

    Rate this question:

  • 38. 

    Which division is responsible for creating and issuing the weekly Drawing Issuance report?

    • TMC EDM

    • QD

    • PUR

    • Z

    Correct Answer
    A. TMC EDM
    Explanation
    TMC EDM is responsible for creating and issuing the weekly Drawing Issuance report.

    Rate this question:

  • 39. 

    If supplier drawing request date is _________ than designers issuance plan date, then parts are targeted for drawing coordination meeting.

    • Later

    • Earlier

    • Same as

    Correct Answer
    A. Earlier
    Explanation
    If the supplier drawing request date is earlier than the designer's issuance plan date, it means that the supplier has submitted their drawing request before the designer has issued their plan. In this case, the parts are targeted for a drawing coordination meeting, as it is necessary to coordinate and align the supplier's drawings with the designer's plan.

    Rate this question:

  • 40. 

    Drawings are coordinated to meet _____________ Target.

    • Tooling Kick-off

    • Off-Process

    • Off-Tool

    • 1W/A

    Correct Answer
    A. Off-Tool
    Explanation
    Drawings are coordinated to meet the "Off-Tool" target. This means that the drawings are prepared and coordinated to ensure that the tooling process, such as the creation of molds or dies, can begin. "Off-Tool" refers to the point at which the tooling process is completed and the tools are ready for production. Coordinating the drawings with this target ensures that the tooling process can proceed smoothly and efficiently.

    Rate this question:

  • 41. 

    If a drawing coordination meeting is required, the designer should negotiate with the supplier to gain agreement prior to the scheduled drawing coordination meeting.

    • True

    • False

    Correct Answer
    A. True
    Explanation
    In order for a drawing coordination meeting to be successful, it is necessary for the designer and supplier to reach an agreement beforehand. This ensures that both parties are on the same page and can effectively collaborate during the meeting. Without prior agreement, the meeting may be unproductive and lead to misunderstandings or conflicts. Therefore, it is important for the designer to negotiate with the supplier and gain their agreement before the scheduled meeting.

    Rate this question:

  • 42. 

    The "Strategy" activity (including PPO/ILA Project Kick off meeting) is completed about 1 month prior to the _____________.

    • Style Approval

    • CE Image

    • Tooling Kick-off

    • SE Kick-off

    Correct Answer
    A. CE Image
    Explanation
    The "Strategy" activity, which includes the PPO/ILA Project Kick off meeting, is completed about 1 month prior to the CE Image.

    Rate this question:

  • 43. 

    Who is the window group responsible for follow-up with suppliers?

    • PE

    • PUR

    • SED

    • PPM

    Correct Answer
    A. SED
    Explanation
    The window group responsible for follow-up with suppliers is SED.

    Rate this question:

  • 44. 

     DIR/ECI cut off schedule coordination is led by Z with support from related divisions (PPM, Design, VPE, Plant).

    • True

    • False

    Correct Answer
    A. False
    Explanation
    The statement is false because the coordination for the DIR/ECI cut off schedule is not led by Z with support from related divisions.

    Rate this question:

  • 45. 

    The ECI Cut-off schedule does not need to be issued by Z on a Tech Notice.

    • True

    • False

    Correct Answer
    A. False
    Explanation
    The ECI Cut-off schedule needs to be issued by Z on a Tech Notice. This means that Z is responsible for announcing the cut-off schedule, which determines the deadline for submitting ECI (Engineering Change Instructions) in a technical notice. Therefore, the correct answer is False, as Z is required to issue the ECI Cut-off schedule on a Tech Notice.

    Rate this question:

  • 46. 

    PPM is the leader for Star 1 & 2 reflections.

    • True

    • False

    Correct Answer
    A. False
    Explanation
    PPM is not the leader for Star 1 & 2 reflections.

    Rate this question:

  • 47. 

    Drawing Issuance report includes the list of drawings to be issued in the next __________.

    • 6 weeks

    • 5 weeks

    • 1 week

    • 3 weeks

    Correct Answer
    A. 3 weeks
    Explanation
    The correct answer is 3 weeks because the Drawing Issuance report includes the list of drawings that will be issued in the next 3 weeks. This report helps in planning and organizing the issuance of drawings in a timely manner, ensuring that the necessary drawings are available when needed for various projects or purposes.

    Rate this question:

  • 48. 

    What is the official paper request to Design from Sales and/or manufacturing to modify OE vehicle for ease of ILA/PPO installation?

    • Candidate Cost Investigation Sheet

    • Cost Reduction Evaluation Sheet

    • Accommodation sheet

    • Obeya Paper

    Correct Answer
    A. Accommodation sheet
    Explanation
    The official paper request to Design from Sales and/or manufacturing to modify OE vehicle for ease of ILA/PPO installation is called the Accommodation sheet. This sheet is used to communicate the necessary modifications and adjustments that need to be made to the vehicle design in order to facilitate the installation of ILA/PPO components. It serves as a formal request from Sales and/or manufacturing to the Design department, outlining the specific changes that need to be implemented for the purpose of improving the ease of installation.

    Rate this question:

  • 49. 

    Drawing coordination date information, such as an agreed date, is carried forward from provisional part number to production part by the use of?

    • RDSF

    • KPIMAPS download info

    • 21= comment in production parts list

    • FSR record in MIK

    Correct Answer
    A. 21= comment in production parts list
    Explanation
    The correct answer is "21= comment in production parts list." This is because a comment in the production parts list can be used to carry forward drawing coordination date information, such as an agreed date, from the provisional part number to the production part. This allows for easy reference and ensures that the necessary information is available during the production process.

    Rate this question:

Quiz Review Timeline (Updated): Nov 11, 2024 +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Nov 11, 2024
    Quiz Edited by
    ProProfs Editorial Team
  • Feb 19, 2018
    Quiz Created by
    Lnperez
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.