Quiz Topics:
1. Drawing Coordination
2. Reflection
3. PPO/ILA
4. Drawing Follow-up
5. ECI C/O
Later
Earlier
Same as
Rate this question:
Is
Is not
Rate this question:
Tooling Kick-off
Off-Process
Off-Tool
1W/A
Rate this question:
RDSF
KPIMAPS download info
21= comment in production parts list
FSR record in MIK
Rate this question:
Evaluate proposals for cost reduction
Build a bank of parts for tool changeover
Provide quote information to purchasing
Supply Off-tool parts for target trial
Rate this question:
True
False
Rate this question:
Standard lead time data from SED
Actual off-tool %
Standard off-tool %
Rate this question:
PE
PPM
SED
Z/Design
Rate this question:
251
210
211
100
Rate this question:
Tooling Kick-off Meeting result
Design drawing plan date
Target to have off-tool parts available
All new delivery part numbers and specific QE/PUR coordinated direct supply parts
Rate this question:
Drawing release timing
Master Schedule result
RMBSS Release and Sourcing
Unachieved BR-AD & SSR KPIs (all departments)
Rate this question:
PPM
Z
QD
Plant PC
Rate this question:
Star 1
Star 2
Star 3
All of the above
Rate this question:
True
False
Rate this question:
Six Sigma
Trial and Error
Each department utilizes own methodology
TBP
True
False
Rate this question:
True
False
Rate this question:
Major, Minor/Model (if significant problem exist)
All projects
Only major
None of the above
Rate this question:
Finish before MPTA K/O
Finish before CV K/O
Rate this question:
Analyst
Manager or above
No less than VP
None of the above
Rate this question:
True
False
Rate this question:
Deadline is clearly communicated during reflection K/O meeting
Division A/M's are responsible for keeping report creation on schedule
A series of status check meetings with executives are held
Follow up weekly with leaders to check status of reports
Rate this question:
True
False
Rate this question:
PPD
TCI
TLS
CAOD
Rate this question:
True
False
Rate this question:
Style Approval
CE Image
Tooling Kick-off
SE Kick-off
Rate this question:
Dealer Location
On-line in plant
Off-line near plant or in Hub/Yard
Rate this question:
Plant
Dealer Location
Hub/Yard near plant
Rate this question:
True
False
Rate this question:
True
False
Rate this question:
Candidate Cost Investigation Sheet
Cost Reduction Evaluation Sheet
Accommodation sheet
Obeya Paper
Rate this question:
Total Accessories List
Global ILA Candidate Sheet
ADRF
Study List
Rate this question:
Final ILA Production List
WVTA Approval
ILA QCS Readiness
1 week
2 weeks
6 weeks
4 weeks
Rate this question:
PUR
ED leaders
PE
Z division
Rate this question:
After the original plan date (target at most 2 weeks after)
Never
Before the original plan date (target at least 2 weeks before)
Rate this question:
6 weeks
5 weeks
1 week
3 weeks
Rate this question:
TENIS
DCSI/Excel tracking file
SMS BR
N-SMS
Rate this question:
RDDP
TIS
RAD
ASA
Rate this question:
PE
PUR
SED
PPM
Rate this question:
TMC EDM
QD
PUR
Z
Rate this question:
ASA
EDM
RDDP
RAD
Rate this question:
Cost target
Kick-off meeting target
Off-Process target
Off-Tool target
Rate this question:
True
False
Rate this question:
True
False
Rate this question:
True
False
Rate this question:
True
False
Rate this question:
True
False
Rate this question: