Project Quality Management MCQs Quiz

Approved & Edited by ProProfs Editorial Team
The editorial team at ProProfs Quizzes consists of a select group of subject experts, trivia writers, and quiz masters who have authored over 10,000 quizzes taken by more than 100 million users. This team includes our in-house seasoned quiz moderators and subject matter experts. Our editorial experts, spread across the world, are rigorously trained using our comprehensive guidelines to ensure that you receive the highest quality quizzes.
Learn about Our Editorial Process
| By Daina
D
Daina
Community Contributor
Quizzes Created: 1 | Total Attempts: 15,179
Questions: 10 | Attempts: 15,240

SettingsSettingsSettings
Project Quality Management MCQs Quiz - Quiz

Here, we have brought this "Project quality management MCQs quiz." Do you know some of the important concepts of project quality management? One can easily come up with a plan for a project, follow it, and still fail at attaining the right quality leading to failure of a project. This quiz will help you learn how to ensure that all aspects needed to make a project successful and worthwhile are met.


Questions and Answers
  • 1. 

    TQM stands for

    • A.

      Team Quality Management

    • B.

      Total Quality Managers

    • C.

      Team Quality Managers

    • D.

      Total Quality Management

    Correct Answer
    D. Total Quality Management
    Explanation
    PMBOK, p. 180.

    Rate this question:

  • 2. 

    The cost of quality refers to

    • A.

      The cost to put quality systems and checks in place.

    • B.

      The additional cost to make better products or services.

    • C.

      The total cost of all efforts related to quality.

    • D.

      None of the above.

    Correct Answer
    C. The total cost of all efforts related to quality.
    Explanation
    PMBOK, p. 181.

    Rate this question:

  • 3. 

    Quality Control is

    • A.

      Evaluating overall project performance to ensure the project will satisfy the relevant quality standards.

    • B.

      Identifying the relevant quality standards to the project and how to satisfy them.

    • C.

      Monitoring specific project results to ensure that they comply with the relevant quality standards while identifying ways to improve overall quality.

    • D.

      None of these

    Correct Answer
    C. Monitoring specific project results to ensure that they comply with the relevant quality standards while identifying ways to improve overall quality.
    Explanation
    Week 10 Powerpoint slide #3

    Rate this question:

  • 4. 

    Quality Assurance is

    • A.

      Evaluating overall project performance to ensure the project will satisfy the relevant quality standards.

    • B.

      Identifying the relevant quality standards to the project and how to satisfy them.

    • C.

      Both of these

    • D.

      None of these

    Correct Answer
    A. Evaluating overall project performance to ensure the project will satisfy the relevant quality standards.
    Explanation
    Week 10 Powerpoint slide #3

    Rate this question:

  • 5. 

    Which of the following is NOT a tool for Quality Planning?

    • A.

      Pareto Diagram

    • B.

      Benchmarking

    • C.

      Design of Experiments

    • D.

      Cost-Benefit Analysis

    Correct Answer
    A. Pareto Diagram
    Explanation
    PMBOK, p. 185.
    Pareto Diagrams, used for Quality Control, are covered on p. 195.

    Rate this question:

  • 6. 

    The Quality Management Plan must address

    • A.

      Quality Control for the project.

    • B.

      Quality Assurance for the project.

    • C.

      Continuous Process Improvement for the project .

    • D.

      All of the above.

    • E.

      None of the above.

    Correct Answer
    D. All of the above.
    Explanation
    PMBOK, p. 186.

    Rate this question:

  • 7. 

    In the context of Project Quality Management, a scatter diagram is a

    • A.

      Quality Control tool or technique

    • B.

      Quality Control output

    • C.

      Quality Assurance tool or technique

    • D.

      Quality Assurance output

    • E.

      Quality Planning tool or technique

    Correct Answer
    A. Quality Control tool or technique
    Explanation
    PMBOK, p. 196.

    Rate this question:

  • 8. 

    Which of the following statements is true?

    • A.

      The skills of the worker who is directly involved in the production of the product or service have the most influence over quality.

    • B.

      Quality only has a cost when it is poor, and the rework is necessary.

    • C.

      It is important for leadership to promote quality.

    • D.

      Quality should first be considered during the "controlling" phase of a project.

    Correct Answer
    C. It is important for leadership to promote quality.
    Explanation
    Week 10 PowerPoint slides # 12-13.

    Rate this question:

  • 9. 

    When a defect is discovered and corrected before product delivery, this is considered what kind of quality cost?

    • A.

      Prevention cost

    • B.

      Appraisal cost

    • C.

      Internal Failure cost

    • D.

      External Failure cost

    • E.

      Measurement and Test Equipment cost

    Correct Answer
    C. Internal Failure cost
    Explanation
    Week 10 PowerPoint slide # 15.

    Rate this question:

  • 10. 

    When doing Quality Planning, the following need to be considered, except:

    • A.

      The Project Scope Statement

    • B.

      The Project Network Diagram

    • C.

      Rules, standards, or guidelines that relate to the product or service

    • D.

      Procedures, standards, or guidelines that pertain to the organization

    Correct Answer
    B. The Project Network Diagram
    Explanation
    PMBOK, p. 184

    Rate this question:

Quiz Review Timeline +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 22, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Mar 07, 2009
    Quiz Created by
    Daina
Back to Top Back to top