PMP Quiz 2 (50 Questions)

Reviewed by Editorial Team
The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Agilep3
A
Agilep3
Community Contributor
Quizzes Created: 9 | Total Attempts: 9,869
| Attempts: 395 | Questions: 94
Please wait...
Question 1 / 94
0 %
0/100
Score 0/100
1. You are the project manager for a software development project. When you need to get staff from the manager of the QA department, he suggests a few test engineers with performance problems for your team. Which is the BEST response to this situation?

Explanation

B- You need to figure out the root cause of the problem if you are going to find a lasting solution to it.

Submit
Please wait...
About This Quiz
PMP Quizzes & Trivia

This PMP Quiz 2 features 50 questions covering key project management concepts as defined in PMBOK, focusing on organizational systems, progressive elaboration, initiating processes, triple constraint, conflict sources, and scope statements.

Tell us your name to personalize your report, certificate & get on the leaderboard!
2. Why is it important to have a staff release plan for people within the project team?

Explanation

D - A staff release plan provides a clean break point for an individual and saves the project money in the process.

Submit
3. In which plan do you define the processes that will be used to keep people informed throughout the project?

Explanation

D- The Communications Management Plan defines all of the processes that will be used for communication on the project.

Submit
4. You are a project manager on a construction project. You have just prepared an RFP to send around to electrical contractors. You get a call from your uncle who owns an electrical contracting company. He wants to bid on your project. You know he's done good work before, and it may be a good fit for your company. How do you proceed?

Explanation

B- Any time there’s a conflict of interest, it’s your duty to disclose it to your company. After that, you should always proceed based on your company’s policies.

Submit
5. A hierarchical structure of resources organized by resource type category and resource type used in resource leveling schedules is known as:

Explanation

D - The Resource Breakdown Structure is a hierarchical structure of resources by resource category and resource type used in resource leveling schedules and to develop resource-limited schedules. This may also be used to identify and analyze project human resource assignments.

Submit
6. Which of the following is NOT a stakeholder?

Explanation

B- A stakeholder is anyone who is affected by the cost, time, or scope of your project. And that includes Unions

Submit
7. You have been asked to establish a project charter for your new project. According to PMBOK, who normally has the responsibility to authorize the charter?

Explanation

B - The project initiator or sponsor external to the project authorizes the project charter. However, a project manager should be involved in the process as early as possible.

Submit
8. You are the project manager on a construction project. As you're planning out the work your team will do, you divide up all of the work into work packages and create a WBS that shows how they fit into categories. For each one of the work packages, you write down details such as initial estimates and information about what account it should be billed against. Where do you store all of that information?

Explanation

C- The WBS Dictionary is the companion document to the WBS. It gives all the details that you know about each work package in the WBS, including estimates and billing information.

Submit
9. A project manager is just finishing a project that has not gone well. Apart from cost overruns and schedule overruns, there have been a lot of quality defects and the project required a lot of senior management intervention to finally reach completion. The project manager should now:

Explanation

D - A project manager has a professional responsibility to conduct lessons learned sessions for all projects with key internal and external stakeholders, particularly if the project yielded less than desirable results.

Submit
10. If you want to have multiple vendors bid on your contract, what is the best way to ensure that all vendors have the same information before bidding?

Explanation

B - A bidder's conference is a good way to ensure all bidders have the same information at the same time and to ensure fairness and equity within the bidding process.

Submit
11. Tom is the project manager of an accounting project. He has just finished defining the scope for the project and is creating the WBS. He goes to his organizational process asset library and finds a WBS from a past project to use as a jumping off point. Which of the following describes the asset that Tom is using?

Explanation

D- Tom is using a Template. As your company completes projects, the documents created along the way are stored in an Organizational Process Asset library.

Submit
12. A team member approaches you with a change that could cut your schedule down by a month. What is the first thing you should do?

Explanation

C- Just because the change will help the project’s timeline doesn’t mean that it will be an overall benefit to the project. It’s important to check how the project will impact the other two constraints as part of your change request.

Submit
13. If you have an unresolved issue while working on a project, what is the best way to communicate that issue?

Explanation

C - An issue log allows you to communicate, track, and resolve project issues.

Submit
14. A project manager is reporting the final status of the closed contract to the stakeholders. Which form of communication is appropriate?

Explanation

C- All project reports must be communicated as formal written documents. Not only that, but anything that has to do with a contract DEFINITELY needs to be formal written.

Submit
15. You have just delivered a product to your client for acceptance, when you get a call that some features they were expecting are missing. What's the first thing you should do?

Explanation

D- You can’t do anything about the problem until you understand it. You should meet with the client to get a better understanding of what went wrong and why the product is not meeting their needs.

Submit
16. What is the main output of the Define Scope process?

Explanation

D- The Project Scope Statement builds defines the scope of work for the project. It’s where everyone comes to a common understanding about the work that needs to be accomplished on the project.

Submit
17. You have recently been assigned to be the project manager for a project that is already underway (the previous project manager has been moved to a different project). As you begin to learn about the project, you realize that a project charter was never established. What should you do?

Explanation

C - Even if done late, a project charter can help establish the legitimacy of a project and should be completed as soon as possible.

Submit
18. Which of the following is NOT a type of communication ?

Explanation

D- Noise is something that interferes with communication. It’s not a communication type.

Submit
19. Project scope, time, and cost are often referred to as the:

Explanation

B - Project quality is affected by balancing project scope, time, and cost. High quality projects deliver the required product, service, or result within scope, on time, and within budget.

Submit
20. A notice sent to a subcontractor about the contract is an example of which kind of communication?

Explanation

B- Anytime you have any communication having to do with the contract, it’s always formal written communication.

Submit
21. As an external vendor, you are managing a complex software project that has been contracted on Time & Material (T&M). One of your team- members reports a break-through in automating some of the testing activities. This will potentially result in cost savings to the project as well as the project getting completed ahead of schedule by a month. Which of the following actions would you take?

Explanation

C - A project manager should always communicate an accurate statement of the project status. There could be subsequent actions to discuss how the savings could be best utilized, whether there can be any cost sharing etc - but they would need to done following the appropriate procedure.

Submit
22. Midway through a project, a project manager determined that the project was running way behind schedule. If the project manager needs to now shorten the project schedule, without changing the project scope, which of the following schedule compression techniques could be applied?

Explanation

A - Crashing is the technique that can be applied to compress the project schedule without changing the project scope. The other technique is Fast tracking.

Submit
23. If you want to reduce the number of quality inspections and thus reduce the cost of quality control for your project, which technique should be used?

Explanation

C - Statistical sampling will provide sufficient inspection to ensure a high likelihood of a quality product, while saving money for the project.

Submit
24. Two efficiency indicators that reflect the cost and schedule performance of a project are:

Explanation

B - The CPI and SPI are two efficiency indicators in the project to reflect the cost and schedule performance of the project.

Submit
25. A project manager is negotiating with a contractor. Neither has a good idea of how long the project will take, or how much the materials will cost. Which contract type is MOST appropriate for this project?

Explanation

B-Time and Materials (T&M) contracts are used in labor contracts. In a T&M contract, the seller pays a rate for each of the people working on the team plus their material costs.

Submit
26. During lunch with a project manager from another department, you are given to understand that it is sufficient to adhere to the applicable Standards for the project. Regulations are not necessarily applicable to projects since they are guidelines and you as PM have the option to decide whether they are applicable or not. Your understanding is that :

Explanation

A - Standards are seen more as guidelines, developed by a recognized body, established by consensus. In contrast, regulations are government imposed requirements. Ex: Building codes are an example of regulation

Submit
27. While creating a project charter, you discover a new project management software tool has come onto the market. You spend the weekend taking an online tutorial to learn about it. This is an example of:

Explanation

D- The PMP Code of Professional Conduct tells us that an important part of any project manager’s career is enhancing personal professional competence. This means increasing your knowledge and applying it so that you can improve your ability to manage projects.

Submit
28. While analyzing a project, the project manager calculated the ratio of the Earned Value (EV) to the Actual Costs (AC) and obtained a value of 1.2. The project manager decided that this was an unfavorable condition to the project and decided to take corrective action. What is your view?

Explanation

C - The project manager is not correct. CPI = Cost Performance Index, and is the ratio of EV to AC. A value greater than 1 is a favorable condition for the project. The project manager has incorrectly interpreted the situation.

Submit
29. During a presentation to management, you want to display the project schedule with only the key deliverables displayed. What is the correct tool for this purpose?

Explanation

C - A milestone chart displays only the key deliverables and is simple and easy to understand.

Submit
30. Which of the following BEST describes the main purpose of the project charter?

Explanation

A- The project charter does several important things: it lays out the project requirements, describes
an initial summary milestone schedule, documents the business case, and identifies initial risks, assumptions, and constraints. But the most important thing that a project charter does is that it identifies the project manager, and assigns him or her the authority necessary to get the job done.

Submit
31. Which of the following is NOT a characteristic of the Project Management Plan?

Explanation

C- The Project Management Plan is not a bar chart (or a Gantt chart). It’s the collection of all of the planning documents you create through all of the knowledge areas within the five process groups.

Submit
32. Which of the following is NOT found in a project charter?

Explanation

C- The procedure for managing changes to a contract is found in the Contract Management Plan.
The other three answers are all things you typically find in a project charter.

Submit
33. As a project manager, you are performing various project performance measurements to assess the magnitude of variation. You then attempt to determine the cause and decide whether corrective action is required. This would be known as:

Explanation

B - This is known as Variance Analysis. As project manager, you would then attempt to determine the cause of the Variance, relative to the scope baseline and then decide on whether corrective action is required.

Submit
34. Project risks should include impacts to project:

Explanation

D - Schedule, cost, quality and performance are often the key factors that risks can impact for a project.

Submit
35. Which of the following statements is correct?

Explanation

A - A portfolio refers to a collection of projects of programs that are grouped together to facilitate their effective management. The projects or programs need not be directly related or interdependent.

Submit
36. Which of the following is NOT a tool or technique of Perform Qualitative Risk Analysis?

Explanation

B- Perform Qualitative Risk Analysis is all about figuring out prioritizing each risk, and figuring out its probability and impact. It’s an important part of risk planning. But it’s not about coming up with
specific numbers!

Submit
37. What does a Cost Performance Index (CPI) of more than 1.0 indicate?

Explanation

C - The CPI is calculated as the earned value divided by the actual cost. An index of greater than one indicates that you have spent less than you forecasted to this point.

Submit
38. If you want to compress a project schedule, what are two of the recommended alternatives to consider?

Explanation

B - Crashing and fast tracking can increase the project's schedule when necessary, but might come at a higher cost and rework potential.

Submit
39. A project manager's primary professional responsibility is towards:

Explanation

C - The project management team's professional responsibilities are not limited to any one of the stakeholders. The other choices are correct but not complete by themselves.

Submit
40. Which of these is NOT a risk diagramming technique?

Explanation

C - Risk diagramming techniques can include: cause and effect diagrams (also known as fishbone diagrams), flowcharts, and influence diagrams.

Submit
41. You are managing a construction project that is currently being initiated. You met with the sponsors, and have started to work on identifying stakeholders. You've documented several key stakeholders and identified their needs. Before you can finish initiating the project, your company guidelines require that you make a rough order of magnitude estimate of both time and cost, so that the sponsor can allocate the final budget.   What's the range of a rough order of magnitude (ROM) estimate?

Explanation

B- A rough order of magnitude (ROM) estimate is an estimate that is very rough. According to the PMBOK® Guide, you should expect a ROM estimate to be anywhere from half (-50%) to one and a half times (+50%) the actual result. That means that if your ROM estimate for a project is six months, then you should expect the actual project to be anywhere from three months to nine months.

Submit
42. Which quality control technique or tool should be used when trying to determine the cause of a major defect?

Explanation

D - A fishbone diagram, also called a cause and effect diagram, helps identify potential causes of an issue or problem.

Submit
43. What is the advantage of preparing an estimate of costs by an outside professional estimator?

Explanation

D - An estimate of costs will serve as a benchmark on proposed responses. Any significant differences in cost estimates can be an indication that the procurement statement of work was deficient, ambiguous or the prospective sellers failed to understand the work.

Submit
44. You have just been authorized to manage a new project for your company. Which of the following BEST describes your first action?

Explanation

D- Since the project charter is what authorizes a project manager to work on a project, it means that the Develop Project Charter process has just been performed. So which of the processes in the list comes next? The other Initiating process: Identify Stakeholders.

Submit
45. A project manager is planning the staffing levels that will be needed through the course of her project. She figures out the number of people that will be needed in each role over time and displays that information in a chart as part of her staffing management plan. What is that chart called?

Explanation

D- A resource histogram is just a way to visualize the number of people in each role that you will need on your project as time goes on.

Submit
46. You have been hired by a contractor, who wants you to manage a construction project for one of their clients. The project team has been working for six weeks. You need to determine whether the team is ahead of or behind schedule. Which of the following tools and techniques is the BEST one for you to consult?

Explanation

A- Performance measurement is what you’re doing when you look at the work that the team is performing in order to determine whether the project is ahead or behind schedule.

Submit
47. Which of the following BEST describes the records management system?

Explanation

A- The records management system is one of the tools that you use in the Close Procurements process. It’s what you use to store your contracts and any related documents, so that future project managers can refer to them in future projects.

Submit
48. A project manager wishes to expand an existing list of sellers. Which of the following techniques should she consider?

Explanation

D - Advertising is a good avenue to expand existing lists of sellers. Advertisements can be placed in general circulation publications in order to achieve this.

Submit
49. Customer satisfaction should be measured at the end of the project to maintain long-term relationships. Which of the following is NOT always an aspect of customer satisfaction?

Explanation

B- Customers can be satisfied even when a project is not profitable—customer satisfaction isn’t always about money.

Submit
50. Which of the following is NOT a tool or technique of Estimate Costs?

Explanation

C- Cost Aggregation is used to build your budget, but it is not a tool for cost estimation. Bottom-up,
Parametric, and Analogous estimation techniques are used for both cost and time estimates.

Submit
51. Paul is a project manager for an industrial design project. The project has a 60% chance of making the company $230,000 over the next year. It has a 40% chance of costing the company $150,000. What's the project's EMV?

Explanation

C- $230,000 x 0.70 = $ 138,000 savings, and $150,000 x 0.40 = -$60,000 expenses. Add them together and you get $78,000.

Submit
52. In a cause and effect diagram, which of these is not a potential cause?

Explanation

B - The potential causes of a specific effect fall into these categories: time, machine, method, material, energy, measurement, personnel, and environment.

Submit
53. Which document describes the project's deliverables and the work required to create those deliverables?

Explanation

B - The project scope statement is the correct response. This document describes the project's deliverables in details and the work that is required to create those deliverables. It also forms the baseline for evaluating whether requests for changes are within or outside the project's boundaries.

Submit
54. A project team member finds that the color scheme of the webpage he is designing appears too gaudy and decides to change it to a mellowed down color scheme. The independent testing team flags this as a defect and there is a heated discussion between the team member and the testing team. What is your view?

Explanation

B - The testing team is correct in their findings. Even though the new color scheme might be a better choice than the old one, all changes need to follow the change management process and go through the appropriate change and approval process.

Submit
55. One way the Close Project or Phase process differs from Close Procurement is:

Explanation

C- When you’re performing the Close Procurements process, you’re closing out work done by a seller for a contract. To do that, you do a few things: you verify that all of the work and deliverables are acceptable, you finalize any open claims, and in case of early termination, you follow the termination clause in the contract.
On the other hand, when you’re performing the Close Project or Phase process, you’re finalizing all of the various activities that you do across all of the process groups, and you’re also verifying that the work and deliverables are complete.

Submit
56. Which of these is an input to the Collect Requirements process?

Explanation

D - The project charter is an input to the Collect Requirements process. The other choices are not valid. Requirement management plan is an output of the Collect Requirements process. [Project Integration

Submit
57. While identifying risks for a new construction project, you discover that a chemical you are using on your building cannot be applied in rainy conditions. You also learn that your project will be ready for the chemical application around the time when most of the rainfall happens in this part of the country. Since the project can't be delayed until after the rainy season and you need to make sure the building gets the chemical coating, you decide that your team will just have to allow enough time in the schedule for non worked rain days. This is an example of which strategy?

Explanation

C- This is an example of accepting a risk. The team can’t do anything about the weather, so the project manager has accepted the fact that they could end up being delayed by it.

Submit
58. The scope baseline consists of:

Explanation

D- The scope baseline is made up of the Project Scope Statement and the WBS and the WBS Dictionary. The WBS Dictionary is considered a supporting document to the WBS, so if the WBS were to change, then the dictionary would, too.

Submit
59. You are managing an accounting project when a new CFO is hired at your company. He'll be affected by all accounting projects in your company. What's the BEST thing for you to do?

Explanation

B- Since the CFO is affected by your project, that means he’s a stakeholder. The best thing you can do in this situation is get the new stakeholder’s opinion incorporated in the project up front.

Submit
60. A company is about to begin work on a large construction project to build four new buildings for a bank that wants to open new branches. The sponsor is writing a project charter. She recalls that a previous project the company performed for another bank ran over budget because the team had underestimated the effort required to install the reinforced walls in the vault. The previous project manager had documented the details of the lessons learned from this project. Where should the sponsor look for these lessons learned?

Explanation

B- Lessons learned from past projects are always part of a company’s organizational process.

Submit
61. At the close of your project, you measure the customer satisfaction and find that some customer needs were not fully met. Your supervisor asks you what steps you took on your project to improve customer satisfaction. Which subsidiary plan would you consult to determine this information?

Explanation

A- Customer satisfaction is an important part of modern quality management. Remember, customer satisfaction is about making sure that the people who are paying for the end product are happy with what they get.

Submit
62. Which of the following statements is not true about a subproject?

Explanation

B - A subproject is not necessarily the smallest unit. On very large projects, the subproject can further consist of a series of even smaller projects.

Submit
63. You're managing an industrial design project. Your project is currently in the Initiating phase. The project charter has been created, and you are working on identifying the stakeholders. Which of the following is NOT something that you should do?

Explanation

D- You don’t create the change control system in the Initiating phase—that’s something that you do as part of your project planning activities.

Submit
64. Which of the following is NOT an input of the Close Project or Phase process?

Explanation

B- The project management methodology describes the process (or lifecycle) that you use to manage your project. It really doesn’t have anything to do with closing a project or phase.

Submit
65. Which is the BEST description of project scope?

Explanation

D- Product scope means the features and functions of the product or service being built.

Submit
66. Organizations can be categorized according to their operations style. Which two types of organizational systems are recognized by the PMBOK?

Explanation

A - Project-based organizations are those whose operations consist primarily of projects. Non-project based organizations often may lack management systems designed to support project needs efficiently and effectively.

Submit
67. You are initiating project that has a virtual team. Half of your team members will be located in another country, where they are working for a subcontractor. The subcontractor's team members speak a different dialect of English than your team does. After a conference call to review the project charter, two of your team members make jokes about the way your subcontractor's team members speak. What is the BEST way to handle this situation?

Explanation

A- Sexism, racism, or other discrimination should never be tolerated, no matter what the circumstances.

Submit
68. When are the most expensive defects most likely to be introduced into a product?

Explanation

B- The most expensive defects are the ones introduced when the product is being designed.

Submit
69. You are developing the project scope statement for a new project. Which of the following is NOT part of creating a project scope statement?

Explanation

A- Verify Scope is the Monitoring & Controlling process for the Scope Management knowledge area. It doesn’t have anything to do with planning out the scope of the project—you do it as you complete
each project phase to make sure that your team has completed all of the project work.

Submit
70. On obtaining the project charter, the project manager of a project immediately put together the project team to execute the project. Is this correct?

Explanation

D - No, the project team is not acquired immediately after signing of the project charter. Acquisition of a project team starts with HR planning in the Planning process group, followed by the Acquisition of the team in the Execution phase. The other answers are wrong because the Acquisition of the project team is mentioned in the wrong phase. It is also not the responsibility of the Project Sponsor to provide the team for execution.

Submit
71. Defining the requirements for a new product is what type of activity?

Explanation

A - The Initiating process group consists of the processes performed to define a new project or a new phase of an existing project by obtaining authorization to start the project of phase.

Submit
72. Which of the following is NOT a tool in Identify Risks?

Explanation

B- Risk Urgency Assessment is a tool of Perform Qualitative Risk Analysis. Identify Risks is all about finding risks. Perform Qualitative Risk Analysis is about ranking them based on what your team thinks their impact and probability will be for your project.

Submit
73. Which of the following is inaccurately represented by the term Progressive elaboration?

Explanation

A - The distinction between Progressive elaboration and Scope Creep needs to be understood since the two terms are different. The changes to scope (especially in an uncontrolled manner) are called scope creep. In contrast, Progressive elaboration involves building on, or elaborating the output of a previous phase.

Submit
74. Which enterprise environmental factor defines how work is assigned to people?

Explanation

D- The work authorization system is a part of your company’s Enterprise Environmental Factors, and it’s generally part of any change control system.

Submit
75. Configuration Status Accounting is an activity that is performed as part of which process?

Explanation

D - Configuration Status Accounting is a key configuration management activity and is done as part of the Perform Integrated Change Control process

Submit
76. A project manager is working in a country where it is customary to pay the police for private protection services, and those costs have increased the AC. This has affected his earned value calculations. When he reviews the budget with his company's management, his supervisor tells him that in another country, those costs would be considered a bribe, and questions whether they should be added to the budget. What is the BEST way for the project manager to proceed?

Explanation

B- Some questions on the exam might ask you about how to operate in another country. In this case,
the question is about whether or not something is a bribe. Clearly, if it’s a bribe, you can’t pay it. But is it? If a payment to a government official (or anyone else) is customary, then it’s not a bribe. You
should go ahead and pay the police—as long as it’s acceptable and legal in that country.

Submit
77. Which of the following contracts has the MOST risk for the buyer?

Explanation

B- Of all of the contract types listed in the question, the Time & Materials (T&M) contract is the riskiest kind of contract for the buyer, because if the cost of the materials gets really high then they’re passed along to the buyer—and the seller doesn’t have any incentive to keep them down!

Submit
78. Fill in the blank: _______________ means developing in steps and continuing by increments.

Explanation

D - Progressive elaboration is a characteristic of projects that allows a project management team to manage it to a greater level as the project evolves.

Submit
79. Joe is a project manager on an industrial design project. He has found a pattern of defects occurring in all of his projects over the past few years and he thinks there might be a problem in the process his company is using that is causing it. He uses Ishikawa diagrams to come up with the root cause for this trend over projects so that he can make recommendations for process changes to avoid this problem in the future. What process is he doing?

Explanation

B- Joe is doing root-cause analysis on process problems: that’s Perform Quality Assurance.

Submit
80. Which of the following is not a general management technique used to generate different approaches to execute and perform the project work?

Explanation

C - Alternatives Identification concerns itself with identifying techniques to generate different approaches to execute and perform the work of the project. Map-Out is not a valid technique - the other three namely Brainstorming, Lateral thinking and Six Thinking Hats are techniques used to generate ideas for different approaches.

Submit
81. Which of these tools is NOT part of the Seven Basic Tools of Quality?

Explanation

B - The seven basic tools of quality are: cause and effect diagrams, control charts, flowcharting, histograms, pareto charts, run charts, and scatter diagrams.

Submit
82. Which of the following is NOT a tool of the Define Scope process?

Explanation

B- Constrained Optimization doesn’t have anything to do with Define Scope—it’s a kind of benefit selection method.

Submit
83. You are managing a software project. You are partway through the project, and your team has just delivered a preliminary version of part of the software. You are holding a weekly status meeting, when one of the team members points out that an important stakeholder is running into a problem with one of the features of the current software. The team member feels that there is a risk that the stakeholder will ask for a change in that feature, even though that change would be out of scope of the current release—and if the stakeholder requests that change, there is a high probability that the change control board would approve the change. What is the BEST action to take next?

Explanation

C- Your risk register is one of the most important project management tools that you have—that’s why you review it and go over your risks at every meeting.

Submit
84. As project manager, you would like to show the relationship between two variables to help your project team understand the quality impacts better. Which tool should be used?

Explanation

A - A scatter diagram plots several occurrences of two variables (one on each axis). A relationship can then often be determine between the two variables based on how closely they fit a geometric model.

Submit
85. The date through which the project has provided actual status and accomplishments is called:

Explanation

A - The date through which the project has provided actual status and accomplishments is called as Data Date. It is also known as as-of Date or status Date

Submit
86. Which is NOT an example of cost of quality?

Explanation

D- Any activity that helps you find, prevent or fix defects in your product is included in the cost of quality.

Submit
87. When is the BEST time to have project kickoff meetings?

Explanation

C- If your project is broken up into phases, you should have a kickoff meeting at the start of each phase.

Submit
88. Where would you find a detailed list and description of specific project assumptions associated with the project?

Explanation

B - The Project scope statement lists and describes the specific project assumptions associated with project scope and the potential impact of those assumptions if they prove to be false. The assumptions listed in the detailed project scope statement are typically more numerous and detailed than the project assumptions listed in the project charter.

Submit
89. Which of these is not one of the tools and techniques recommended in the Control Schedule process?

Explanation

B - Expert Judgment is not used as a tool and technique in the Control Schedule process since the focus is on current project performance.

Submit
90. When do you perform stakeholder analysis?

Explanation

A- Stakeholder Analysis is one of the tools and techniques of the Identify Stakeholders process.

Submit
91. Which of the following is not a tool or technique of the Perform Quality Control process?

Explanation

B- Quality audits are when your company reviews your project to make sure that you are following all of the processes in your company correctly. They are a tool of the Perform Quality Assurance process.

Submit
92. The terms of union contracts are considered ______________ in your project plan.

Explanation

B- When you work with a union then the union contract can have an impact on your project. That means you need to consider the union itself a stakeholder, and when you do your planning you need to make sure any union rules and agreements are considered as constraints.

Submit
93. Which of the following is NOT one of the most common sources of project conflict?

Explanation

D- It’s important to know that resources, schedules, and priorities cause 50% of project problems
and conflicts.

Submit
94. Which of the following is NOT an input to Perform Quality Control?

Explanation

D- The most important part of the Perform Quality Control process is that your team has to inspect each deliverable in order to verify that it meets its requirements.

Submit
View My Results

Quiz Review Timeline (Updated): Feb 26, 2024 +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Feb 26, 2024
    Quiz Edited by
    ProProfs Editorial Team
  • Mar 05, 2013
    Quiz Created by
    Agilep3
Cancel
  • All
    All (94)
  • Unanswered
    Unanswered ()
  • Answered
    Answered ()
You are the project manager for a software development project. When...
Why is it important to have a staff release plan for people within the...
In which plan do you define the processes that will be used to keep...
You are a project manager on a construction project. You have just...
A hierarchical structure of resources organized by resource type...
Which of the following is NOT a stakeholder?
You have been asked to establish a project charter for your new...
You are the project manager on a construction project. As you're...
A project manager is just finishing a project that has not gone well....
If you want to have multiple vendors bid on your contract, what is the...
Tom is the project manager of an accounting project. He has just...
A team member approaches you with a change that could cut your...
If you have an unresolved issue while working on a project, what is...
A project manager is reporting the final status of the closed contract...
You have just delivered a product to your client for acceptance, when...
What is the main output of the Define Scope process?
You have recently been assigned to be the project manager for a...
Which of the following is NOT a type of communication ?
Project scope, time, and cost are often referred to as the:
A notice sent to a subcontractor about the contract is an example of...
As an external vendor, you are managing a complex software project...
Midway through a project, a project manager determined that the...
If you want to reduce the number of quality inspections and thus...
Two efficiency indicators that reflect the cost and schedule...
A project manager is negotiating with a contractor. Neither has a good...
During lunch with a project manager from another department, you are...
While creating a project charter, you discover a new project...
While analyzing a project, the project manager calculated the ratio of...
During a presentation to management, you want to display the project...
Which of the following BEST describes the main purpose of the project...
Which of the following is NOT a characteristic of the Project...
Which of the following is NOT found in a project charter?
As a project manager, you are performing various project performance...
Project risks should include impacts to project:
Which of the following statements is correct?
Which of the following is NOT a tool or technique of Perform...
What does a Cost Performance Index (CPI) of more than 1.0 indicate?
If you want to compress a project schedule, what are two of the...
A project manager's primary professional responsibility is...
Which of these is NOT a risk diagramming technique?
You are managing a construction project that is currently being...
Which quality control technique or tool should be used when trying to...
What is the advantage of preparing an estimate of costs by an outside...
You have just been authorized to manage a new project for your...
A project manager is planning the staffing levels that will be needed...
You have been hired by a contractor, who wants you to manage a...
Which of the following BEST describes the records management system?
A project manager wishes to expand an existing list of sellers. Which...
Customer satisfaction should be measured at the end of the project to...
Which of the following is NOT a tool or technique of Estimate Costs?
Paul is a project manager for an industrial design project. The...
In a cause and effect diagram, which of these is not a potential...
Which document describes the project's deliverables and the work...
A project team member finds that the color scheme of the webpage he is...
One way the Close Project or Phase process differs from Close...
Which of these is an input to the Collect Requirements process?
While identifying risks for a new construction project, you discover...
The scope baseline consists of:
You are managing an accounting project when a new CFO is hired at your...
A company is about to begin work on a large construction project to...
At the close of your project, you measure the customer satisfaction...
Which of the following statements is not true about a subproject?
You're managing an industrial design project. Your project is...
Which of the following is NOT an input of the Close Project or Phase...
Which is the BEST description of project scope?
Organizations can be categorized according to their operations style....
You are initiating project that has a virtual team. Half of your team...
When are the most expensive defects most likely to be introduced into...
You are developing the project scope statement for a new project....
On obtaining the project charter, the project manager of a project...
Defining the requirements for a new product is what type of activity?
Which of the following is NOT a tool in Identify Risks?
Which of the following is inaccurately represented by the term...
Which enterprise environmental factor defines how work is assigned to...
Configuration Status Accounting is an activity that is performed as...
A project manager is working in a country where it is customary to pay...
Which of the following contracts has the MOST risk for the buyer?
Fill in the blank: _______________ means developing in steps and...
Joe is a project manager on an industrial design project. He has found...
Which of the following is not a general management technique used to...
Which of these tools is NOT part of the Seven Basic Tools of Quality?
Which of the following is NOT a tool of the Define Scope process?
You are managing a software project. You are partway through the...
As project manager, you would like to show the relationship between...
The date through which the project has provided actual status and...
Which is NOT an example of cost of quality?
When is the BEST time to have project kickoff meetings?
Where would you find a detailed list and description of specific...
Which of these is not one of the tools and techniques recommended in...
When do you perform stakeholder analysis?
Which of the following is not a tool or technique of the Perform...
The terms of union contracts are considered ______________ in your...
Which of the following is NOT one of the most common sources of...
Which of the following is NOT an input to Perform Quality Control?
Alert!

Advertisement