Full Length PMP Simulation Test 4 assesses knowledge in project management processes, including TCPI calculations, Pareto diagrams, and integrated change control. It tests understanding of techniques like co-location and evaluates decision-making skills using expected monetary value.
Indirect costs only
Direct as well as Indirect costs
Direct costs only
Staffing costs only
Rate this question:
Ask the project team member to go ahead with the changes.
The changes are documented and they follow the change management process to become an Approved Change request.
Summarize the changes and archive your discussion with the team member as a future record.
Ask the team member to ignore the changes.
Rate this question:
Initiating
Planning
Monitoring & Controlling
Executing
Rate this question:
Scope statement
Communications management plan
Project charter
Organizational plan
Rate this question:
Balanced matrix.
Strong matrix.
Functional.
Weak matrix.
Rate this question:
The PMI WBS and PRINCE2 product breakdown structure (PBS) are effectively the same thing.
The WBS is the same as the organisational breakdown structure (OBS).
The WBS is a deliverable oriented, hierarchical decomposition of the work to be executed by the project team.
The WBS is the bill of materials (BoM) needed to accomplish the work of the project.
Rate this question:
Analogous
Resource-based
Judgment-based
SWAG
Rate this question:
CV=EV-AC
CV=AC-EV
CV=BAC-(AC-EV)
CV=SV-BC
Rate this question:
Fixed Price Incentive Fee
Firm Price Incentive Free
Fixed Price Indicator Factor
Fast Performance Incentive Fee
Rate this question:
Monitoring and controlling
Planning
Executing
Initiating
Rate this question:
Work Item
Workaround
Work Package
Reserve plan
Rate this question:
Has a definite beginning and end
Temporary
Progressively elaborated
Ongoing Effort
Rate this question:
Report the accurate status to your manager and send a separate report stating that each team member was busy for 40 hours
Report this accurately on the status report and ensure that activities are re-planned as necessary, to keep the team completely occupied.
Report on the status report that each team member was busy for 40 hours, and use the time saved for other activities not related to the project.
Avoid mentioning these kinds of savings on status reports.
Rate this question:
The project charter
The project scope
The project budget.
The project kickoff
Rate this question:
An Organizational Breakdown Structure (OBS)
A Department Breakdown Structure (DBS)
A Resource Breakdown Structure (RBS)
A Hierarchical Breakdown Structure (HBS)
Rate this question:
Its primary use is to authorise the start of a project or phase.
It provides the project manager with authority to apply resources and expend money on project activities.
Its primary use is to request bids or proposals for the work it defines.
The project charter can be created by the person external to the project, responsible for the authorisation of the work, or that person can delegate the creation of the project charter to the project manager.
Rate this question:
It is an output of the Verify Scope process.
It describes the project’s deliverables and the work needed to create them.
It may contain explicit scope exclusions that can assist in managing stakeholder expectations.
It provides a common understanding of the project’s scope among the project’s stakeholders.
Rate this question:
The cost of correcting mistakes through an inspection is much lesser than the cost of preventing them.
The cost of preventing mistakes is generally much lesser than the cost of correcting them as revealed by inspection.
It does not matter where a defect is captured as long as the finished work product does not have a defect.
The cost of correcting mistakes through an inspection is more or less that same as the cost of preventing them since the same effort goes into both activities.
Rate this question:
Free Float
Lead Float
Total Float
Lag Float
Rate this question:
A conversation with a team member from a similar project that failed in the past.
Project Scope statement from the project planning process.
An article from PM Network Magazine
Resource plan from the project planning process
Rate this question:
A constraint
A necessity
A choice
An assumption
Rate this question:
Balanced Matrix
Functional
Strong Matrix
Projectized
Rate this question:
Buying professional indemnity insurance.
The cost of defects and rework caused by failing to achieve requirements.
The cost of inspecting and appraising conforming products produced by the project.
Preventing non-conformance to requirements.
Rate this question:
Sharing
Mitigation
Transference
Avoidance
Rate this question:
Source Activities
Estimate Activity Resources
Define Activities
Sequence Activities
Rate this question:
Perform Integrated Change Control
Direct and Manage Project Execution
Develop Project Management Plan
Monitor and Control Project Work
Rate this question:
Levelized Billing
Funding Limit Reconciliation
A financial review
Rescheduling
Rate this question:
AC + (BAC – EV)
(BAC - EV)/(BAC - AC)
BAC/CPIcum
(BAC - EV)/(EAC - AC)
Rate this question:
Based on expert judgement and is consequently more accurate than standard critical path estimating.
Used when there is a limited amount of detailed information available.
A calculation based on a three point estimate using a modified BETA distribution.
The same as ‘bottom up’ estimating.
Rate this question:
Contingent Response Strategy
Active acceptance
Passive acceptance
Avoidance
Rate this question:
15 stakeholders
6 stakeholders
8 stakeholders
105 stakeholders
Rate this question:
Critical resources
Hammock Activity
Direct activity
Resource Identifier
Rate this question:
Project plan updates.
Expert judgement.
Change control meetings.
A change control board to approve or reject changes.
Rate this question:
Time and Material contract
Cost-Plus-Fixed-Fee contract
Cost-Plus-Incentive-Fee contract
Fixed-price contract
Rate this question:
RACI Chart
Issue Log
Risk Register
Project Performance Appraisals
Rate this question:
A resource breakdown structure
A scope baseline
A bill of materials
A WBS dictionary entry
Rate this question:
It is a technique to reduce bias and prevent any one person from exerting undue influence.
It is a way to reach a consensus of experts.
It is an Oracle® database application used to optimise future outcomes.
Individual experts are unaware of who else is participating in the process.
Rate this question:
Cost-Plus-Fixed-Fee contract
A Time and material contract
Lump sum contract
Cost-Plus-Fee contract
Rate this question:
Resource Leveling
Fast Tracking
Crashing
Risk Transference
Rate this question:
Work breakdown structure
Deconstruction
Tasking
Decomposition
Rate this question:
A schedule network analysis
An arrow diagram
A backward pass
A forward pass
Rate this question:
A. Delete the requirements in question. if a requirement in not measurable, it is not valid
B. Notify project stakeholders that the requirements have not been elaborated adequately,and must be reviewed by the team?
C. Request a contract modification on the basis of invalid requirements.
D. Modify the text of the requirements yourself.If a requirement is not measurable ,it is not valid.
Rate this question:
Performing activities in accordance with the project management plan.
Managing changes to the deliverables.
Completing the work in accordance with the defined quality framework and specification.
Coordinating people and resources.
Rate this question:
Is the system used to keep track of purchases and contracts.
Is any numbering system used to uniquely identify each component of the work breakdown structure.
Links the work breakdown structure to the schedule task identifier.
Is the alpha-numeric reference used in the organisations accounts system to identify cost centres.
Rate this question:
Maslow.
McGregor.
Hertzberg.
Deming.
Rate this question:
Talk to the customer about the impact of the change
Change the risk management plan
Include the expected monetary value of the risk in the new cost estimate
Analyze the impacts of the change with the team
Rate this question:
Decision tree analysis is more effective using net present values (NPV) in its calculations rather than EMV.
The EMV of an opportunity is generally a positive value.
EMV is a statistical concept that calculates the average value of a future scenario that may, or may not happen by multiplying the value of each possible outcome by the probability of it occurring and summing the products.
The EMV of a threat is generally a negative value.
Rate this question:
Forecast future performance based on past performance
Calculate the number of days left in the project
Calculate the value provided to the customer
Calculate the profitability of the project
Rate this question:
Quiz Review Timeline (Updated): Mar 21, 2023 +
Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.
Wait!
Here's an interesting quiz for you.