Full Length PMP Simulation Test 2 assesses knowledge in project management, focusing on prototype building, network diagrams, budget analysis, and cost estimation. It prepares learners for PMP certification by testing critical skills and decision-making in realistic project scenarios.
15 days
16 days
59 days
14 days
Rate this question:
Your project is under budget
Your SPI is also negative
Your project is above budget
CV cannot be negative and there must be an error in the calculation
Rate this question:
EAC = BAC/CPI
EAC = AC+ETC
EAC = AC+BAC-EV
ETC = EAC-AC
Rate this question:
70%
42%
5%
50%
Rate this question:
Stop the project because you are over budget
Ignore the sunk cost in the decision making process
The SPI is positive, therefore we can continue
Defer the decision to the project control board
Rate this question:
205
10
3
-10
Rate this question:
388
402
397
400
Rate this question:
About 20 hours later
At 7:27pm
At 7:30pm
About 40 hours later
Rate this question:
298
300
305
295
Rate this question:
100
102
7
2
Rate this question:
1 Sigma
2 Sigma
3 Sigma
4 Sigma
Rate this question:
CHF 500,000
CHF 1,500,000
CHF 2,000,000
CHF 2,500,000
Rate this question:
10
86.5
90
86.2
Rate this question:
15,006
123
7,503
15,129
Rate this question:
We are over budget and ahead of schedule
We are ahead of schedule but under budget
We are over budget and behind schedule
We are behind schedule and under budget
Rate this question:
$399,757
$401,627
$379,597
$397,957
Rate this question:
DKK 100,000
DKK 75,000 - 150,000
DKK 85,000 - 150,000
DKK 95,000 - 110,000
Rate this question:
$400
$144
$240
$86.40
Rate this question:
1 day
2 days
3 days
4 days
Rate this question:
Project Gold with a BCR of 0.9
Project Silver with a CBR of 0.9 and cost of $100,000
Project Diamond with a cost of $100,000 and benefits of $110,000
Project Platinum with a BCR of 1.2
Rate this question:
20%
$240
40%
$140
Rate this question:
2
8
16
17
Rate this question:
20%
40%
2/15th
4/15th
Rate this question:
1
10
11
12
Rate this question:
CHF 170,000 to CHF 300,000
CHF 110,000 to CHF 300,000
CHF 190,000 to CHF 220,000
CHF 180,000 to CHF 250,000
Rate this question:
Project Gold with a total of 213,000 profit at the end of year 4
Project Silver with a total of 97,000 profit at the end of year 1
Project Bronze with a total of 128,000 profit at the end of year 2
Project Leather with a total of 168,000 profit at the end of year 3
Rate this question:
1,452,500
2,250,000
1,312,500
1,550,000
Rate this question:
3.16 days
146.5 days
64.8 days
10.2 days
Rate this question:
£81,900
5
£94,000
£82,000
Rate this question:
These projects are exactly equal in benefits.
Project Gold has a PV that is about €33,000 higher than Project Silver
Project Silver is more attractive than Project Gold and should be undertaken
Project Silver has a PV that is about €25,000 higher than Project Gold
Rate this question:
1.03
-3
3
8
Rate this question:
Mean = n * (n-1) /2
Mean = (Pessimistic - Optimistic) / 6
Mean = (45 + 49 + 48 + 50 + 52 + 49 + 48 + 50 + 46) / 9
Mean = √sum (45 + 49 + 48 + 50 + 52 + 49 + 48 + 50 + 46) / 9
Rate this question:
ETC = 30,000, when EAC = 100,000 and AC = 70,000
ETC = 120,000, when BAC = 100,000 and EV = 20,000
ETC = 110,000, when BAC = 125,000 and EV = 25,000 and CPI = 1.1
ETC = 70,000, when BAC = 100,000 and AC = 30,000
Rate this question:
68.26%
95.46%
99.73%
99.99%
Rate this question:
The project is ahead of schedule and on budget
The project is on schedule and below budget
The EAC is incorrect
The project is behind schedule and on budget
Rate this question:
2,000
-8,000
-6,100
-4,500
Rate this question:
7 days
10 days
13 days
16 days
Rate this question:
CV = -25,000 , SV = +30,000
CV = -25,000 , SV = -30,000
CV = +25,000 , SV = +30,000
CV = +25,000 , SV = -30,000
Rate this question:
Internal Rate of Return
Present value
Pareto Analysis
Benefit Cost Ratio
Rate this question:
Company A: 8,000 m2 of production space and 500 m2 of pallet storage
Company B: 8,000 m2 of production space and 250 m2 of pallet storage
Company C: 8,000 m2 of production space and 150 m2 of pallet storage
Company D: 8,000 m2 of production space and 0 m2 of pallet storage
Rate this question:
Cannot be calculated based on these numbers
-7
-6
7
Rate this question:
¥17,000,000
¥15,000,000
-¥2,000,000
¥2,000,000
Rate this question:
Preliminary Estimate
Definitive Estimate
Order of Magnitude Estimate
Final Estimate
Rate this question:
491,761
454,545
189,761
476,190
Rate this question:
The cost of the work to be performed to finish the project
The value of the work that has already been performed
The cost of the work that was completed
The expected total cost of our project once it is finished
Rate this question:
Constraints
Exclusions
Deliverables
Provisions
Rate this question:
Project Scope Evolution
Delayed Planning
Rolling Wave Planning
Time Delayed Decomposition
Rate this question:
Scope Management plan
Procurement Management plan
Project Body of Knowledge
Communications Management Plan\\
Rate this question:
Quiz Review Timeline (Updated): Mar 21, 2023 +
Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.
Wait!
Here's an interesting quiz for you.