Full Length PMP Simulation Test 2 assesses knowledge in project management, focusing on prototype building, network diagrams, budget analysis, and cost estimation. It prepares learners for PMP certification by testing critical skills and decision-making in realistic project scenarios.
An S-curve
An inverted S curve.
Pie-chart
A Z curve
Rate this question:
Slow down work on the project to have it finish on schedule.
Continue the work within the project's scope and possibly finish ahead of schedule.
Exaggerate his experience to the sponsor to try to get a project manager position for him on other upcoming projects.
Inform the client the project is behind schedule and it will have to be extended.
Rate this question:
High probability, Low probability, Most likely
Best-case, Worst-case, Mean
Most likely, Most dangerous, Average
Most likely, Optimistic, Pessimistic
Rate this question:
Middle stage
Influence is similar at all stages
Final stage
Initial stage
Rate this question:
Closing
Monitoring and Controlling
Planning
Executing
Rate this question:
The Organization HR manual
The Project Charter
The PMBOK
The Scope statement
Rate this question:
Planning, Monitoring and Controlling, Initiating, Executing, Closing
Planning, Initiating, Executing, Monitoring and Controlling, Closing
Initiating, Monitoring and Controlling, Planning, Executing, Closing
Initiating, Planning, Executing, Monitoring and Controlling, Closing
Rate this question:
15,006
123
7,503
15,129
Rate this question:
Internal Rate of Return
Present value
Pareto Analysis
Benefit Cost Ratio
Rate this question:
Executing
Monitoring and Controlling
Planning
Time Management
Rate this question:
Finish to Finish
Start to Finish
Start to Start
Finish to Start
Rate this question:
Weak Matrix
Strong Matrix
Functional
Balanced Matrix
Rate this question:
Deming
Crosby
Juran
Pareto
Rate this question:
Project Gold with a BCR of 0.9
Project Silver with a CBR of 0.9 and cost of $100,000
Project Diamond with a cost of $100,000 and benefits of $110,000
Project Platinum with a BCR of 1.2
Rate this question:
2
8
16
17
Rate this question:
SWOT Analysis
Interviewing
Delphi Technique
Brainstorming
Rate this question:
Cost-Reimbursable, Time and Material, Cost plus fixed fee
Fixed Price, Cost-Reimbursable and Lump Sum
Fixed Price, Cost-Reimbursable , Time and material.
Fixed Price, Time and Material, Lump Sum
Rate this question:
-25 to +25 %, Rough Order of Magnitude
-10 to +10 %, Budgetary
-1 to +1 %, Definitive
-50 to +50 %, Rough Order of Magnitude
Rate this question:
Completion Estimate
Original Estimate
Rough Order of Magnitude Estimate
Approximate Estimate
Rate this question:
Project Closure
Perform Integrated Change Control
Direct and Manage Project Execution
Monitor and Control Project Work
Rate this question:
Expert
Analogous Estimating
Bottom Up
Parametric Estimating
Rate this question:
Work Breakdown Structure (WBS)
Stakeholder register
WBS Dictionary
Project Scope Statement
Rate this question:
Sequence Activities
Define Activities
Develop Schedule
Control Schedule
Rate this question:
Regressive Elaboration
Expert Judgment
Progressive Elaboration
Historical Analysis
Rate this question:
Global Team
Virtual Team
Cross Functional Global Team
Diverse Team
Rate this question:
Budget Director
Public Relations Manager
Project Sponsor
Fund Manager
Rate this question:
Operations manager
Project team
Project manager
Project sponsor
Rate this question:
Develop Project Management Plan process
Management Contingency Reserve
Reserve Analysis
Cost Variance
Rate this question:
100
102
7
2
Rate this question:
Mean = n * (n-1) /2
Mean = (Pessimistic - Optimistic) / 6
Mean = (45 + 49 + 48 + 50 + 52 + 49 + 48 + 50 + 46) / 9
Mean = √sum (45 + 49 + 48 + 50 + 52 + 49 + 48 + 50 + 46) / 9
Rate this question:
CV = -25,000 , SV = +30,000
CV = -25,000 , SV = -30,000
CV = +25,000 , SV = +30,000
CV = +25,000 , SV = -30,000
Rate this question:
Crashing
Lead
Fast Track
Lag
Rate this question:
Verify Scope
Perform Quality Control
Accept Scope
Perform Quality Assurance
Rate this question:
Closing
Planning
Executing
Monitoring and Controlling
Rate this question:
Exploit the impact.
Mitigate the risk
Share the risk
Avoid the risk
Rate this question:
Lessons learned session
Project party
Fault-finding session
360 degree session
Rate this question:
Procurement management
Integrations management
Communications management
Execution management
Rate this question:
Expert Judgment
Change Control Board
Project Management Methodology
Perform Integrated Change Control
Rate this question:
Projectized, Functional
Strong Matrix, Organic
Weak Matrix, Pre-existing
Functional, Transactional
Rate this question:
Project Scope Management Plan
Activity List
WBS Dictionary
Project Charter
Rate this question:
2
14
13
28
Rate this question:
Taguchi diagrams
Pareto diagrams
Ishikawa diagrams
Process diagrams
Rate this question:
Acquisition
Coercion
Politics
Negotiation
Rate this question:
16
20
23
60
Rate this question:
PV
SV
EV
CPI
Rate this question:
Your project is under budget
Your SPI is also negative
Your project is above budget
CV cannot be negative and there must be an error in the calculation
Rate this question:
10
86.5
90
86.2
Rate this question:
Project Scope Evolution
Delayed Planning
Rolling Wave Planning
Time Delayed Decomposition
Rate this question:
Quiz Review Timeline (Updated): Mar 21, 2023 +
Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.
Wait!
Here's an interesting quiz for you.