A ______ is a collection of projects or programs grouped together for...
The Cost Performance Baseline is a time-phased budget and is used as a...
A project manager colleague of yours is currently working under...
What are the three-point estimates used during the Estimate Activity...
At which stage, in a typical project, do stake holders have maximum...
Which process group corresponds to the "do" part of the...
A project manager is about to start on a new project. Where would he...
The five process groups should be done in the correct order to achieve...
Your company is holding their annual employee get together. This year...
Your company has a very elaborate project selection method. You use...
PMBOK recognizes five process groups typical of almost all projects....
You are the project manager responsible for building a 100,000 sq ft....
The project managers have maximum authority in which type of...
The Plan-Do-Check-Act (PDCA) cycle as the basis for Quality...
Using the Benefit Cost Ratio, which of the following projects do you...
Your 8-person team is getting support from 2 external consultants. How...
You are meeting with your team, early in the project, and would like...
The three categories into which contracts can be broadly classified...
Lucy is a project manager involved in the Estimate Costs process in...
You are in the initiation phase of your project and believe the...
During your weekly status reports you are reporting the earned value...
You have been asked to provide a somewhat accurate estimate, but not...
Which of these is not a component of the scope baseline that is...
Which of the Project Time Management processes involves identifying...
Rolling wave planning is a form of:
You are working in the US, but have outsourced programming to India...
Project stakeholders are individuals and organizations that are...
The project charter should be authorized by the ______
Although not a separate process in the Project Cost Management...
PV = 100, EV = 105, BAC = 400, AC = 102, CV = 3, ETC = 300, EAC = 407....
Your quality assurance team is doing a review of a process. They find...
You recently installed a new PMIS tool that also allows you to perform...
There are two activities on your schedule, which are: 1) Install...
Accepted deliverables are an input to the Close Project or Phase...
The Manage Project Team process is part of what process group?
An organization wishes to ensure that the opportunity arising from a...
Pierre is a project manager who has just finished a project. This...
Which of the following is not one of the Knowledge Area processes?
You have just returned from the weekly change control board meeting...
Organizations strongly influence the project framework. Which of the...
You are 8 months into a project and you have been given a new resource...
Alan is the project manager of a project with 6 stakeholders. If the...
Cause and Effect diagrams are used to illustrate how various factors...
As part of a new project that you have just started on as project...
Your project team has 25 members. You have a monthly "All hands"...
Which of the following is your estimate for the work that has been...
Your project has a CV of -200. This means:
You have received the following values from your statistical sampling:...
You have been assigned a project where you are responsible for...
Lee is the project manager of a project and is planning responses to a...
The change requests created as an output of the Monitor and Control...
You have met with your project sponsor and have been told that the...
The Develop Project Management Plan process includes which of the...
Project Cost Management is primarily concerned with the cost of...
The Risk Register is a component of the project management plan. It...
You have been assigned as a project manager of a new project to be...
Three strategies that typically deal with negative risks or threats...
Which of the following is least likely to be a project?
You are involved as project manager in a fairly large-sized project....
Inspection shows that roughly 72% of your products are produced defect...
Your earned value analysis shows the following values: EV = 90,000,...
You are assigned to prepare the Procurement Management Plan for a...
The correct sequence of processes in the Risk management area is:
A project is contracted as a Time & Material (T&M) type of...
When writing the roles and responsibilities for team members you...
As a project manager, you periodically do project performance reviews...
You have just sat through an exhausting change control meeting...
How much is the Cost Performance Index?
Your Project has the following 4 tasks:...
You will be reporting to management, for the week of 07/15, that your...
You just found out that a major subcontractor for your project...
You the project manager responsible for building a 100,000 sq ft. data...
You are the project manager for a large petroleum company and are in...
You have been contracted to build a manufacturing plant in Kuala...
John, a project manager, for Code Crashers Inc. has been assigned a...
A process that states how formal verification and acceptance of the...
You are working with your team and are looking at the cost risks in...
The paint on the exotic cars that are manufactured in your plant is...
During a work breakdown structure meeting you have decomposed the...
Lisa is the project manager of a large project. Early on she...
Management Contingency Reserve is identified in which process:
Which of the following is accurate regarding the Estimate Activity...
You are managing a project team that is distributed across global...
An estimating technique that uses a statistical relationship between...
A project is estimated to cost $ 50,000 with a timeline of 50 days....
AC = 100, CPI = 0.9, SPI = 1.1. How much is the Cost Variance?
What information does the EAC contain?
You and your team have diligently been working on a project over the...
You are responsible for measuring the errors in the paint process for...
You work at a software company that authors Material Safety Data...
When does the Close Project or Phase process need to be performed in...
Steve is the project manager of a global project. He finds that of...
You are the project manager managing a project to design a print head...
What does it mean if the Earned Value is equal to Actual Cost?
While the five process groups are typically completed in order, they...
In a Finish to Start relationship between predecessor and successor...
You are working on a large project that has been divided into the...
You estimate that a task will take anywhere from 60 - 70 days to...
What is the EMV of the following event?...
You are in the execution stage of your project and you have been...
You are attempting to estimate the resources required to put the...
You are analyzing the risk in a project and decide to do Sensitivity...
The project management plan can best be described as
You have been identified as the project manager for constructing a...
You are the project manager of the Gutenberg project. One major...
AC = 105, EV = 100, PV = 97, CV = -5. How much is the...
When a project is performed under contract, the contractual provisions...
Which technique among the following will help to improve decision...
You have recently started working at a company as a senior project...
Your company has been chosen to develop a new line of business for a...
As part of your staffing management plan, you have developed a chart...
You are a sponsor of a project that is designed to record phone calls...
As a project manager, you are analyzing a process and looking at the...
Which of the following is an output of the Define Activity process?
Your company owns an asset with an original value of $1,000. This...
You are working with your team and are looking at the cost risks in...
As part of the Define Scope process, a project manager documented the...
A control chart is used to determine whether or not a process is...
You are managing a project to lengthen a runway at a major airport....
You have just received an email from your customer that contains the...
Your project has an SPI of 1.1 and a CPI of 0.9. What does this mean?
In the past you have had issues with stakeholders who come back to you...
A tool that is used for charting human resources is a:
Which of the following Projects will you select?
PV = 100, EV = 105, BAC = 400, AC = 102, CV = 3, EAC = 390. How much...
A new CEO has come into your company and promptly shut down your...
In a project, Activity A has a duration of 4 days and begins on the...
Which of the following inaccurately describes a prototype?
Your sponsor would like to know how long it takes to build the...
You are 3 months into a 9 month project. The project is progressing as...
Which of the following is a control tool that helps the project...
The Administer Procurements process ensures that the seller's...
Your project is exactly half finished. You consult your earned value...
The activity "Pack Container" in your network diagram has an early...
How much is the Estimate to Complete?
You are in the procurement process for a high-tech product that is...
Under which of the following scenarios would you not use a Decision...
Contractual agreements with unions or other employee groups can...
2 hours after a successful project status presentation you get a call...
You are the project manager of the Sterling project. The goal is to...
Your company is constructing a new just in time manufacturing facility...
EV = 105 and SPI = 0.9375. How much is the Schedule Variance (SV)?
Which of the following is not accurate about the initial phase of a...
Report Performance includes information on how resources are being...
You have landed your dream job, as project manager working in an...
What are the outputs of the Plan Procurements process?
You work in the PMO of a mid-sized company. Your PPM tool shows...
Stakeholders have vested interest in the outcome of the project. Which...
Which of the following is not true about the WBS?
Your project is budgeted at £500,000 with a schedule duration of...
Contingency Reserves are estimated costs to be used at the discretion...
You are on the phone with your project sponsor discussing the most...
Calculate the Point of Total Assumption on the following contract:...
Your company owns an asset with an original value of $1,000. This...
Your company has a small staff and due to resource constraints not all...
Which of the following is not a valid instance of Risk Transference?
Which of the following statements best describes Time & Material...
Which of these is not an example of an Information Gathering technique...
You are a consultant specializing in recovery of troubled projects....
You have just been assigned to a new project that is very similar to...
Which of these is accurate regarding the Develop Schedule process?
Your Vice President has asked you what the Estimate at Completion is...
You are about to contract out a project to a service provider. However...
While managing a project, you decide to contract to an external...
How do you calculate the Estimate to Complete?
Which of these are not inputs to the Determine Budgets process?
You have received the following estimates from vendors: Vendor 1:...
One of the configuration management activities in the project involved...
A project is contracted as a Cost- Plus-Incentive-Fee (CPIF) type of...
Analogous Cost Estimating is which of the following?
After the last project meeting your sponsor has asked you to give her...
You are a project manager arranging for some interviewing techniques...
Which of these statements is accurate regarding quality management?
You are an expatriate working in a foreign country and have been asked...
Funding requirements for a project are usually in incremental amounts...
You are in the procurement phase of a government project. You are the...
PV = 100, EV = 105, BAC = 400, AC = 102, CV = 3, ETC = 300, EAC = 407....
Your customer is asking for an order of magnitude estimate. What...
Assuming a 3% interest rate, which of the following projects would you...
You have your project team members record the time they spend on...
As the project manager on the construction of a new hotel you have...
A Probability and Impact Matrix contains risks prioritized according...
The activity "Ship Container" in your network diagram has an early...
PV = 100, EV = 105, BAC = 400, AC = 102, CV = 3, ETC = 300. How much...
You are planning a speed networking event. The idea is to bring 50 top...
A technique that uses a project model to translate the uncertainties...
A variance threshold for costs or other indicators to indicate the...
Your friend Joe is planning to retire 20 years from today. He is...
Which of the following is not an example of a procurement document?
You have successfully passed your PMP and are leading a project to...
As an experienced PMP, you have found that running a WBS meeting is...
Which of the following is accurate regarding Project Integration...
When solving complex problems with the team, what type of...
Your project is mid-way through a delivery schedule. As project...
What is the BEST way to make an accurate forecasting of ETC?
Your company owns an asset with an original value of $5,000. This...
Your customer is asking you for a preliminary estimate. Your numbers...
Your designer has given his resignation. This means that you will be...
You have just returned from the weekly change control board meeting...
You have run away and joined the carnival as a project manager and are...