12 Questions

Settings
PMP Quizzes & Trivia

Questions and Answers
  • 1. 
    The following are all inputs to the Develop Project Charter process except:
    • A. 

      Project Statement of Work

    • B. 

      Business Case

    • C. 

      Contract

    • D. 

      EEF (Enterprise Environmental Factors)

    • E. 

      OPA (Organizational Process Assets)

    • F. 

      Preliminary Scope Statement

  • 2. 
    Which of the following is an output of Develop Project Charter process?
    • A. 

      Project Charter

    • B. 

      Project Management Plan

    • C. 

      Schedule

    • D. 

      WBS and WBS Dictionary

  • 3. 
    All of the following are inputs to the Develop Project Management Plan process except:
    • A. 

      Project Charter

    • B. 

      Outputs from planning process

    • C. 

      EEF (Enterprise Environmental Factors)

    • D. 

      OPA (Organizational Project Assets)

    • E. 

      Define Stakeholders

  • 4. 
    What is an output of Develop Project Management Plan process?
    • A. 

      Project Management Plan

    • B. 

      Project Charter

    • C. 

      Quality Audit

    • D. 

      Contracts

  • 5. 
    All are inputs to the Direct and Manage Project Execution process except:
    • A. 

      Project Management Plan

    • B. 

      Approved Change Requests

    • C. 

      Enterprise Environmental Factors

    • D. 

      Organizational Process Assets

    • E. 

      Statement of Work

  • 6. 
    • A. 

      Deliverables

    • B. 

      Work Performance Information

    • C. 

      Change Requests

    • D. 

      Project Management Plan Updates

    • E. 

      Project Document Updates

    • F. 

      Charter

    • G. 

      Approved Change Requests

    • H. 

      Performance Reports

  • 7. 
    • A. 

      Project Management Plan

    • B. 

      Performance Reports

    • C. 

      Enterprise Environmental Factors

    • D. 

      Organizational Process Assets

    • E. 

      Scope Statement

    • F. 

      Stakeholder Analysis

    • G. 

      Change Requests

  • 8. 
    Which of the following is not an output of the Monitor and Control Project Work process?
    • A. 

      Change Requests

    • B. 

      Deliverables

    • C. 

      Project Management Plan Updates

    • D. 

      Project Document Updates

  • 9. 
    • A. 

      Project Management Plan

    • B. 

      Work Performance Information

    • C. 

      Change Requests

    • D. 

      EEFs

    • E. 

      OPAs

    • F. 

      Project Charter

    • G. 

      Change Control Meetings

    • H. 

      Lessons Learned

  • 10. 
    All are outputs of Perform Integrated Change Control process except:
    • A. 

      Change Request Status Updates

    • B. 

      Project Management Plan Updates

    • C. 

      Project Document Updates

    • D. 

      Deliverables

  • 11. 
    Which of the following are inputs to the Close Project or Phase process?
    • A. 

      Project Management Plan

    • B. 

      Accepted Deliverables

    • C. 

      OPAs

    • D. 

      EEFs

    • E. 

      Change Requests

    • F. 

      Lessons Learned

  • 12. 
    Which of the following are outputs to the Close Project or Phase process?
    • A. 

      Final Product, Service, or Result Transition

    • B. 

      OPA Updates

    • C. 

      Charter

    • D. 

      Change Requests

    • E. 

      Approved Change Requests