This is a cumulative PMP Mock Exam which can be used as a benchmark for your PMP aptitude. This practice test includes questions from all PMBOK knowledge areas, inciuding the five process groups.
A. Always only provide a summary or high level plan
B. Include only the details your manager specifically requested
C. Always provide the maximum level of detail possible
D. Provide the level of detail based on the project complexity and application area
Rate this question:
A. Issue a standard request for bid and do not allow any questions
B. Hold a bidder's conference
C. Communicate only through email
D. Develop a qualified sellers list
Rate this question:
A. 64 channels
B. 56 channels
C. 8 channels
D. 28 channels
Rate this question:
A. Ask one of the systems engineers to install the patch during the next maintenance window
B. Ask the IT manager to install the patch as part of another change request that was approved
C. Argue with the change manager until he relents.
D. Present the change request per company process.If it is denied, escalate the issue to management for assistance and submit an emergency change request.
Rate this question:
A. Company president or CEO
B. Project initiator or sponsor
C. Key project stakeholders
D. Project manager
Rate this question:
A. Not often completed
B. Complete and 100%
C. In-depth and thorough
D. Quick and cost- effective
Rate this question:
A. Scope Analysis
B. Variance Analysis
C. Performing Reporting
D. Configuration Management
Rate this question:
A. Cost Projection Index (CPI) and Schedule Projection Index (SPI)
B. Cost Performance Index (CPI) and Schedule Performance Index (SPI)
C. Actual Cost (AC) and Planned Value (PV)
D. Cost Pricing Index (CPI) and Schedule Performance Index (SPI)
Rate this question:
A. Discuss the issue with the other project manager
B. Do nothing. The corporate methodology permits decisions to be made by a plurality, rather than a majority. A plurality decision is based on the largest block of supporters,even if that block is not a majority.
C. Report the project manager to his or her manager. Requirements must be supported by more than 50% of the team
D. Notify the project sponsor there is a discrepancy and suggest a formal requirements review
Rate this question:
A. Fast Tracking and Schedule Network Analysis
B. Crashing and Fast Tracking
C. Resource leveling and what-if scenario analyiss
D. Crashing and schedule network analysis
Rate this question:
A. Networking
B. Outsourcing
C. Expert Judgement
D. Advertising
Rate this question:
A. Control chart
B. Statistical sampling
C. Flow charting
D. Scatter diagram
Rate this question:
A. Pareto chart
B. Control chart
C. Histogram
D. Fishbone diagram
Rate this question:
A. Delete the requirements in question. if a requirement in not measurable, it is not valid
B. Notify project stakeholders that the requirements have not been elaborated adequately,and must be reviewed by the team?
C. Request a contract modification on the basis of invalid requirements.
D. Modify the text of the requirements yourself.If a requirement is not measurable ,it is not valid.
Rate this question:
Quiz Review Timeline (Updated): Aug 21, 2023 +
Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.
Wait!
Here's an interesting quiz for you.