PMP- Initiating Process Group

Reviewed by Editorial Team
The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Agilep3
A
Agilep3
Community Contributor
Quizzes Created: 9 | Total Attempts: 9,868
| Attempts: 5,134 | Questions: 80
Please wait...
Question 1 / 80
0 %
0/100
Score 0/100
1. Which of the following is an Output of  Develop Project Charter?

Explanation

The output of Develop Project Charter is the Project Charter itself. This document formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. It includes key information such as project objectives, high-level requirements, stakeholders, and initial project risks. The Project Charter is an important document that serves as a reference throughout the project's life cycle and provides guidance to all stakeholders involved in the project.

Submit
Please wait...
About This Quiz
PMP- Initiating Process Group - Quiz

This PMP quiz focuses on the Initiating Process Group, assessing knowledge on handling cultural differences, stakeholder analysis, defect costs, project authorization, and project scope. It prepares learners for... see moreeffective project initiation and management. see less

2. A notice sent to a subcontractor about the contract is an example of which kind of communication?

Explanation

B- Anytime you have any communication having to do with the contract, it’s always formal written communication.

Submit
3. Which of the following are enterprise environmental factors influencing a project's success?

Explanation

D - All the three listed factors are enterprise environmental factors that influence a project's success. Enterprise environmental factors may enhance or constrain project management options.

Submit
4. You have recently been assigned to be the project manager for a project that is already underway (the previous project manager has been moved to a different project). As you begin to learn about the project, you realize that a project charter was never established. What should you do?

Explanation

C - Even if done late, a project charter can help establish the legitimacy of a project and should be completed as soon as possible.

Submit
5. Which of the following describes the Executing process group?

Explanation

The Executing process group is responsible for putting project plans into action. This involves coordinating and managing the resources, tasks, and activities outlined in the project plan. During this phase, the project team carries out the work defined in the plan, and progress is monitored and controlled. Project performance measurements are taken and analyzed in the Monitoring and Controlling process group, not in the Executing process group. Developing project plans and publishing them typically occur in the Planning process group.

Submit
6. Which of the following is NOT a type of communication ?

Explanation

D- Noise is something that interferes with communication. It’s not a communication type.

Submit
7. Which of the following is NOT a stakeholder?

Explanation

B- A stakeholder is anyone who is affected by the cost, time, or scope of your project. And that includes Unions

Submit
8. You have been asked to establish a project charter for your new project. According to PMBOK, who normally has the responsibility to authorize the charter?

Explanation

B - The project initiator or sponsor external to the project authorizes the project charter. However, a project manager should be involved in the process as early as possible.

Submit
9. If you want to have multiple vendors bid on your contract, what is the best way to ensure that all vendors have the same information before bidding?

Explanation

B - A bidder's conference is a good way to ensure all bidders have the same information at the same time and to ensure fairness and equity within the bidding process.

Submit
10. Which of the following is an Output of Develop Project Management Plan?

Explanation

The output of the Develop Project Management Plan process is the Project Management Plan. This plan is a comprehensive document that outlines the approach and strategies for managing the project. It includes information on project scope, schedule, budget, communication, risk management, and other important aspects. The Project Management Plan serves as a guide for the project team and stakeholders throughout the project's lifecycle, ensuring that everyone is aligned and working towards the same goals.

Submit
11. Ongoing operations and a project both have Initiating Processes, but only a project has __________.

Explanation

B - A project is a finite effort; the Initiating Process Group starts the cycle, and the closing Process Group ends the cycle.

Submit
12. Why is it important to have a staff release plan for people within the project team?

Explanation

D - A staff release plan provides a clean break point for an individual and saves the project money in the process.

Submit
13. Which of the following BEST describes the main purpose of the project charter?

Explanation

A- The project charter does several important things: it lays out the project requirements, describes
an initial summary milestone schedule, documents the business case, and identifies initial risks, assumptions, and constraints. But the most important thing that a project charter does is that it identifies the project manager, and assigns him or her the authority necessary to get the job done.

Submit
14. A company is about to begin work on a large construction project to build four new buildings for a bank that wants to open new branches. The sponsor is writing a project charter. She recalls that a previous project the company performed for another bank ran over budget because the team had underestimated the effort required to install the reinforced walls in the vault. The previous project manager had documented the details of the lessons learned from this project. Where should the sponsor look for these lessons learned?

Explanation

B- Lessons learned from past projects are always part of a company’s organizational process.

Submit
15. Project risks should include impacts to project:

Explanation

D - Schedule, cost, quality and performance are often the key factors that risks can impact for a project.

Submit
16. While creating a project charter, you discover a new project management software tool has come onto the market. You spend the weekend taking an online tutorial to learn about it. This is an example of:

Explanation

D- The PMP Code of Professional Conduct tells us that an important part of any project manager’s career is enhancing personal professional competence. This means increasing your knowledge and applying it so that you can improve your ability to manage projects.

Submit
17. Which of the following is NOT found in a project charter?

Explanation

C- The procedure for managing changes to a contract is found in the Contract Management Plan.
The other three answers are all things you typically find in a project charter.

Submit
18. Mary is a project manager at a consulting company. The company regularly builds teams to create products for clients. When the product is delivered, the team is dissolved and assigned to other projects. What kind of organization is she working for?

Explanation

B- Mary is working for a projectized organization. In those companies, the project manager has authority over the team as well as the project.

Submit
19. Project scope, time, and cost are often referred to as the:

Explanation

B - Project quality is affected by balancing project scope, time, and cost. High quality projects deliver the required product, service, or result within scope, on time, and within budget.

Submit
20. A hierarchical structure of resources organized by resource type category and resource type used in resource leveling schedules is known as:

Explanation

D - The Resource Breakdown Structure is a hierarchical structure of resources by resource category and resource type used in resource leveling schedules and to develop resource-limited schedules. This may also be used to identify and analyze project human resource assignments.

Submit
21. Which of the following is an Input to Close Project or Phase?

Explanation

Accepted deliverables are the outputs of the project that have been reviewed and approved by the project stakeholders. They are the tangible or intangible products, services, or results that have met the specified requirements and are ready to be handed over to the customer or end user. These accepted deliverables serve as an input to the Close Project or Phase process, as they indicate that the project or project phase has been successfully completed and can be formally closed.

Submit
22. Which of these is NOT a risk diagramming technique?

Explanation

C - Risk diagramming techniques can include: cause and effect diagrams (also known as fishbone diagrams), flowcharts, and influence diagrams.

Submit
23. As a PMP, one of your responsibilities is to ensure integrity on the project. When your personal interests are put above the interests of the project or when you use your influence to cause others to make decisions in your favor without regard for the project outcome, this is considered:

Explanation

When a PMP prioritizes their personal interests over the interests of the project or manipulates others to make decisions in their favor without considering the project's outcome, it is known as a conflict of interest. This means that the individual is not acting in the best interest of the project and is compromising its integrity. It is important for project managers to remain impartial and make decisions that benefit the project as a whole.

Submit
24. Which of the following shows roles and responsibilities on your project?

Explanation

The RACI matrix shows roles and responsibilities on your project. RACI stands for Responsible, Accountable, Consulted, Informed.

Submit
25. You are a project manager for the information technology division of a local satellite TV broadcasting company. This spring, the chief information officer for your company gave you the project to convert and upgrade all the PCs in the department to the latest release of a specific desktop application. Prior to this conversion, all manner of desktop software existed on machines throughout the company and had caused increasing problems with sharing files and information across the company. A lot of unproductive hours were spent typing information into several formats. This project came about as a result of which of the following?  

Explanation

The project to convert and upgrade all the PCs in the department to the latest release of a specific desktop application came about as a result of a business need. The increasing problems with sharing files and information across the company, as well as the unproductive hours spent typing information into several formats, indicated a need for a standardized desktop software. By converting and upgrading all the PCs, the company aims to address this business need and improve productivity and efficiency within the department.

Submit
26. Which of the following statements is true regarding Close Project?

Explanation

The correct answer is that Close Project occurs at the end of a project phase and at the end of the project. This means that Close Project is performed both when a specific phase of the project is completed and when the entire project is finished. It is important to close a project phase to ensure that all deliverables are completed and approved before moving on to the next phase. Similarly, closing the entire project ensures that all project objectives have been met and all project documentation is finalized.

Submit
27. During a presentation to management, you want to display the project schedule with only the key deliverables displayed. What is the correct tool for this purpose?

Explanation

C - A milestone chart displays only the key deliverables and is simple and easy to understand.

Submit
28. You are developing the project charter for a new project. Which of the following is NOT part of the enterprise environmental factors?

Explanation

A- Lessons learned are part of the organizational process assets, not enterprise environmental factors. Your company’s enterprise environmental factors tell you about how your company typically does business—like how your company’s departments are structured, and the
regulatory and industry environment your company operates in.

Submit
29. Dave is the project manager for a construction project that is building a gazebo. When the project first started, he met with the stakeholders to define the scope. The sponsors mentioned that the gazebo is a really important part of their daughter's wedding ceremony that was planned for seven months from then. In fact, they said that if the gazebo couldn't be completed in seven months, it wouldn't be worth it for them to even start the project. Dave wrote down the seven-month deadline to put in his Project Scope Statement. In which section of the document did the deadline appear?

Explanation

C- Since the project absolutely must be completed in seven months for it to be worth doing, the deadline is a constraint.

Submit
30. During lunch with a project manager from another department, you are given to understand that it is sufficient to adhere to the applicable Standards for the project. Regulations are not necessarily applicable to projects since they are guidelines and you as PM have the option to decide whether they are applicable or not. Your understanding is that :

Explanation

A - Standards are seen more as guidelines, developed by a recognized body, established by consensus. In contrast, regulations are government imposed requirements. Ex: Building codes are an example of regulation

Submit
31. What is the advantage of preparing an estimate of costs by an outside professional estimator?

Explanation

D - An estimate of costs will serve as a benchmark on proposed responses. Any significant differences in cost estimates can be an indication that the procurement statement of work was deficient, ambiguous or the prospective sellers failed to understand the work.

Submit
32. All of the following are inputs into the Directing and Managing Project Execution EXCEPT?

Explanation

The Risk Register is not an input into the Directing and Managing Project Execution process. The Risk Register is a tool used in the Identify Risks process, which is part of the Project Risk Management knowledge area. The Directing and Managing Project Execution process focuses on executing the project plan and managing the project team, and does not directly involve the Risk Register. The other options listed - Organisational Process Assets, Enterprise Environmental Factors, and Project Management Plan - are all inputs into the Directing and Managing Project Execution process.

Submit
33. A company that designs and manufactures a series of new bicycles each year may manage the effort more efficiently how?

Explanation

A - A program is a group of related projects managed in a coordinated way to obtain benefits and control not available from managing them individually.

Submit
34. Estimating the type and quantities of material, people, equipment or supplies required to perform each activity is:

Explanation

D - Estimate Activity Resources is the process of estimating the type and quantities of material, people, equipment or supplies required to perform each activity.

Submit
35. You're managing an industrial design project. Your project is currently in the Initiating phase. The project charter has been created, and you are working on identifying the stakeholders. Which of the following is NOT something that you should do?

Explanation

D- You don’t create the change control system in the Initiating phase—that’s something that you do as part of your project planning activities.

Submit
36. Which of the following statements is correct?

Explanation

A - A portfolio refers to a collection of projects of programs that are grouped together to facilitate their effective management. The projects or programs need not be directly related or interdependent.

Submit
37. Deliverables can be described as?

Explanation

Deliverables can be described as the verifiable results of products or services that must be produced to consider the project complete. This means that deliverables are the tangible or intangible outputs that are expected to be produced as a result of the project. They are the measurable outcomes that demonstrate the successful completion of the project and can be used to evaluate its success.

Submit
38. On obtaining the project charter, the project manager of a project immediately put together the project team to execute the project. Is this correct?

Explanation

D - No, the project team is not acquired immediately after signing of the project charter. Acquisition of a project team starts with HR planning in the Planning process group, followed by the Acquisition of the team in the Execution phase. The other answers are wrong because the Acquisition of the project team is mentioned in the wrong phase. It is also not the responsibility of the Project Sponsor to provide the team for execution.

Submit
39. You are initiating project that has a virtual team. Half of your team members will be located in another country, where they are working for a subcontractor. The subcontractor's team members speak a different dialect of English than your team does. After a conference call to review the project charter, two of your team members make jokes about the way your subcontractor's team members speak. What is the BEST way to handle this situation?

Explanation



This option addresses the issue by acknowledging the cultural differences between team members and promotes understanding and inclusivity within the project. It is important to recognize and respect cultural diversity when working with virtual teams from different countries and backgrounds. Discriminatory remarks should not be tolerated, and setting expectations for teams to understand and respect cultural differences is a constructive approach to managing such situations.
Submit
40. The Project Management Knowledge Areas _______________

Explanation

The correct answer states that the Project Management Knowledge Areas consist of nine areas that bring together processes that have things in common. This means that the knowledge areas in project management are organized based on the similarities and commonalities of the processes within each area. This approach allows for a systematic and cohesive understanding of project management, as it groups together related processes and ensures that they are addressed in a comprehensive manner.

Submit
41. The primary function of the Closing processes is to perform which of the following?

Explanation

The primary function of the Closing processes is to formalize project completion and disseminate this information to project participants. This includes activities such as obtaining formal acceptance of the deliverables, documenting lessons learned, conducting post-implementation audits, and ensuring that all project documentation is complete and archived. The purpose is to bring the project to a controlled and orderly conclusion, ensuring that all project objectives have been met and that the project is formally closed.

Submit
42. Which of the following statements is not true about a subproject?

Explanation

B - A subproject is not necessarily the smallest unit. On very large projects, the subproject can further consist of a series of even smaller projects.

Submit
43. All of the following statements are true of the project Closing processes except for which one?

Explanation

The project closing processes involve finalizing all project activities and formally closing the project. During this phase, the probability for success is high because the project is nearing completion and all deliverables are being finalized. The project manager's influence is also significant during the closing processes as they oversee the completion of all project tasks and ensure that all project objectives are met. Additionally, stakeholders' influence may be minimal during this phase as their involvement may decrease as the project nears its end. However, the statement "Risk is greatest in the project Closing processes" is incorrect. The closing processes are focused on wrapping up the project and mitigating any remaining risks, so the level of risk is typically lower during this phase compared to earlier stages of the project.

Submit
44. All of the following processes form part of the Executing process group except?

Explanation

The Executing process group involves performing activities in accordance with the project management plan, completing the work in accordance with the defined quality framework and specification, and coordinating people and resources. Managing changes to the deliverables, on the other hand, falls under the Monitoring and Controlling process group, where changes to the project are identified, evaluated, and implemented. Therefore, managing changes to the deliverables is not part of the Executing process group.

Submit
45. A project manager's primary professional responsibility is towards:

Explanation

C - The project management team's professional responsibilities are not limited to any one of the stakeholders. The other choices are correct but not complete by themselves.

Submit
46. You are developing the project scope statement for a new project. Which of the following is NOT part of creating a project scope statement?

Explanation

A- Verify Scope is the Monitoring & Controlling process for the Scope Management knowledge area. It doesn’t have anything to do with planning out the scope of the project—you do it as you complete
each project phase to make sure that your team has completed all of the project work.

Submit
47. Organizations can be categorized according to their operations style. Which two types of organizational systems are recognized by the PMBOK?

Explanation

A - Project-based organizations are those whose operations consist primarily of projects. Non-project based organizations often may lack management systems designed to support project needs efficiently and effectively.

Submit
48. Fill in the blank: _______________ means developing in steps and continuing by increments.

Explanation

D - Progressive elaboration is a characteristic of projects that allows a project management team to manage it to a greater level as the project evolves.

Submit
49. When is the BEST time to have project kickoff meetings?

Explanation

C- If your project is broken up into phases, you should have a kickoff meeting at the start of each phase.

Submit
50. You are managing a construction project that is currently being initiated. You met with the sponsors, and have started to work on identifying stakeholders. You've documented several key stakeholders and identified their needs. Before you can finish initiating the project, your company guidelines require that you make a rough order of magnitude estimate of both time and cost, so that the sponsor can allocate the final budget.   What's the range of a rough order of magnitude (ROM) estimate?

Explanation

B- A rough order of magnitude (ROM) estimate is an estimate that is very rough. According to the PMBOK® Guide, you should expect a ROM estimate to be anywhere from half (-50%) to one and a half times (+50%) the actual result. That means that if your ROM estimate for a project is six months, then you should expect the actual project to be anywhere from three months to nine months.

Submit
51. Where would you find a detailed list and description of specific project assumptions associated with the project?

Explanation

B - The Project scope statement lists and describes the specific project assumptions associated with project scope and the potential impact of those assumptions if they prove to be false. The assumptions listed in the detailed project scope statement are typically more numerous and detailed than the project assumptions listed in the project charter.

Submit
52. Your company is going to introduce a new service called Phone Home. This service will allow you to speak the name of the person you want to call into your cellular phone. To call home, you would simply speak the word home into the phone, and it will dial that number for you. Your company is taking advantage of the progress that has been made recently with voice recognition software. Initial projections show that market demand is very high for this product. This project came about as a result of which of the following?  

Explanation

This project came about as a result of a technological advance in voice recognition software. The company is introducing a new service called Phone Home that utilizes this technology. The service allows users to speak the name of the person they want to call into their cellular phone, making it convenient and easy to dial numbers. The initial projections also indicate a high market demand for this product, further emphasizing the significance of the technological advance in driving the development of this project.

Submit
53. When are the most expensive defects most likely to be introduced into a product?

Explanation

B- The most expensive defects are the ones introduced when the product is being designed.

Submit
54. Fill in the blank: A _______ is a document established by consensus and approved by a recognized body that provides, for common and repeated use, rules, guidelines or characteristics for activities or their results, aimed at the achievement of the optimum degree of order in a given context.

Explanation

B- Standards ensure reproducible results or products, within a specific set of parameters. Examples of standards are USB 2.0 and the octane rating of gasoline.

Submit
55. Which document describes the project's deliverables and the work required to create those deliverables?

Explanation

B - The project scope statement is the correct response. This document describes the project's deliverables in details and the work that is required to create those deliverables. It also forms the baseline for evaluating whether requests for changes are within or outside the project's boundaries.

Submit
56. You are a project manager working on a new software product. Your company plans for market businesses. The project sponsor told you that the project must be completed by September 1. The company plans to demo the new software product at a trade show in late September and therefore needs the project completed in time for the trade show. However, the sponsor has also told you that the budget is fixed at $85,000 and cannot be increased by even $10 due to overall budget cuts this year. You must complete the project within the given time frame and budget. Which of the following is the primary constraint? for this project?  

Explanation

The primary constraint for this project is the budget. The project manager has been informed that the budget is fixed at $85,000 and cannot be increased. This means that the project must be completed within this budget constraint, without any additional funds. The time frame and schedule are important factors, but the primary constraint in this case is the budget.

Submit
57. You are the project manger for Xylophone Phonics. This company produces children's software programs that teach basic reading and math skills. You are ready to assign project roles, responsibilities, and reporting relationships. Which project Planning process are you working on?

Explanation

The correct answer is Human Resource Planning. In this question, the project manager is ready to assign project roles, responsibilities, and reporting relationships. This is a key aspect of Human Resource Planning, which involves identifying and documenting project roles, responsibilities, and reporting relationships, as well as determining the staffing needs for the project. Resource Planning, Acquire Staff, and Human Resource Acquisition are not the correct answers because they do not specifically address the process of assigning project roles and responsibilities.

Submit
58. All the following are Inputs to Close Project or Phase EXCEPT

Explanation

Enterprise Environment Factors are not inputs to the Close Project or Phase process. The Close Project or Phase process is focused on finalizing all activities and completing the project or phase. The inputs to this process typically include the Project Management Plan, Accepted Deliverables, and Organizational Process Assets. Enterprise Environment Factors, on the other hand, are external factors that can influence the project but are not directly used as inputs for closing the project or phase.

Submit
59. Which of the following is an Input to Monitor and Control Project Work?

Explanation

Organizational Process Assets are the inputs to Monitor and Control Project Work. These assets include the documented procedures, guidelines, and historical information that are used to manage projects within an organization. They provide a framework for project management and help in making informed decisions during project execution. By using these assets, project managers can monitor and control the progress of the project, assess performance, and make necessary adjustments to ensure project success. Teaming agreements, work performance information, and procurement contract award are not specifically mentioned as inputs for monitoring and controlling project work.

Submit
60. Which of the following is a "hygiene factor" under Herzberg's Motivation-Hygiene Theory?

Explanation

C- Herzberg’s Motivation-Hygiene Theory states that people need things like good working conditions, a satisfying personal life, and good relations with the boss and coworkers—these are called “hygiene factors.”

Submit
61. What does a Cost Performance Index (CPI) of more than 1.0 indicate?

Explanation

C - The CPI is calculated as the earned value divided by the actual cost. An index of greater than one indicates that you have spent less than you forecasted to this point.

Submit
62. Which is the BEST description of project scope?

Explanation

D- Product scope means the features and functions of the product or service being built.

Submit
63. Which conflict resolution technique is most effective?

Explanation

D- Confronting means figuring out the cause of the problem and fixing it. That’s the best way to be
sure that the right decision is made.

Submit
64. You have just been authorized to manage a new project for your company. Which of the following BEST describes your first action?

Explanation

D- Since the project charter is what authorizes a project manager to work on a project, it means that the Develop Project Charter process has just been performed. So which of the processes in the list comes next? The other Initiating process: Identify Stakeholders.

Submit
65. You are refining the product description for your company's new line of ski boots. Which of the following statements is true?

Explanation

The correct answer is that you are in the Initiating process of your project and know that the product description will contain less detail in this stage and greater detail as the project progresses. This is because during the Initiating process, the project is just starting and the details of the product are not fully defined. As the project progresses and more information becomes available, the product description will be refined and more detail will be added.

Submit
66. All of the following are Inputs to Direct and Manage Project Execution EXCEPT?

Explanation

Direct and Manage Project Execution is a process in project management that involves carrying out the project activities as planned and controlling the project work. Inputs to this process typically include project management plans, organisational process assets, and approved change requests. Risk management plans, on the other hand, are not direct inputs to this process. Risk management plans are used in the Identify Risks and Plan Risk Responses processes, which are part of the project risk management knowledge area. Therefore, the correct answer is Risk Management Plans.

Submit
67. Name the ethical code you'll be required to adhere to as a PMP.

Explanation

The correct answer is "Project Management Professional Code of Professional Conduct." As a PMP, you are expected to follow a specific code of ethics that outlines the professional conduct expected from project managers. This code ensures that project managers act with integrity, honesty, and fairness in their interactions with stakeholders and the project team. It also emphasizes the importance of maintaining confidentiality, avoiding conflicts of interest, and promoting the overall well-being of the project and its stakeholders.

Submit
68. Which of the following is an Input to Monitor and Control Project Work?

Explanation

Organisational Process Assets are an input to Monitor and Control Project Work. These assets include the policies, procedures, and knowledge base of an organization that can be used to guide and control project execution. They provide the necessary guidelines and frameworks for monitoring and controlling project work, ensuring that it is aligned with the organization's standards and best practices. By utilizing these assets, project managers can effectively monitor and control the progress, performance, and outcomes of their projects.

Submit
69. Which of the following is NOT one of the most common sources of project conflict?

Explanation

D- It’s important to know that resources, schedules, and priorities cause 50% of project problems
and conflicts.

Submit
70. Which of these is an input to the Collect Requirements process?

Explanation

D - The project charter is an input to the Collect Requirements process. The other choices are not valid. Requirement management plan is an output of the Collect Requirements process. [Project Integration

Submit
71. When do you perform stakeholder analysis?

Explanation

Stakeholder analysis is typically performed during the initial stages of a project, particularly when managing communications. This analysis helps identify all stakeholders, understand their interests, influence, and expectations, and plan how to effectively communicate with them throughout the project. It can also inform the development of the project charter and the project management plan, but it is crucial in establishing the foundation for project communications.

Submit
72. Defining the requirements for a new product is what type of activity?

Explanation

A - The Initiating process group consists of the processes performed to define a new project or a new phase of an existing project by obtaining authorization to start the project of phase.

Submit
73. When a project is being performed under contract, the product description is provided by which of the following?  

Explanation

The project sponsor is responsible for providing the product description when a project is being performed under contract. The project sponsor plays a crucial role in defining the scope and objectives of the project, including the specific requirements and characteristics of the product that is being developed or delivered. They have the overall responsibility for the success of the project and are typically the ones who initiate and fund the project. Therefore, it is their responsibility to provide the product description to ensure that the project meets their expectations and requirements.

Submit
74. What are the inputs to the Initiation process?

Explanation

The inputs to the Initiation process include the strategic plan, project overview document, feasibility study, and historical information. These inputs are essential in determining the feasibility and viability of the project. The strategic plan provides the overall direction and objectives of the project, while the project overview document outlines the scope, objectives, and deliverables. The feasibility study assesses the project's technical, economic, and organizational viability. Historical information helps in understanding past project experiences and lessons learned, which can be valuable in planning and decision-making.

Submit
75. Which of the following is inaccurately represented by the term Progressive elaboration?

Explanation

A - The distinction between Progressive elaboration and Scope Creep needs to be understood since the two terms are different. The changes to scope (especially in an uncontrolled manner) are called scope creep. In contrast, Progressive elaboration involves building on, or elaborating the output of a previous phase.

Submit
76. According to the PMBOK Guide, the project manager is identified and assigned during which process?

Explanation

While the PMBOK Guide does not explicitly mandate a specific time for assigning a project manager, it emphasizes the importance of having a project manager in place early in the project lifecycle. Ideally, the project manager should be assigned before the Develop Project Charter process begins. This allows the project manager to contribute to the project charter's development, ensuring alignment with organizational objectives and stakeholder expectations. Assigning the project manager early also enables them to lead the planning processes and guide the project effectively from initiation to closure.

Submit
77. The date through which the project has provided actual status and accomplishments is called:

Explanation

A - The date through which the project has provided actual status and accomplishments is called as Data Date. It is also known as as-of Date or status Date

Submit
78. Each of the following statements describes an element of the Develop Project Management Plan process except for which one?

Explanation

The Develop Project Management Plan process involves various elements that help in creating a comprehensive plan for project management. These elements include project management methodology, configuration management system, and expert judgment. However, project specifications are not specifically mentioned as an element of this process. Project specifications typically refer to the detailed requirements and characteristics of the project deliverables, and while they are important for project planning, they are not explicitly mentioned as an element of the Develop Project Management Plan process.

Submit
79. The transition from one phase to another within a project's life cycle (e.g. design to manufacturing) is typically marked by:

Explanation

A - The transition from one phase to another within a project's lifecycle generally involves, and is usually defined by, some form of technical transfer or handoff.

Submit
80. An important part of performing stakeholder analysis is documenting quantifiable expectations. Which of the following expectations is quantifiable?

Explanation



Quantifiable expectations are those that can be measured and expressed numerically. A 15% reduction in part cost is a specific, measurable objective that can be quantified, hence it meets the criteria of a quantifiable expectation. The other options are qualitative and lack specific metrics for measurement.
Submit
View My Results

Quiz Review Timeline (Updated): Oct 15, 2024 +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Oct 15, 2024
    Quiz Edited by
    ProProfs Editorial Team
  • Feb 25, 2013
    Quiz Created by
    Agilep3
Cancel
  • All
    All (80)
  • Unanswered
    Unanswered ()
  • Answered
    Answered ()
Which of the following is an Output of  Develop Project Charter?
A notice sent to a subcontractor about the contract is an example of...
Which of the following are enterprise environmental factors...
You have recently been assigned to be the project manager for a...
Which of the following describes the Executing process group?
Which of the following is NOT a type of communication ?
Which of the following is NOT a stakeholder?
You have been asked to establish a project charter for your new...
If you want to have multiple vendors bid on your contract, what is the...
Which of the following is an Output of Develop Project Management...
Ongoing operations and a project both have Initiating Processes, but...
Why is it important to have a staff release plan for people within the...
Which of the following BEST describes the main purpose of the project...
A company is about to begin work on a large construction project to...
Project risks should include impacts to project:
While creating a project charter, you discover a new project...
Which of the following is NOT found in a project charter?
Mary is a project manager at a consulting company. The company...
Project scope, time, and cost are often referred to as the:
A hierarchical structure of resources organized by resource type...
Which of the following is an Input to Close Project or Phase?
Which of these is NOT a risk diagramming technique?
As a PMP, one of your responsibilities is to ensure integrity on the...
Which of the following shows roles and responsibilities on your...
You are a project manager for the information technology division of a...
Which of the following statements is true regarding Close Project?
During a presentation to management, you want to display the project...
You are developing the project charter for a new project. Which of the...
Dave is the project manager for a construction project that is...
During lunch with a project manager from another department, you are...
What is the advantage of preparing an estimate of costs by an outside...
All of the following are inputs into the Directing and Managing...
A company that designs and manufactures a series of new bicycles each...
Estimating the type and quantities of material, people, equipment or...
You're managing an industrial design project. Your project is...
Which of the following statements is correct?
Deliverables can be described as?
On obtaining the project charter, the project manager of a project...
You are initiating project that has a virtual team. Half of your team...
The Project Management Knowledge Areas _______________
The primary function of the Closing processes is to perform which of...
Which of the following statements is not true about a subproject?
All of the following statements are true of the project Closing...
All of the following processes form part of the Executing process...
A project manager's primary professional responsibility is...
You are developing the project scope statement for a new project....
Organizations can be categorized according to their operations style....
Fill in the blank: _______________ means developing in steps and...
When is the BEST time to have project kickoff meetings?
You are managing a construction project that is currently being...
Where would you find a detailed list and description of specific...
Your company is going to introduce a new service called Phone Home....
When are the most expensive defects most likely to be introduced into...
Fill in the blank: A _______ is a document established by consensus...
Which document describes the project's deliverables and the work...
You are a project manager working on a new software product. Your...
You are the project manger for Xylophone Phonics. This company...
All the following are Inputs to Close Project or Phase EXCEPT
Which of the following is an Input to Monitor and Control Project...
Which of the following is a "hygiene factor" under Herzberg's...
What does a Cost Performance Index (CPI) of more than 1.0 indicate?
Which is the BEST description of project scope?
Which conflict resolution technique is most effective?
You have just been authorized to manage a new project for your...
You are refining the product description for your company's new line...
All of the following are Inputs to Direct and Manage Project Execution...
Name the ethical code you'll be required to adhere to as a PMP.
Which of the following is an Input to Monitor and Control Project...
Which of the following is NOT one of the most common sources of...
Which of these is an input to the Collect Requirements process?
When do you perform stakeholder analysis?
Defining the requirements for a new product is what type of activity?
When a project is being performed under contract, the product...
What are the inputs to the Initiation process?
Which of the following is inaccurately represented by the term...
According to the PMBOK Guide, the project manager is identified and...
The date through which the project has provided actual status and...
Each of the following statements describes an element of the Develop...
The transition from one phase to another within a project's life...
An important part of performing stakeholder analysis is documenting...
Alert!

Advertisement