PMP Exam Prep- Set-1

1 Question

Settings
PMP Quizzes & Trivia

This is PMP Exam Prep Set is related to depth of your understanding in PMBoK Knowledge Areas


Questions and Answers
  • 1. 
    PMBok is
  • 2. 
    What are the areas of PMI involved in?
  • 3. 
    Which knowledge area has process in all process groups
    • A. 

      Project Procurement Management

    • B. 

      Project Communication Management

    • C. 

      Project Integration Management

    • D. 

      Project Time Management

  • 4. 
    How many process in planning process group
    • A. 

      19

    • B. 

      20

    • C. 

      21

    • D. 

      22

  • 5. 
    Which of the knowledge areas does not have any planning process
    • A. 

      Project Quality Management

    • B. 

      Project Risk Management

    • C. 

      Project Time Management

    • D. 

      None of the above

    • E. 

      All of A, B, C

  • 6. 
    Which of the knowledge area does not have process in Executing Process Group?
    • A. 

      Project Integration Management

    • B. 

      Project Procurement Management

    • C. 

      Project Human Resource Management

    • D. 

      Project Risk Management

  • 7. 
    Which of the knowledge areas does not have process in monitoring and controlling process group
    • A. 

      Project Risk Management

    • B. 

      Project Human Resource Management

    • C. 

      Project Quality Management

    • D. 

      Project Procurement Management

  • 8. 
    Which knowledge area has maximum number of processs in planning process group?
    • A. 

      Project Scope Management

    • B. 

      Project Risk Managment

    • C. 

      Project Cost Management

    • D. 

      Project Human Resource Management

  • 9. 
    In the following network logic diagram start dates are defined as early morning, finish dates are evening. If tasks are scheduled to begin at early start date, what is true?
    • A. 

      Activity B has a free float of 10 d.

    • B. 

      Activity B has a total float of 10 d.

    • C. 

      Activity A has a free float of 10 d.

    • D. 

      Activity A has a total float of 10 d.

  • 10. 
    A Project Manager is using AOA to perform critical path analysis. The network diagram is represented as shown using below. Which of the following represents the path Activity Duration Dependent on A 3 none C 3 none B 2 A D 5 C E 2 none F 4 E G 3 D,F H 1 D,F I 2 B,G R 0 H,I
    • A. 

      ABIR

    • B. 

      CDHR

    • C. 

      CDGIR

    • D. 

      EFGIR