The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Hari_Thapliyal
H
Hari_Thapliyal
Community Contributor
Quizzes Created: 1 | Total Attempts: 396
| Attempts: 396 | Questions: 9
Please wait...
Question 1 / 9
0 %
0/100
Score 0/100
1. Which knowledge area has process in all process groups

Explanation

Being responsible for integration of all the process of remaining knowledge area only Project Integration Management knowledge area has process is all the process groups.

Submit
Please wait...
About This Quiz
PMP Exam Prep- Set-1 - Quiz

This is PMP Exam Prep Set is related to depth of your understanding in PMBoK Knowledge Areas

2. Which of the knowledge areas does not have any planning process

Explanation

All nine knowledge areas has planning processes

Submit
3. Which of the knowledge area does not have process in Executing Process Group?

Explanation

Risk should not executed in project, if they come they should be managed through contingency plan. In order to avoid those Project Manager should have contingency plan in place. Risk should be monitored throughout project life cycle.

Submit
4. Which knowledge area has maximum number of processs in planning process group?

Explanation

Project Scope Managment has 3 processes:
Collect Requirements, Define scope, Create WBS
Project Risk Management has 5 processes:
Plan Risk Management, Identify Risk, Perform Qualitative Risk Management, Perform Quantitative Risk Management,
Plan Risk Risponse
Project Cost Managment has 2 processes:
Estimate Cost, Determine Budget
Project Human Resource Managment has 3 processes:
Plan Human Resource Management, acquire project team, develop project team

Submit
5. Which of the knowledge areas does not have process in monitoring and controlling process group

Explanation

PMI believes that Human Resources should not be monitored and controlled, rather processes should be monitored and controlled. Human resource should be managed through the processes not monitored and controlled.

Submit
6. In the following network logic diagram start dates are defined as early morning, finish dates are evening.
If tasks are scheduled to begin at early start date, what is true?

Explanation

not-available-via-ai

Submit
7. A Project Manager is using AOA to perform critical path analysis. The network diagram is represented as shown using below. Which of the following represents the path
Activity Duration Dependent on
A 3 none
C 3 none
B 2 A
D 5 C
E 2 none
F 4 E
G 3 D,F
H 1 D,F
I 2 B,G
R 0 H,I

Explanation

The path represented by EFGIR is the critical path because it has the longest duration of 15 units. The critical path is the sequence of activities that determines the total duration of the project. Any delay in the activities on the critical path will directly impact the project's overall duration. Therefore, the project manager needs to closely monitor and manage the activities on the EFGIR path to ensure that the project is completed on time.

Submit
8.
How many process in planning process group

Explanation

The planning process group consists of various processes that are involved in defining project objectives, scope, and strategies to achieve them. These processes include developing a project management plan, creating a work breakdown structure, identifying project risks, and defining project activities. The correct answer, 20, indicates that there are a total of 20 processes in the planning process group.

Submit
9. PMBok is

Explanation

PMBoK is Body of Project Management Knowledge Area. It is a standard and not specific to any industry.

Submit
View My Results

Quiz Review Timeline (Updated): Mar 19, 2023 +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 19, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Mar 16, 2011
    Quiz Created by
    Hari_Thapliyal
Cancel
  • All
    All (9)
  • Unanswered
    Unanswered ()
  • Answered
    Answered ()
Which knowledge area has process in all process groups
Which of the knowledge areas does not have any planning process
Which of the knowledge area does not have process in Executing Process...
Which knowledge area has maximum number of processs in planning...
Which of the knowledge areas does not have process in monitoring and...
In the following network logic diagram start dates are defined as...
A Project Manager is using AOA to perform critical path analysis. The...
How many process in planning process group
PMBok is
Alert!

Advertisement