PM In Practice : Risk Week 4

Reviewed by Editorial Team
The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Babjam
B
Babjam
Community Contributor
Quizzes Created: 14 | Total Attempts: 31,929
| Attempts: 169 | Questions: 25
Please wait...
Question 1 / 25
0 %
0/100
Score 0/100
1. Insufficient upfront planning is the major contributor  to a project going over budget or late in delivery.

Explanation

Insufficient upfront planning can lead to a project going over budget or being delayed. Without proper planning, there may be a lack of clarity on project requirements, timelines, and resource allocation. This can result in unexpected costs, scope creep, and inefficient use of resources. Adequate upfront planning helps identify potential risks and allows for better estimation and allocation of resources, reducing the chances of budget overruns or delays in project delivery.

Submit
Please wait...
About This Quiz
Risk Management Quizzes & Trivia

This quiz titled 'PM in Practice: Risk Week 4' assesses understanding of project management, focusing on project plans and manager responsibilities. It evaluates knowledge on the structure of project plans and the role of a project manager in task delegation and progress reporting.

Personalize your quiz and earn a certificate with your name on it!
2. At anytime during the project the project manager should be able to give the sponsors:

Explanation

The project manager should be able to provide the sponsors with an accurate assessment of what has been accomplished and what is yet to be accomplished. This is important for the sponsors to have a clear understanding of the progress of the project and to make informed decisions regarding its future. The other options mentioned in the question, such as an end state project schedule, a complete list of risks, and a resource histogram, are also important aspects of project management but may not necessarily be required to be provided to the sponsors at any given time during the project.

Submit
3.
The Project Manager is responsible to create a list of major activities that are required to meet the project objectives.

Explanation

The project manager plays a crucial role in planning and organizing the project activities. One of their responsibilities is to create a list of major activities that are necessary to achieve the project objectives. This list helps in identifying the tasks that need to be completed and ensures that all the necessary activities are included in the project plan. By creating this list, the project manager can effectively allocate resources, set priorities, and monitor the progress of the project. Therefore, the statement is true.

Submit
4. Which of the following is an example of an extenal risk?

Explanation

Inflation is an example of an external risk because it is a factor that is beyond the control of the organization. It refers to the general increase in prices of goods and services over time, which can negatively impact the financial stability of a business. Inflation can lead to higher costs of production, reduced purchasing power, and increased prices for raw materials or resources, ultimately affecting the profitability and competitiveness of a company. Therefore, it is considered an external risk as it is influenced by external economic factors rather than internal decisions or actions of the organization.

Submit
5. A project plan document is shown as a "Microsoft Project" document.

Explanation

The statement is false because a project plan document is not shown as a "Microsoft Project" document. A project plan document is typically created using project management software like Microsoft Project, but it is usually saved in a different file format such as .docx or .pdf. The "Microsoft Project" document format is specific to the software itself and is used to create and manage project schedules and tasks.

Submit
6. Project forms, charts and tables are created and altered for each project by the project manager.

Explanation

The statement is true because project forms, charts, and tables are essential tools for project management. These documents are used to track project progress, allocate resources, and communicate information to stakeholders. The project manager is responsible for creating and altering these documents as needed to ensure that the project is on track and all necessary information is captured.

Submit
7. To be effective, the risk management process should:

Explanation

The correct answer is "be applied throughout the project and at all levels of system decomposition and project organization". This means that risk management should be implemented from the beginning of the project until its completion, and it should be integrated into all aspects of the project, including system decomposition and project organization. This approach ensures that risks are identified and managed at every stage of the project, minimizing the potential impact on the project's success.

Submit
8. There are ten major sections to a project plan.

Explanation

The statement is false because there are typically five major sections to a project plan, which include the introduction, project goals and objectives, project scope, project timeline and milestones, and project budget. While there may be variations in the structure and content of project plans, it is generally agreed that there are five essential sections.

Submit
9. The LRC is a document managed by the project manager that depicts the project tasks listed in rows and includes the department that is responsible to complete the tasks.

Explanation

The LRC, or the Labor Resource Chart, is indeed a document managed by the project manager. It lists the project tasks in rows and specifies the department responsible for completing each task. This document helps in organizing and assigning tasks efficiently, ensuring that each department knows their responsibilities and can complete their assigned tasks effectively.

Submit
10. Risk mitigation involves:

Explanation

Risk mitigation is the process of minimizing or eliminating potential risks that could negatively impact a project. One way to achieve this is by reducing the expected monetary value of a risk event. This involves identifying and assessing the probability of a risk occurring and then implementing measures to decrease the likelihood of it happening. By reducing the probability of a risk event, the potential financial impact is also reduced, thus mitigating the overall risk to the project.

Submit
11. The term risk portfolio refers to:

Explanation

The term risk portfolio refers to the collection and organization of risk data that is gathered and used for the purpose of managing a project. This includes identifying and assessing potential risks, analyzing their potential impact, and developing strategies to mitigate or respond to them. The risk portfolio provides a comprehensive view of all the risks associated with the project, allowing the project management team to make informed decisions and take appropriate actions to minimize the negative impacts of these risks.

Submit
12. Categories of risk response are:

Explanation

The categories of risk response are avoidance, mitigation, and acceptance. Avoidance involves eliminating the risk by avoiding the activity that could lead to it. Mitigation involves reducing the impact or likelihood of the risk through proactive measures. Acceptance involves acknowledging the risk and its potential consequences without taking any specific action to address it. These categories provide a framework for organizations to assess and address risks in their operations and decision-making processes.

Submit
13. The WBS is a key input to the risk identification process because it:

Explanation

The correct answer is "Identifies all the work that must be done and therefore helps identify potential sources of risk." The Work Breakdown Structure (WBS) is a hierarchical decomposition of the project scope into smaller, manageable work packages. By identifying all the work that must be done, the WBS helps in identifying potential sources of risk. It allows project managers to analyze each work package and determine the risks associated with it. This helps in developing effective risk management strategies and mitigating potential threats to the project's success.

Submit
14. Interface coordination is the art of sponsor management by the project manager.

Explanation

Interface coordination is not specifically related to sponsor management by the project manager. It refers to the process of managing and coordinating the interactions and communications between different interfaces or components within a project. While sponsor management may be a part of the project manager's responsibilities, it is not the sole focus of interface coordination. Therefore, the statement is false.

Submit
15. The project manager is responsible to create the list of level 2 tasks for the entire project.

Explanation

The project manager is not solely responsible for creating the list of level 2 tasks for the entire project. This task is typically a collaborative effort involving the project manager, team members, and stakeholders. The project manager may facilitate the process and provide guidance, but ultimately, the creation of the list should involve input from multiple perspectives to ensure accuracy and completeness. Therefore, the statement is false.

Submit
16. The mission statement is found in the Overview section of the Project Plan

Explanation

The mission statement is not found in the Overview section of the Project Plan. The mission statement is typically a separate document or section that outlines the purpose, goals, and values of the project. It is usually located at the beginning of the project plan or in a dedicated section specifically for the mission statement. Therefore, the given answer is false.

Submit
17. All the following criteria are considered essential to the assessment of technical risk except:

Explanation

The correct answer is critical path analysis. Critical path analysis is a project management technique used to identify the sequence of tasks that must be completed on time in order to complete the project as scheduled. It helps in determining the shortest possible duration for completing the project. However, it does not directly assess technical risk. Technical risk refers to the potential problems or challenges that may arise during the development of a system, such as technological limitations or uncertainties. Therefore, critical path analysis is not considered essential for the assessment of technical risk.

Submit
18. The simplest form of risk analysis is:

Explanation

Probability analysis is the simplest form of risk analysis because it involves assessing the likelihood of different outcomes occurring. It focuses on quantifying the chances of specific events happening and the potential impact they may have on a project or decision. By analyzing probabilities, one can identify and prioritize risks, make informed decisions, and develop appropriate risk mitigation strategies. This method is straightforward and widely used in various industries to evaluate and manage risks effectively.

Submit
19. A workaround is defined as:

Explanation

A workaround is an unplanned response to negative risk events. This means that when unexpected issues or risks arise, a workaround is a spontaneous action taken to address and mitigate those risks. It is not a pro-active planned method, a specific response described in a risk management plan, or a plan of action to follow when something unexpected happens. Instead, it is an ad hoc solution that is implemented to deal with unforeseen risks.

Submit
20. All of the following statements about risk avoidance is true except that it:

Explanation

Risk avoidance focuses on eliminating or minimizing the elements that are creating the risk. It includes making the decision not to bid on a project with high risk exposure and leaving the risk with the customer when they are in the best position to mitigate it. However, accepting the consequences of the risk event should it occur is not a characteristic of risk avoidance. Instead, risk avoidance aims to prevent or minimize the occurrence of the risk event in the first place.

Submit
21. Of the following types of historical information that serve as input to risk identification, which one is the least reliable?

Explanation

Lessons learned databases are the least reliable type of historical information that serves as input to risk identification. This is because lessons learned databases are often subjective and based on individual experiences and opinions. The information stored in these databases may not be comprehensive or accurate, as it relies on the willingness of individuals to share their experiences and lessons. Additionally, lessons learned databases may not be regularly updated or maintained, leading to outdated or incomplete information. Therefore, when identifying risks, it is important to consider lessons learned databases cautiously and verify the information from other more reliable sources.

Submit
22. Additional risk response development is needed when the:

Explanation

When the Work Breakdown Structure (WBS) is changed, additional risk response development is needed. The WBS is a hierarchical decomposition of the project scope into smaller, more manageable components. Any changes to the WBS can have an impact on the project's risks. The change in the WBS may introduce new risks or alter the existing risk landscape. Therefore, it is necessary to reassess the project's risks and develop appropriate risk responses to address the potential impact of the changed WBS.

Submit
23. A risk trigger is:

Explanation

A risk trigger is a symptom of a risk. It is an indicator or a warning sign that suggests the presence of a potential risk. It helps in identifying and recognizing the occurrence of a risk event. By monitoring and identifying these triggers, organizations can take proactive measures to mitigate or respond to the risk before it escalates into a larger problem. Therefore, a risk trigger acts as an early warning system, alerting stakeholders to the presence of a risk and allowing them to take appropriate actions.

Submit
24. The first requirement for effective risk management is:

Explanation

Having project team members who are trained in risk and understand its causes is crucial for effective risk management. These team members can identify potential risks, assess their likelihood and impact, and develop appropriate mitigation strategies. Their understanding of risk allows them to make informed decisions and take proactive measures to minimize or eliminate risks. By involving knowledgeable team members in risk management, the project can benefit from their expertise and ensure that risks are properly addressed throughout the project lifecycle.

Submit
25. Risk exposure measures the:

Explanation

Risk exposure measures the range of schedule and cost outcomes. This means that it assesses the potential variability in the estimated time and cost required for a project or activity. By considering the range of possible outcomes, risk exposure helps to identify and quantify the potential impact of risks on the project's schedule and cost. It allows project managers to better understand and plan for potential risks and their potential effects on the project's timeline and budget.

Submit
View My Results

Quiz Review Timeline (Updated): Mar 18, 2023 +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 18, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Apr 19, 2011
    Quiz Created by
    Babjam
Cancel
  • All
    All (25)
  • Unanswered
    Unanswered ()
  • Answered
    Answered ()
Insufficient upfront planning is the major contributor  to a...
At anytime during the project the project manager should be able to...
The Project Manager is responsible to create a list of major...
Which of the following is an example of an extenal risk?
A project plan document is shown as a "Microsoft Project"...
Project forms, charts and tables are created and altered for each...
To be effective, the risk management process should:
There are ten major sections to a project plan.
The LRC is a document managed by the project manager that depicts the...
Risk mitigation involves:
The term risk portfolio refers to:
Categories of risk response are:
The WBS is a key input to the risk identification process because it:
Interface coordination is the art of sponsor management by the project...
The project manager is responsible to create the list of level 2 tasks...
The mission statement is found in the Overview section of the Project...
All the following criteria are considered essential to the assessment...
The simplest form of risk analysis is:
A workaround is defined as:
All of the following statements about risk avoidance is true except...
Of the following types of historical information that serve as input...
Additional risk response development is needed when the:
A risk trigger is:
The first requirement for effective risk management is:
Risk exposure measures the:
Alert!

Advertisement