PM In Practice : Risk Week 4

Approved & Edited by ProProfs Editorial Team
The editorial team at ProProfs Quizzes consists of a select group of subject experts, trivia writers, and quiz masters who have authored over 10,000 quizzes taken by more than 100 million users. This team includes our in-house seasoned quiz moderators and subject matter experts. Our editorial experts, spread across the world, are rigorously trained using our comprehensive guidelines to ensure that you receive the highest quality quizzes.
Learn about Our Editorial Process
| By Babjam
B
Babjam
Community Contributor
Quizzes Created: 14 | Total Attempts: 30,492
Questions: 25 | Attempts: 167

SettingsSettingsSettings
PM In Practice  :  Risk Week 4 - Quiz

Questions and Answers
  • 1. 

    There are ten major sections to a project plan.

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    The statement is false because there are typically five major sections to a project plan, which include the introduction, project goals and objectives, project scope, project timeline and milestones, and project budget. While there may be variations in the structure and content of project plans, it is generally agreed that there are five essential sections.

    Rate this question:

  • 2. 

    The mission statement is found in the Overview section of the Project Plan

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    The mission statement is not found in the Overview section of the Project Plan. The mission statement is typically a separate document or section that outlines the purpose, goals, and values of the project. It is usually located at the beginning of the project plan or in a dedicated section specifically for the mission statement. Therefore, the given answer is false.

    Rate this question:

  • 3. 

    Project forms, charts and tables are created and altered for each project by the project manager.

    • A.

      True

    • B.

      False

    Correct Answer
    A. True
    Explanation
    The statement is true because project forms, charts, and tables are essential tools for project management. These documents are used to track project progress, allocate resources, and communicate information to stakeholders. The project manager is responsible for creating and altering these documents as needed to ensure that the project is on track and all necessary information is captured.

    Rate this question:

  • 4. 

    The project manager is responsible to create the list of level 2 tasks for the entire project.

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    The project manager is not solely responsible for creating the list of level 2 tasks for the entire project. This task is typically a collaborative effort involving the project manager, team members, and stakeholders. The project manager may facilitate the process and provide guidance, but ultimately, the creation of the list should involve input from multiple perspectives to ensure accuracy and completeness. Therefore, the statement is false.

    Rate this question:

  • 5. 

    A project plan document is shown as a "Microsoft Project" document.

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    The statement is false because a project plan document is not shown as a "Microsoft Project" document. A project plan document is typically created using project management software like Microsoft Project, but it is usually saved in a different file format such as .docx or .pdf. The "Microsoft Project" document format is specific to the software itself and is used to create and manage project schedules and tasks.

    Rate this question:

  • 6. 

    At anytime during the project the project manager should be able to give the sponsors:

    • A.

      An accurate assessment of what has been accomplished and what is yet to be accomplished.

    • B.

      An end state project schedule

    • C.

      A complete list of risks.

    • D.

      A resource Histogram of the completed project

    Correct Answer
    A. An accurate assessment of what has been accomplished and what is yet to be accomplished.
    Explanation
    The project manager should be able to provide the sponsors with an accurate assessment of what has been accomplished and what is yet to be accomplished. This is important for the sponsors to have a clear understanding of the progress of the project and to make informed decisions regarding its future. The other options mentioned in the question, such as an end state project schedule, a complete list of risks, and a resource histogram, are also important aspects of project management but may not necessarily be required to be provided to the sponsors at any given time during the project.

    Rate this question:

  • 7. 

    The Project Manager is responsible to create a list of major activities that are required to meet the project objectives.

    • A.

      True

    • B.

      False

    Correct Answer
    A. True
    Explanation
    The project manager plays a crucial role in planning and organizing the project activities. One of their responsibilities is to create a list of major activities that are necessary to achieve the project objectives. This list helps in identifying the tasks that need to be completed and ensures that all the necessary activities are included in the project plan. By creating this list, the project manager can effectively allocate resources, set priorities, and monitor the progress of the project. Therefore, the statement is true.

    Rate this question:

  • 8. 

    The LRC is a document managed by the project manager that depicts the project tasks listed in rows and includes the department that is responsible to complete the tasks.

    • A.

      True

    • B.

      False

    Correct Answer
    A. True
    Explanation
    The LRC, or the Labor Resource Chart, is indeed a document managed by the project manager. It lists the project tasks in rows and specifies the department responsible for completing each task. This document helps in organizing and assigning tasks efficiently, ensuring that each department knows their responsibilities and can complete their assigned tasks effectively.

    Rate this question:

  • 9. 

    Insufficient upfront planning is the major contributor  to a project going over budget or late in delivery.

    • A.

      True

    • B.

      False

    Correct Answer
    A. True
    Explanation
    Insufficient upfront planning can lead to a project going over budget or being delayed. Without proper planning, there may be a lack of clarity on project requirements, timelines, and resource allocation. This can result in unexpected costs, scope creep, and inefficient use of resources. Adequate upfront planning helps identify potential risks and allows for better estimation and allocation of resources, reducing the chances of budget overruns or delays in project delivery.

    Rate this question:

  • 10. 

    Interface coordination is the art of sponsor management by the project manager.

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    Interface coordination is not specifically related to sponsor management by the project manager. It refers to the process of managing and coordinating the interactions and communications between different interfaces or components within a project. While sponsor management may be a part of the project manager's responsibilities, it is not the sole focus of interface coordination. Therefore, the statement is false.

    Rate this question:

  • 11. 

    The first requirement for effective risk management is:

    • A.

      Ownership of the risks that are identified

    • B.

      Appointment of the project manager early in the process to manage the identified risks

    • C.

      Clear visibility of the information needed for decision making

    • D.

      Project team members who are trained in risk and understand its causes to help construct and implement risk mitigation strategies

    Correct Answer
    D. Project team members who are trained in risk and understand its causes to help construct and implement risk mitigation strategies
    Explanation
    Having project team members who are trained in risk and understand its causes is crucial for effective risk management. These team members can identify potential risks, assess their likelihood and impact, and develop appropriate mitigation strategies. Their understanding of risk allows them to make informed decisions and take proactive measures to minimize or eliminate risks. By involving knowledgeable team members in risk management, the project can benefit from their expertise and ensure that risks are properly addressed throughout the project lifecycle.

    Rate this question:

  • 12. 

    Of the following types of historical information that serve as input to risk identification, which one is the least reliable?

    • A.

      Project files

    • B.

      Project team knowledge

    • C.

      Commercial databases

    • D.

      Lessons learned databases

    Correct Answer
    D. Lessons learned databases
    Explanation
    Lessons learned databases are the least reliable type of historical information that serves as input to risk identification. This is because lessons learned databases are often subjective and based on individual experiences and opinions. The information stored in these databases may not be comprehensive or accurate, as it relies on the willingness of individuals to share their experiences and lessons. Additionally, lessons learned databases may not be regularly updated or maintained, leading to outdated or incomplete information. Therefore, when identifying risks, it is important to consider lessons learned databases cautiously and verify the information from other more reliable sources.

    Rate this question:

  • 13. 

    The term risk portfolio refers to:

    • A.

      Risk quantification strategies

    • B.

      Identified schedule and cost risks

    • C.

      Cumulative EMV of the most critical risks

    • D.

      Risk data assembled for the management of the project.

    Correct Answer
    D. Risk data assembled for the management of the project.
    Explanation
    The term risk portfolio refers to the collection and organization of risk data that is gathered and used for the purpose of managing a project. This includes identifying and assessing potential risks, analyzing their potential impact, and developing strategies to mitigate or respond to them. The risk portfolio provides a comprehensive view of all the risks associated with the project, allowing the project management team to make informed decisions and take appropriate actions to minimize the negative impacts of these risks.

    Rate this question:

  • 14. 

    A workaround is defined as:

    • A.

      A pro-active planned method of responding to risks.

    • B.

      A specific response to certain types of risk as described in the risk management plan.

    • C.

      A plan of action to follow when something unexpected happens

    • D.

      An unplanned response to negative risk events

    Correct Answer
    D. An unplanned response to negative risk events
    Explanation
    A workaround is an unplanned response to negative risk events. This means that when unexpected issues or risks arise, a workaround is a spontaneous action taken to address and mitigate those risks. It is not a pro-active planned method, a specific response described in a risk management plan, or a plan of action to follow when something unexpected happens. Instead, it is an ad hoc solution that is implemented to deal with unforeseen risks.

    Rate this question:

  • 15. 

    All the following criteria are considered essential to the assessment of technical risk except:

    • A.

      Reassessment to detect changes in risk during a system's development

    • B.

      Explicit attention to technical risk, not just to schedule or cost risk

    • C.

      Critical path analysis

    • D.

      Planned procedures for completing project activities

    Correct Answer
    C. Critical path analysis
    Explanation
    The correct answer is critical path analysis. Critical path analysis is a project management technique used to identify the sequence of tasks that must be completed on time in order to complete the project as scheduled. It helps in determining the shortest possible duration for completing the project. However, it does not directly assess technical risk. Technical risk refers to the potential problems or challenges that may arise during the development of a system, such as technological limitations or uncertainties. Therefore, critical path analysis is not considered essential for the assessment of technical risk.

    Rate this question:

  • 16. 

    The WBS is a key input to the risk identification process because it:

    • A.

      Identifies all the work that must be done and therefore helps identify potential sources of risk.

    • B.

      Identifies all the work that must be done and therefore includes all the risks on the project.

    • C.

      Helps organize all the work that must be done on the project

    • D.

      Identifies work packages, which enables specific responsibility to be assigned.

    Correct Answer
    A. Identifies all the work that must be done and therefore helps identify potential sources of risk.
    Explanation
    The correct answer is "Identifies all the work that must be done and therefore helps identify potential sources of risk." The Work Breakdown Structure (WBS) is a hierarchical decomposition of the project scope into smaller, manageable work packages. By identifying all the work that must be done, the WBS helps in identifying potential sources of risk. It allows project managers to analyze each work package and determine the risks associated with it. This helps in developing effective risk management strategies and mitigating potential threats to the project's success.

    Rate this question:

  • 17. 

    All of the following statements about risk avoidance is true except that it:

    • A.

      Focuses on eliminating the elements that are creating the risk.

    • B.

      Accepts the consequences of the risk event should it occur

    • C.

      Includes making the decision not to bid on a project in which the risk exposure is believed to be too high.

    • D.

      Includes leaving the risk with the customer when the customer is in the best position to mitigate the risk

    Correct Answer
    B. Accepts the consequences of the risk event should it occur
    Explanation
    Risk avoidance focuses on eliminating or minimizing the elements that are creating the risk. It includes making the decision not to bid on a project with high risk exposure and leaving the risk with the customer when they are in the best position to mitigate it. However, accepting the consequences of the risk event should it occur is not a characteristic of risk avoidance. Instead, risk avoidance aims to prevent or minimize the occurrence of the risk event in the first place.

    Rate this question:

  • 18. 

    The simplest form of risk analysis is:

    • A.

      Probability analysis

    • B.

      The Delphi method

    • C.

      Sensitivity analysis

    • D.

      Utility theory

    Correct Answer
    A. Probability analysis
    Explanation
    Probability analysis is the simplest form of risk analysis because it involves assessing the likelihood of different outcomes occurring. It focuses on quantifying the chances of specific events happening and the potential impact they may have on a project or decision. By analyzing probabilities, one can identify and prioritize risks, make informed decisions, and develop appropriate risk mitigation strategies. This method is straightforward and widely used in various industries to evaluate and manage risks effectively.

    Rate this question:

  • 19. 

    Categories of risk response are:

    • A.

      Technical, marketing, financial, and human

    • B.

      Identification, quantification, response development, and response control

    • C.

      Avoidance, mitigation, and acceptance

    • D.

      Avoidance, retention, control, and deflection

    Correct Answer
    C. Avoidance, mitigation, and acceptance
    Explanation
    The categories of risk response are avoidance, mitigation, and acceptance. Avoidance involves eliminating the risk by avoiding the activity that could lead to it. Mitigation involves reducing the impact or likelihood of the risk through proactive measures. Acceptance involves acknowledging the risk and its potential consequences without taking any specific action to address it. These categories provide a framework for organizations to assess and address risks in their operations and decision-making processes.

    Rate this question:

  • 20. 

    To be effective, the risk management process should:

    • A.

      Be applied primarily during the concept and closeout phases and to some extent during the implementation and planning phases

    • B.

      Be applied throughout the project and at all levels of system decomposition and project organization

    • C.

      Include assembly of certain stakeholders to identify risks and develop mitigation strategies.

    • D.

      Focus on those risks that senior management finds most critical

    Correct Answer
    B. Be applied throughout the project and at all levels of system decomposition and project organization
    Explanation
    The correct answer is "be applied throughout the project and at all levels of system decomposition and project organization". This means that risk management should be implemented from the beginning of the project until its completion, and it should be integrated into all aspects of the project, including system decomposition and project organization. This approach ensures that risks are identified and managed at every stage of the project, minimizing the potential impact on the project's success.

    Rate this question:

  • 21. 

    Risk exposure measures the:

    • A.

      Variability of the estimate

    • B.

      Range of schedule and cost outcomes

    • C.

      Product of the probability and impact of the analysis

    • D.

      Reduced monetary value of the risk event

    Correct Answer
    B. Range of schedule and cost outcomes
    Explanation
    Risk exposure measures the range of schedule and cost outcomes. This means that it assesses the potential variability in the estimated time and cost required for a project or activity. By considering the range of possible outcomes, risk exposure helps to identify and quantify the potential impact of risks on the project's schedule and cost. It allows project managers to better understand and plan for potential risks and their potential effects on the project's timeline and budget.

    Rate this question:

  • 22. 

    Additional risk response development is needed when the:

    • A.

      Project Plan is updated

    • B.

      Risk event was unexpected or the the effect was greater than anticipated

    • C.

      Cost baseline is changed

    • D.

      WBS was changed

    Correct Answer
    D. WBS was changed
    Explanation
    When the Work Breakdown Structure (WBS) is changed, additional risk response development is needed. The WBS is a hierarchical decomposition of the project scope into smaller, more manageable components. Any changes to the WBS can have an impact on the project's risks. The change in the WBS may introduce new risks or alter the existing risk landscape. Therefore, it is necessary to reassess the project's risks and develop appropriate risk responses to address the potential impact of the changed WBS.

    Rate this question:

  • 23. 

    A risk trigger is:

    • A.

      The root cause of the risk event

    • B.

      An input of the risk identification process

    • C.

      A planned risk response to be acted upon should an identified risk occur

    • D.

      A symptom of a risk

    Correct Answer
    D. A symptom of a risk
    Explanation
    A risk trigger is a symptom of a risk. It is an indicator or a warning sign that suggests the presence of a potential risk. It helps in identifying and recognizing the occurrence of a risk event. By monitoring and identifying these triggers, organizations can take proactive measures to mitigate or respond to the risk before it escalates into a larger problem. Therefore, a risk trigger acts as an early warning system, alerting stakeholders to the presence of a risk and allowing them to take appropriate actions.

    Rate this question:

  • 24. 

    Which of the following is an example of an extenal risk?

    • A.

      Poor staff assignments

    • B.

      Incorrect cost estimates

    • C.

      Inflation

    • D.

      Contract type

    Correct Answer
    C. Inflation
    Explanation
    Inflation is an example of an external risk because it is a factor that is beyond the control of the organization. It refers to the general increase in prices of goods and services over time, which can negatively impact the financial stability of a business. Inflation can lead to higher costs of production, reduced purchasing power, and increased prices for raw materials or resources, ultimately affecting the profitability and competitiveness of a company. Therefore, it is considered an external risk as it is influenced by external economic factors rather than internal decisions or actions of the organization.

    Rate this question:

  • 25. 

    Risk mitigation involves:

    • A.

      Using performance and payment bonds

    • B.

      Eliminating a specific threat by eliminating the cause

    • C.

      Avoiding the schedule risk inherent in the project.

    • D.

      Reducing the expected monetary value of a risk event by reducing the probability of the occurrence

    Correct Answer
    D. Reducing the expected monetary value of a risk event by reducing the probability of the occurrence
    Explanation
    Risk mitigation is the process of minimizing or eliminating potential risks that could negatively impact a project. One way to achieve this is by reducing the expected monetary value of a risk event. This involves identifying and assessing the probability of a risk occurring and then implementing measures to decrease the likelihood of it happening. By reducing the probability of a risk event, the potential financial impact is also reduced, thus mitigating the overall risk to the project.

    Rate this question:

Quiz Review Timeline +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 18, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Apr 19, 2011
    Quiz Created by
    Babjam

Related Topics

Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.