Operations Management Quiz 3 evaluates knowledge in project and operations management, focusing on Gantt charts, critical paths, and ethical standards. It tests understanding of project timelines, critical task sequencing, and professional ethics in management.
The critical path is A-B-C, duration 15.
The critical path is A-C, duration 12.
The critical path is A-B-C, duration 13.5
The critical path cannot be determined without knowing PERT expected activity times.
The network has no critical path.
Rate this question:
A-C; 12
A-D-E; 19
B-E; 13
A-B-C-D-E; 29
None of the above
Rate this question:
Has been established by the Project Management Institute
Has been formulated by the Federal government
Has been formulated by the World Trade Organization
Is inappropriate, since everyone should use the same guidance on ethical issues
Does not exist at this time
Rate this question:
Constraint
Slack variable
Objective function
Violation of linearity
Decision variable
Rate this question:
Area of optimal solutions
Area of feasible solutions
Profit maximization space
Region of optimality
Region of non-negativity
Rate this question:
There are two paths in this network.
There are four paths in this network.
There are five paths in this network.
There are 25 paths through this network.
None of these statements is true.
Rate this question:
2X ≥ 7X*Y
2X*7Y≥500
2X+7Y≥100
2X2+7Y≥50
All of the above are valid linear programming constraints.
Rate this question:
(0, 0), (50, 0), (0, 21), and (20, 15)
(0, 0), (70, 0), (25, 0), and (15, 20)
(20, 15)
(0, 0), (0, 100), and (210, 0)
None of the above
Rate this question:
There are four corner points including (50, 0) and (0, 12.5).
The two corner points are (0, 0) and (50, 12.5).
The graphical origin (0, 0) is not in the feasible region.
The feasible region includes all points that satisfy one constraint, the other, or both.
The feasible region cannot be determined without knowing whether the problem is to be minimized or maximized.
Rate this question:
X = 2, y = 1
X = 1, y = 5
X = -1, y = 1
X = 4, y = 4
X = 2, y = 8
Rate this question:
Expected time is an estimate of the time an activity will require if everything goes as planned.
The optimistic time estimate is an estimate of the maximum time an activity will require.
The probable time estimate is calculated as t = (a+4m+b)/6.
Pessimistic time estimate is an estimate of the minimum time an activity will require.
Most likely time estimate is an estimate of the maximum time an activity will require.
Rate this question:
Even though Bechtel is over 100 years old, the Kuwaiti oil fields was its first "project."
Bechtel is the world's premier manager of massive construction and engineering projects.
Bechtel's competitive advantage is supply chain management.
While its projects are worldwide, its network of suppliers is largely in the U.S.
All of the above are true.
Rate this question:
1-3, 3-4, 4-5
2-3, 3-4, 4-5
2-3, 3-5
1-4, 4-5
Two of the Above
Rate this question:
Maximize $40Y = $25Z
Maximize $40Y + $25Z
Maximize $30Y + $20Z
Maximize 0.25Y + 0.20Z
None of the above
Rate this question:
The shortest of all paths through the network is the critical path.
Some activities on the critical path may have slack.
Every network has exactly one critical path.
On a specific project, there can be multiple critical paths, all with exactly the same duration.
The duration of the critical path is the average duration of all paths in the project network.
Rate this question:
Gantt charts give a timeline and precedence relationships for each activity of a project.
Gantt charts use the four standard spines of Methods, Materials, Manpower, and Machinery.
Gantt charts are visual devices that show the duration of activities in a project.
Gantt charts are expensive.
All of the above are true.
Rate this question:
Finding the value of the objective function at the origin
Moving the iso-profit line to the highest level that still touches some part of the feasible regio
Moving the iso-profit line to the lowest level that still touches some part of the feasible region
Finding the coordinates at each corner of the feasible solution space
None of the above
Rate this question:
X+Y>100andX+Y
X+Y>15andX–Y
X+Y5
X
All of the above have a bounded maximum.
Rate this question:
X = 2, y = 0
X = 0, y = 3
X = 0, y = 0
X = 1, y = 5
None of the above
Rate this question:
X+Y>15andX–Y
X+Y>5andX>10
X>10andY>20
X+Y>100andX+Y
All of the above have a feasible region.
Rate this question:
A-B-D; 10
A-B-E; 11
C-E; 12
A-D-E; 13
A-B-C-D-E; 22
Rate this question:
X = -1, y = 1
X = 0, y = 4
X = 2, y = 1
X = 5, y = 1
X = 2, y = 0
There can be multiple critical paths on the same project, all with different durations.
The early finish of an activity is the latest early start of all preceding activities.
The late start of an activity is its late finish plus its duration.
If a specific project has multiple critical paths, all of them will have the same duration.
All of the above are true.
The early finish of an activity is the early start of that activity plus its duration.
The late finish is the earliest of the late start times of all successor activities.
The late start of an activity is its late finish less its duration.
The late finish of an activity is the earliest late start of all preceding activities.
The early start of an activity is the latest early finish of all preceding activities.
Rate this question:
The shadow price of the added resource will rise
The solution stays the same; the extra resource can't be used without more of the other scarce resource.
The extra resource will cause the value of the objective to fall.
The optimal mix will be rearranged to use the added resource, and the value of the objective function will rise.
None of the above
Rate this question:
A-D-E; 5
B-E; 6
B-D-E; 7
A-C-E; 10
B-C-E; 12
Rate this question:
An objective function, expressed in terms of linear equations
Constraint equations, expressed as linear equations
An objective function, to be maximized or minimized
Alternative courses of action
For each decision variable, there must be one constraint or resource limit
Rate this question:
3X≥Y
X≤3Y
X+Y≥3
X–3Y≥0
3X≤Y
Rate this question:
Can be used to help solve a profit maximizing linear programming problem
Is parallel to all other iso-profit lines in the same problem
Is a line with the same profit at all points
None of the above
All of the above
Rate this question:
Quiz Review Timeline (Updated): Mar 21, 2023 +
Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.
Strategic Consensus Of Operations Room 101
This quiz evaluates knowledge and perceptions of supervisory roles and communication effectiveness in an operational setting.
Questions:
10 |
Attempts:
78 |
Last updated:
Mar 15, 2023
|
Operations Management - QP9
Operations Management - QP9 explores key concepts in efficient business practices, focusing on JIT systems, kanban usage, and operational strategies like setup times and...
Questions:
10 |
Attempts:
131 |
Last updated:
Jul 26, 2024
|
Operations Management Basic Questions! Quiz
Test your knowledge on the fundamentals of operations management with this quiz. It covers key concepts such as JIT methods, scheduling, and capacity planning, focusing on...
Questions:
10 |
Attempts:
165 |
Last updated:
Mar 22, 2023
|
Operations Management - QP7
Operations Management - QP7 explores managerial expertise, Japanese economic strategies, productivity measures, and problem-solving methodologies. It assesses understanding of...
Questions:
14 |
Attempts:
152 |
Last updated:
Sep 06, 2024
|
Operations Management - QP6
Operations Management - QP6 examines key concepts in operations management, including the Kano model, quality costs, and pricing influence. This quiz assesses understanding of...
Questions:
15 |
Attempts:
180 |
Last updated:
Mar 22, 2023
|
Operations Management - QP2
Operations Management - QP2 is a quiz designed to assess understanding in product development and market strategies. It evaluates knowledge on R&D groundwork, product strategies,...
Questions:
12 |
Attempts:
233 |
Last updated:
Mar 21, 2023
|
Wait!
Here's an interesting quiz for you.