This quiz covers deployment planning, mobilization planning, and readiness reporting in the Air Force as per the 2019 guidelines.
2 kilometers (km)
4 km
8 km
16 km
Rate this question:
MQ–9 Reaper
RQ–11B Raven
MQ–1B Predator
RQ–4B Global Hawk
Rate this question:
Funding
Technical solution
Requirements management plan
Answers, guidance, and education
Rate this question:
Cost management plan
Allied support plan
Technical plan
Material plan
Rate this question:
Follow-up
Controlling
Organization
Documenting
Rate this question:
1
2
3
4
Rate this question:
Organic
Contract
Inorganic
Self-Help
Rate this question:
Programming Plan (PPLAN)
Program Action Directive (PAD)
Operations Plan (OPLAN) major paragraph
Time Phased Force and Deployment Data (TPFDD)
Rate this question:
Special Measures
Administration
Assumptions
Logistics
Rate this question:
Sole Source
Firm Fixed Price
Time and Material
Performance Based
Rate this question:
Base Civil Engineering
Gaining Work Center
Contracting Office
Quality Assurance
Rate this question:
Force protection
Airfield operations
Force accountability
Explosive Ordinance Disposal (EOD)
Rate this question:
Generate the mission
Establish the airbase
Operate the airbase
Robust the airbase
Rate this question:
1942
1954
1988
1998
Rate this question:
Processes
Priorities
Requirements
Technical solutions
Rate this question:
Requires services from outside agencies
Mobility (deployment) equipment
Requires additional manpower
Requires additional funding
Rate this question:
Major Construction
Minor Construction
All military construction
None, construction projects do not require authorization and appropriation
Rate this question:
Force protection and logistics
Intelligence and force protection
Secure communications and intelligence
Secure communications and force accountability
Rate this question:
Pilot Units
Joint Planners
Logistics Readiness Squadron
Each unit is responsible for building its own LOGDET
Rate this question:
Work orders
Trouble tickets
Infrastructure requirements
Communications and Information Systems Installation Records (CSIR)
Rate this question:
AFTO Form 745
AFTO Form 747
AFTO Form 749
AF Form 1747
Rate this question:
Service design, service transition, service plan, and continual service improvement
Service plan, service transition, service operation, and continual service improvement
Service design, service transition, service operation, and continual service improvement
Service design, service disposition, service operation, and continual service improvement
Rate this question:
Concept Plan
Functional Plan
Supporting Plan
Operational Plan
Rate this question:
Communications and Information (C&I) Systems Planning Forum
Facilities Utilization Board
Mission Briefings
Informal Meeting
Rate this question:
6 months
1 year
2 years
3 years
Rate this question:
Scott AFB, IL
Travis AFB, CA
Peterson AFB, CO
Joint Base McGuire-Dix-Lakehurst, NJ
Rate this question:
Air Force Personnel Center (AFPC) Aerospace Expeditionary Forces (AEF) Center
Installation Deployment Officer (IDO)
Unit Deployment Monitor (UDM)
Joint Staff
Rate this question:
2 days, 7 days
2 days, 14 days
7 days, 14 days
14 days, 30 days
Rate this question:
Project monitor
Project manager
Program action officer
Program action monitor
Rate this question:
38 Engineering Squadron (ES)
38 Contracting Squadron (CONS)
38 Operations Support Squadron (OSS)
85 Engineering Installation Squadron (EIS)
Rate this question:
The status
A milestone
A deliverable
The final result
Rate this question:
Standard unit type code (UTC)
Joint force/capability
In-lieu-of (ILO)
Ad hoc
Rate this question:
Strategy
Combat plans
Combat support
Combat operations
Rate this question:
Status request
Defect repairs
Preventive action
Corrective action
Rate this question:
AF Form 1067
DD Form 1067
AF Form 1144
DD Form 1144
Rate this question:
3D0X3, Cyber Surety
3D1X2, Cyber Transport Systems
3D1X3, RF Transmission Systems
3D1X7, Cable and Antenna Systems
Rate this question:
Training
Personnel
Home station mission
Equipment condition
Rate this question:
Command and control
Operate the airbase
Robust the airbase
Open the airbase
Rate this question:
Project monitor
Project manager
Communication squadron
Implementing organization
Rate this question:
Facility Manager
Quality Assurance Evaluator
Functional Director/Commander
Unit plans, planning, and agreements section
Rate this question:
MPTO 00–33A–1001
MPTO 00–33A–1002
MPTO 00–33A–2001
MPTO 00–33A–2002
Rate this question:
Major
Minor
Major and minor
Major and critical
Rate this question:
AF Form 1146
AF Form 1747
AFTO Form 46
AFTO Form 47
Rate this question:
Request for action and organization validation
Using command and lead command validation
Work center manager certification and approval
Program manager review and approval of technical requirements and solution
Rate this question:
Unusual or compelling urgency
Unit commander’s interest
National security interests
Sole Source
Rate this question:
Volume 1
Volume 2
Volume 3
Volume 4
Rate this question:
$750 thousand (K)
$1 million (M)
$1.5 M
$5 M
Rate this question:
Training
Personnel
Facility condition
Equipment condition
Rate this question:
Quiz Review Timeline (Updated): Jun 18, 2024 +
Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.