Chapter 3 Trivia Quiz: Project Management

10 Questions | Total Attempts: 629

SettingsSettingsSettings
Chapter 3 Trivia Quiz: Project Management - Quiz

Welcome to the trivia quiz designed to help you review chapter 3 in the project management course you are undertaking. A chapter review is a good way to ensure that you understand each chapter perfectly. Do give it a try and feel free to take it as many times as you wish.


Questions and Answers
  • 1. 
    A _________ is a series of actions directed toward a particular result
    • A. 

      Goal

    • B. 

      Process

    • C. 

      Plan

    • D. 

      Project

  • 2. 
    _______________ processes include coordinating people and other resources to carry out the project plans and produce the products, services, or results of the project or phase.
    • A. 

      Initiating

    • B. 

      Planning

    • C. 

      Executing

    • D. 

      Monitoring and controlling

    • E. 

      Closing

  • 3. 
    Which process group normally requires the most resources and time?
    • A. 

      Initiating

    • B. 

      Planning

    • C. 

      Executing

    • D. 

      Monitoring and controlling

    • E. 

      Closing

  • 4. 
    What methodology was developed in the U.K., defines 45 separate subprocesses, and organizes these into eight process groups?
    • A. 

      Six Sigma

    • B. 

      RUP

    • C. 

      PMBOK Guide

    • D. 

      PRINCE2

  • 5. 
    Which of the following outputs is often completed before initiating a project?
    • A. 

      Stakeholder register

    • B. 

      Business case

    • C. 

      Project charter

    • D. 

      Kick-off meeting

  • 6. 
    A work breakdown structure, project schedule, and cost estimates are outputs of the ________________ process.
    • A. 

      Initiating

    • B. 

      Planning

    • C. 

      Executing

    • D. 

      Monitoring and controlling

    • E. 

      Closing

  • 7. 
    Initializing involves developing a project charter, which is part of the project ________ management knowledge area.
    • A. 

      Integration

    • B. 

      Scope

    • C. 

      Communications

    • D. 

      Risk

  • 8. 
    __________ involves measuring progress toward project objectives and taking corrective action.
    • A. 

      Initiating

    • B. 

      Planning

    • C. 

      Execution

    • D. 

      Monitoring and controlling

    • E. 

      Closing

  • 9. 
    What type of report do project teams create to reflect on what went right and what went wrong with the project?
    • A. 

      Lesson-learned report

    • B. 

      Progress report

    • C. 

      Final project report

    • D. 

      Business case

  • 10. 
    Many people use __________ to have a standard format for preparing various project management documents.
    • A. 

      Methodologies

    • B. 

      Templates

    • C. 

      Project management software

    • D. 

      Standards