Microsoft Project Test

Reviewed by Editorial Team
The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Timmy198
T
Timmy198
Community Contributor
Quizzes Created: 577 | Total Attempts: 339,004
| Attempts: 3,543 | Questions: 10
Please wait...
Question 1 / 10
0 %
0/100
Score 0/100
1. What is the default view of a new project?

Explanation

The default view of a new project is the Gantt view. This view displays the project tasks and their corresponding timelines in the form of a Gantt chart. It allows users to visualize the project schedule, dependencies, and progress easily. The Gantt view is commonly used in project management to track and manage tasks efficiently.

Submit
Please wait...
About This Quiz
Microsoft Project Test - Quiz

This is a software which manages projects of firms, organizations and companies. It was created, developed and sold by Microsoft. It asists project managers develop plans, assigning resources to tasks and projects. A software costs up to 590 USD. What do you know? Have these quiz.

Personalize your quiz and earn a certificate with your name on it!
2. Project lets you customize the calender for?

Explanation

The project calendar can be customized to cater to the needs of the people working on the project. It can be adjusted to reflect the project duration accurately, ensuring that all the important milestones and deadlines are included. Additionally, the calendar can be used to schedule and track the tasks that are part of the project, allowing for better organization and coordination. Therefore, all of the given options are valid reasons for customizing the project calendar.

Submit
3. When you create a task, you can apply a subtask or set subtasks?

Explanation

You can apply a subtask or set subtasks to any task entered in the task list entry table. This means that when creating a task, you have the option to break it down into smaller subtasks or assign subtasks to existing tasks in the list. This flexibility allows for better organization and management of tasks, ensuring that each task can be further divided and tracked if necessary.

Submit
4. Can all tasks be set as recurring?

Explanation

All tasks can be set as recurring because the option to set a task as recurring is available in most task management systems. This allows users to automatically repeat tasks at specified intervals, such as daily, weekly, monthly, or annually. Recurring tasks are useful for activities that need to be performed regularly, such as paying bills, attending meetings, or completing routine chores. By setting tasks as recurring, users can save time and effort by avoiding the need to manually create the same task repeatedly.

Submit
5. How can you recognise the timeframe of a new project?

Explanation

To recognize the timeframe of a new project, one should choose the project information in the properties group in the project tab. This implies that there is a specific feature or option available in the properties group that allows users to input or select the timeframe for the project. This suggests that the timeframe can be identified and set within the project properties, indicating that it is possible to recognize the timeframe of a new project.

Submit
6. What is the latest version of the Microsoft project?

Explanation

The latest version of Microsoft Project is Project 2016.

Submit
7. Is it included among the office suite?

Explanation

The given answer "No" suggests that the item in question is not included among the office suite.

Submit
8. What year was Microsoft project released?

Explanation

Microsoft Project was released in 1984.

Submit
9. Which one do you like?

Explanation

Assigning a duration of zero days to the milestone task is the correct answer because a milestone task is a significant event or achievement in a project that marks progress. It does not require any specific duration as it represents a point in time rather than a task that requires time to complete. Therefore, assigning a duration of zero days accurately represents the nature of a milestone task.

Submit
10. What year was the Macintosh version released?

Explanation

The correct answer is 1991. This is the year when the Macintosh version was released.

Submit
View My Results

Quiz Review Timeline (Updated): Mar 22, 2023 +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 22, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Mar 05, 2018
    Quiz Created by
    Timmy198
Cancel
  • All
    All (10)
  • Unanswered
    Unanswered ()
  • Answered
    Answered ()
What is the default view of a new project?
Project lets you customize the calender for?
When you create a task, you can apply a subtask or set subtasks?
Can all tasks be set as recurring?
How can you recognise the timeframe of a new project?
What is the latest version of the Microsoft project?
Is it included among the office suite?
What year was Microsoft project released?
Which one do you like?