Contracting 7 Level CDCs

Reviewed by Editorial Team
The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Pgreen946
P
Pgreen946
Community Contributor
Quizzes Created: 1 | Total Attempts: 386
| Attempts: 386 | Questions: 101
Please wait...
Question 1 / 101
0 %
0/100
Score 0/100
1. Who is required to receive job safety training?

Explanation

All government personnel are required to receive job safety training. This includes civilian personnel, military personnel, and contractor personnel. This training ensures that all government employees are aware of the potential hazards in their workplace and are equipped with the necessary knowledge and skills to prevent accidents and injuries. It is important for all government personnel to receive this training to maintain a safe and healthy working environment for everyone.

Submit
Please wait...
About This Quiz
CDC Quizzes & Trivia

This quiz assesses knowledge in government contracting, focusing on the Contracting 7 Level CDCs. It covers key areas such as LPTA source selection, RFP structure, proposal evaluation, and... see moresolicitation factors, essential for professionals in contract management. see less

2. Which of the following is used to update and post the percentage completed to the appropriate time interval on the progress schedule?

Explanation

A progress report is used to update and post the percentage completed to the appropriate time interval on the progress schedule. This report provides an overview of the progress made on a project, including the tasks completed, milestones achieved, and any issues or delays encountered. It allows stakeholders to track the project's progress and make informed decisions regarding resource allocation and schedule adjustments. Payrolls, preorientation conferences, and material approval submittals are not directly related to updating and posting the percentage completed on a progress schedule.

Submit
3. What procedure is available for use by contractors and the government to resolve issues in controversy?

Explanation

Alternative Dispute Resolution (ADR) refers to a procedure that allows contractors and the government to resolve issues in controversy without going through litigation. ADR methods, such as mediation or arbitration, provide a more informal and less adversarial approach to dispute resolution. It allows both parties to negotiate and find a mutually acceptable solution, which can often be more efficient and cost-effective than going to court. This option is commonly used in contract disputes to avoid the lengthy and expensive process of litigation.

Submit
4. What action might a contract officer (CO) take if an untimely request for a debriefing was received?

Explanation

The correct answer is that the CO may decline to provide the debriefing. This is because the question specifically states that the request for a debriefing is untimely. In such cases, the CO has the discretion to decline the request.

Submit
5. What process is used to request relief from deployment taskings due to extenuating circumstances?

Explanation

A "reclama" is a process used to request relief from deployment taskings due to extenuating circumstances. This allows individuals to seek relief from their assigned tasks if they have valid reasons such as medical issues or personal emergencies. It provides a formal channel for individuals to communicate their situation and request for alternative arrangements or exemptions from their deployment responsibilities.

Submit
6. What is not a benefit of the Self-Inspection Program?

Explanation

The Self-Inspection Program offers several benefits such as identifying training needs, allowing for immediate corrective actions, and promoting effective levels of standardization. However, it does not dissolve the need for other compliance inspections. This means that even with the implementation of the Self-Inspection Program, other compliance inspections are still necessary to ensure full compliance with regulations and standards.

Submit
7. It may become necessary to walk away from negotiations when

Explanation

When negotiations reach a point where a reasonable person would deem it to be a bad deal, it may become necessary to walk away. This means that if the terms and conditions of the negotiation do not meet the standards of what a reasonable individual would consider fair or beneficial, it is better to discontinue the negotiation rather than accepting an unfavorable agreement. This decision is based on the judgment of a reasonable person's assessment of the deal's value and potential outcomes.

Submit
8. What document is used to support the price agreement in all negotiated awards not based on adequate price competition?

Explanation

The Price Negotiation Memorandum is used to support the price agreement in all negotiated awards not based on adequate price competition. It is a document that summarizes the negotiations, justifications, and decisions made during the price negotiation process. It includes information such as the background of the procurement, the offeror's proposal, the government's analysis of the proposal, and the final negotiated price. The Price Negotiation Memorandum is an essential document for ensuring transparency and accountability in the procurement process.

Submit
9. Post-award debriefings must include

Explanation

Post-award debriefings must include the government's evaluation of the significant weaknesses in the offeror's proposal. This is important because it allows the offeror to understand the areas where their proposal fell short and how it was evaluated by the government. By providing this information, the offeror can gain valuable insights into their weaknesses and improve their future proposals. It also promotes transparency and fairness in the procurement process by ensuring that the offeror has a clear understanding of the evaluation criteria and how their proposal was assessed.

Submit
10. All of the following are responsibilities of the Quality Assurance Program Coordinator except

Explanation

The Quality Assurance Program Coordinator is responsible for supporting multi-functional teams, assisting with the evaluation of contractor Quality Control Plans, and providing initial and recurring training to contracting officer representatives (COR). However, the role of acting as a liaison between contractors and the wing commander is not a responsibility of the Quality Assurance Program Coordinator.

Submit
11. In noncompetitive negotiations, which price position supports the price believed to be most reasonable based on the government's analysis?

Explanation

In noncompetitive negotiations, the objective price position supports the price believed to be most reasonable based on the government's analysis. This means that the price is determined by considering all relevant factors and data, and is not influenced by competition or other external factors. The objective price position aims to find a fair and reasonable price that reflects the true value of the goods or services being negotiated.

Submit
12. What action must be taken if a proposal exceeds established page limitations stated in the solicitation?

Explanation

If a proposal exceeds the established page limitations stated in the solicitation, the action that must be taken is to remove pages in excess of the maximum allowed from the back of the proposal. This means that any pages that go beyond the specified limit should be taken out from the back of the proposal. This is necessary to ensure that the proposal adheres to the stated page limitations and to maintain fairness and consistency in the evaluation process.

Submit
13. Simplified Acquisition of Base Engineer Requirements (SABER) contracts normally authorize the inclusion of minimum design in task orders up to

Explanation

Simplified Acquisition of Base Engineer Requirements (SABER) contracts typically allow for the inclusion of minimum design in task orders up to 35%. This means that when issuing task orders under a SABER contract, the contracting officer can authorize the inclusion of design work up to a maximum of 35% of the total task order value. This allows for flexibility in the contract and ensures that the necessary design work can be included as needed while still maintaining the simplified acquisition process.

Submit
14. A proposal that meets requirements and indicates an exceptional approach and understanding of the requirements is given what color/rating?

Explanation

The proposal that meets requirements and demonstrates an exceptional approach and understanding of the requirements is rated as Blue/Outstanding. This indicates that the proposal goes above and beyond expectations and stands out as exceptional compared to other proposals.

Submit
15. How might the overall quality of awards packages be improved?

Explanation

Involving people in the process of creating awards packages can improve the overall quality. This allows for different perspectives and input, ensuring that the awards are fair and accurately reflect the achievements of the individuals. It also promotes transparency and inclusivity, as everyone has a chance to contribute and provide feedback. Additionally, involving people in the process can help identify any biases or inconsistencies that may exist in the current system and work towards addressing them.

Submit
16. Simplified Acquisition of Base Engineer Requirements (SABER) is generally best suited for

Explanation

Simplified Acquisition of Base Engineer Requirements (SABER) is a procurement method that is typically used for non-complex minor construction projects. This means that it is most suitable for small-scale projects that do not require extensive design work. SABER is designed to streamline the acquisition process for these types of projects, making it a cost-effective and efficient option. This method is not specifically geared towards cost-type contracts or projects estimated at less than $100K, but rather for non-complex minor construction projects.

Submit
17. Which of the following is not a characteristic of the Acquisition Professional Development Program?

Explanation

The correct answer is "It requires members to quickly attain the highest possible certification." This means that the Acquisition Professional Development Program does not prioritize or require members to achieve the highest certification quickly. The program is designed to be a progressive program of training and education, allowing individuals to advance at their own pace. The other options all describe characteristics of the program, such as using Community College of the Air Force course work for credits and requiring both military and civilian personnel to meet education and training standards.

Submit
18. The inability to compromise may be avoided by

Explanation

Establishing an opening position that allows room to compromise is a strategy that can help avoid the inability to compromise. By starting with a position that is not extreme or rigid, there is flexibility to negotiate and find common ground. This approach creates a cooperative environment and encourages both parties to work towards finding a mutually satisfactory solution.

Submit
19. Which section of a request for proposal (RFP) provides offerors with instructions for proposal preparation?

Explanation

Section L of a request for proposal (RFP) typically provides offerors with instructions for proposal preparation. This section outlines the specific requirements and guidelines that potential vendors must follow when preparing and submitting their proposals. It may include information on the format, structure, and content that should be included in the proposal, as well as any specific instructions or evaluation criteria that will be used to assess the proposals.

Submit
20. What type of Contractor Performance Assessment Reporting System (CPARS) report is used at the end of the first 12 month option period on a 5 year contract?

Explanation

The correct answer is Annual interim report. This report is used at the end of the first 12 month option period on a 5 year contract. It provides an assessment of the contractor's performance during the first year of the contract and serves as a progress update. It helps to evaluate the contractor's ability to meet the requirements and expectations of the contract, and provides valuable feedback for future decision-making regarding the contract.

Submit
21. How often must the contracting squadron commander brief the installation commander on government purchase card violations, suspended accounts, and surveillance results?

Explanation

The contracting squadron commander must brief the installation commander on government purchase card violations, suspended accounts, and surveillance results at least quarterly. This frequency allows for regular updates and communication between the two commanders regarding any violations or issues related to government purchase cards. A quarterly briefing ensures that the installation commander remains informed and can take appropriate actions if necessary.

Submit
22. Which of the following is true when determining the competitive range?

Explanation

The correct answer is to limit the number of proposals to the greatest number that will permit an efficient competition among the most highly rated proposals. This means that only a certain number of proposals should be included in the competitive range, based on the number of highly rated proposals and the efficiency of the competition. It does not specify a specific number or percentage, but rather emphasizes the need for efficiency and competition among the top-rated proposals.

Submit
23. Which of the following factors affect comparability during price analysis?

Explanation

Differences in quantities or size can affect comparability during price analysis because when comparing prices, it is important to ensure that the quantities or sizes being compared are similar. If there are significant differences in quantities or sizes, it can distort the comparison and make it difficult to determine the true value or cost. Therefore, it is important to consider and account for these differences when conducting price analysis to ensure accurate and meaningful comparisons.

Submit
24. What type of change improperly exceeds the scope of a procurement and is one which could not have been reasonably anticipated by offerors?

Explanation

A cardinal change is a type of change that goes beyond the scope of a procurement and is one that offerors could not have reasonably anticipated. It is a significant alteration to the original contract that fundamentally changes the nature of the work or the obligations of the parties involved. This type of change is considered improper because it goes beyond what was originally agreed upon and may require a new procurement process to be followed.

Submit
25. What type of exchange does not allow for responses to identified weaknesses, but allows offerors to address apparent minor or clerical errors?

Explanation

Clarifications are a type of exchange in the procurement process that allows offerors to address apparent minor or clerical errors in their proposals. Unlike discussions, which allow for responses to identified weaknesses, clarifications are limited to addressing minor issues and do not allow for significant revisions or improvements to the proposal. Clarifications are typically used to ensure that the proposal is complete, consistent, and accurate, without opening the door for extensive negotiations or changes.

Submit
26. When is a contractor required to certify a claim?

Explanation

A contractor is required to certify a claim when it exceeds $100,000. This means that if the contractor is seeking payment for a claim that is less than $100,000, they are not required to provide a certification. However, if the claim exceeds $100,000, the contractor must certify that the claim is accurate and supported by appropriate documentation. This certification ensures that the contractor is accountable for the claim and that it has been thoroughly reviewed and validated.

Submit
27. Which of the following is an example of an extra-organizational stressor?

Explanation

Financial issues can be considered an example of an extra-organizational stressor because they originate outside of the organization and can have a significant impact on an individual's stress levels. These issues may include personal financial problems, such as debt, unemployment, or economic instability, which can create stress and anxiety for individuals regardless of their work environment. Unlike deployments, increased workload, or network downtime, which are more directly related to the organization's operations, financial issues are external factors that can affect an individual's well-being and performance in the workplace.

Submit
28. What option does a contract officer (CO) have to expedite fiscal year-end requirements reserved for Simplified Acquisition of Base Engineer Requirements (SABER) when funding is not yet available?

Explanation

The correct answer is to obtain a no-cost or hold harmless agreement and process up to the point of award. This means that the contract officer can proceed with the award process, including negotiations, up until the point of actually awarding the contract. By obtaining a no-cost or hold harmless agreement, the contractor agrees to proceed with the work without receiving payment until funding becomes available. This allows the CO to expedite the fiscal year-end requirements reserved for SABER even when funding is not yet available.

Submit
29. Functional experts assigned to the exercise evaluation team are made up of

Explanation

The functional experts assigned to the exercise evaluation team are comprised of the most qualified unit personnel. This means that the individuals selected for this team are chosen based on their expertise and qualifications within their respective units. By including the most qualified personnel, the evaluation team can ensure that they have the necessary knowledge and skills to effectively assess and evaluate the exercise. This ensures that the evaluation process is thorough and accurate, leading to valuable feedback and improvement opportunities for the units involved.

Submit
30. Offerors without a record of relevant past performance will receive what performance confidence rating?

Explanation

The correct answer is "Unknown Confidence" because if an offeror does not have a record of relevant past performance, it is not possible to assess their performance and determine their confidence rating. Without any information or data about their past performance, it is unknown whether they can perform satisfactorily or if there are any concerns or limitations regarding their capabilities.

Submit
31. Contractor progress schedules are required

Explanation

Contractor progress schedules are required when contracts exceed the Simplified Acquisition Threshold (SAT) and the performance period is greater than 60 days. This means that for construction contracts that have a value above the SAT and a duration of more than 60 days, it is necessary for contractors to provide progress schedules. This allows for better planning, monitoring, and coordination of the construction project, ensuring that it stays on track and meets the required timeline.

Submit
32. What strategic sourcing tool is used to assess data such as money spent, type of contracts used, size of purchase, item(s) purchased, etc?

Explanation

Spend analysis is the correct answer because it is a strategic sourcing tool that helps assess data related to money spent, type of contracts used, size of purchase, and item(s) purchased. It provides insights into spending patterns, identifies cost-saving opportunities, and helps in making informed procurement decisions. Cost analysis focuses on analyzing the cost of individual products or services, price analysis evaluates the pricing of specific items, and portfolio management involves managing a collection of investments.

Submit
33. Technical analysis of offeror proposals should

Explanation

The correct answer is "examine the types and quantities of materials proposed." When conducting a technical analysis of offeror proposals, it is important to examine the types and quantities of materials proposed. This is crucial in determining whether the materials meet the requirements of the project and if they are suitable for the intended purpose. By evaluating the materials, the contract officer can assess the feasibility and effectiveness of each offeror's proposal and make an informed decision based on the analysis.

Submit
34. When a deficiency is found in an offeror's proposal, the government must

Explanation

When a deficiency is found in an offeror's proposal, the government must identify it and provide the offeror an opportunity to improve the proposal. This means that the government will inform the offeror about the deficiency and give them a chance to address and correct it. By doing so, the government ensures fairness and allows the offeror to have a chance to improve their proposal before making a final decision. This approach promotes transparency and gives all offerors an equal opportunity to compete for the award.

Submit
35. Providing career advice to enlisted personnel requires all of the following except

Explanation

The correct answer is "encouraging on duty study time for promotions during downtime." This is because providing career advice to enlisted personnel involves becoming familiar with personnel programs, encouraging membership in professional organizations, and discussing the pros and cons of separating from the Air Force. However, encouraging on duty study time for promotions during downtime is not necessary for providing career advice, as it is not directly related to career guidance or decision-making.

Submit
36. How is pricing established in Simplified Acquisition of Base Engineer Requirements (SABER) contracts?

Explanation

In Simplified Acquisition of Base Engineer Requirements (SABER) contracts, pricing is established using unit price guides and coefficients. This means that there are predetermined prices for different units or quantities of work, and these prices are adjusted based on coefficients that take into account factors such as location, labor rates, and material costs. This method allows for consistency and transparency in pricing, as well as efficiency in the contract negotiation process.

Submit
37. Contractor costs such as overhead, profit, design cost, bond premiums, and General & Administrative (G&A) expenses are

Explanation

Contractor costs such as overhead, profit, design cost, bond premiums, and General & Administrative (G&A) expenses are negotiated into coefficients. This means that these costs are factored into the coefficients used to determine the final price of a contract. The coefficients are determined through negotiation between the contractor and the client, taking into account the specific requirements of the project. By negotiating these costs into coefficients, both parties can ensure that the final price accurately reflects the expenses incurred by the contractor.

Submit
38. Price or cost to the government

Explanation

In every source selection, the price or cost to the government must be evaluated. This means that when making a decision on which source to select, the government must consider the price or cost associated with each option. This evaluation is necessary to ensure that the government is making a cost-effective decision and getting the best value for their money. By evaluating the price or cost in every source selection, the government can make informed decisions and ensure that taxpayer dollars are being used efficiently.

Submit
39. A preconstruction orientation

Explanation

A preconstruction orientation may be used to issue the Notice to Proceed. This means that the orientation serves as a formal confirmation or authorization for the contractor to begin work on a project. It indicates that all necessary preparations and requirements have been met, and the contractor can proceed with the construction process. The orientation may include important information about the project, such as timelines, expectations, and safety guidelines, ensuring that the contractor is well-informed before starting work.

Submit
40. Payments against Simplified Acquisition of Base Engineer Requirements (SABER) task orders are typically based upon

Explanation

Payments against Simplified Acquisition of Base Engineer Requirements (SABER) task orders are typically based on a percentage of completion for projects of 60 calendar days or longer. This means that the contractor will receive payments based on the progress made on the project, with the percentage increasing as the project nears completion. This method ensures that contractors are incentivized to complete the project in a timely manner and provides a fair payment structure based on the work completed.

Submit
41. A contractor may submit a claim

Explanation

A contractor may submit a claim within 6 years after accrual of a claim. This means that the contractor has a time limit of 6 years from the point when the claim first arises to submit their claim. This allows the contractor a reasonable amount of time to gather evidence, assess damages, and prepare their claim before submitting it. It is important for the contractor to be aware of this time limit to ensure they do not miss the deadline and potentially lose their right to submit a claim.

Submit
42. An offeror's technical volume is used by offerors to

Explanation

The offeror's technical volume is used to address how it intends to meet the government's requirement. This volume provides a detailed explanation of the offeror's approach, methodology, and resources that will be utilized to fulfill the government's needs. It outlines the specific strategies, techniques, and solutions that the offeror plans to employ to meet the stated requirements. This information helps the government evaluate the feasibility and effectiveness of the offeror's proposed approach and determine if it aligns with their needs.

Submit
43. Which unit management program assists units in determining whether or not they are in compliance with applicable laws, regulations, and policies?

Explanation

A self-inspection program is a unit management program that helps units assess their compliance with relevant laws, regulations, and policies. This program allows units to conduct internal inspections and identify any areas where they may be non-compliant. By proactively examining their operations, units can take corrective actions to ensure they are following the required guidelines. This program is a proactive approach to compliance management, allowing units to address any issues before they are identified during external inspections or audits.

Submit
44. What information is provided in Part II of the Career Field Education and Training Plan (CFETP)?

Explanation

Part II of the Career Field Education and Training Plan (CFETP) provides information on duties, tasks, and references. This section outlines the specific responsibilities and tasks that individuals in the career field are expected to perform. It also includes references to additional resources and materials that can be used to support training and development in the field.

Submit
45. Which of the following is not an internal management control of the government purchase card program?

Explanation

The establishment of grade requirements for cardholders is not an internal management control of the government purchase card program because it pertains to the qualifications and eligibility criteria for individuals holding the card, rather than a control measure put in place to ensure the proper use and monitoring of the card program. Internal management controls typically involve measures such as separation of duties, span of control, and separation of function to prevent fraud, conflicts of interest, and ensure accountability and oversight in the program.

Submit
46. The Air Force Contracting Officer test

Explanation

The Air Force Contracting Officer test is required for warrants above the simplified acquisition threshold. This means that individuals who want to obtain a contracting officer warrant for contracts that exceed the simplified acquisition threshold must pass this test. The test consists of 50 questions, is timed, and is closed book. In order to pass the test, candidates must score a minimum of 75%.

Submit
47. Solicitation evaluation factors are used to distinguish one proposal from another by

Explanation

Solicitation evaluation factors are used to differentiate or distinguish one proposal from another. These factors are used to evaluate and compare the proposals submitted by different vendors or suppliers. By using discriminators, the evaluation factors can effectively identify the unique or distinguishing features of each proposal, allowing for a fair and objective evaluation process. This helps in selecting the most suitable proposal that meets the requirements and objectives of the solicitation.

Submit
48. In order for an enlisted member to obtain the Acquisition Professional DevelopmentProgram (APDP) Level III certification, they must meet all of the following requirements except

Explanation

To obtain the Acquisition Professional Development Program (APDP) Level III certification, enlisted members must meet several requirements. These include possessing a Community College of the Air Force (CCAF) degree, occupying a superintendent position, and completing the SNCOA correspondence course. However, holding the rank of Senior/Chief Master Sergeant is not a requirement for obtaining the certification.

Submit
49. Common aspects of past performance relevancy include all of the following except

Explanation

The question is asking for the exception among the common aspects of past performance relevancy. The options provided are complexity, dollar value, similarity of service/support, and number of contracts performed. Complexity, dollar value, and similarity of service/support are all relevant factors when considering past performance. However, the number of contracts performed is not directly related to the relevancy of past performance. Therefore, the correct answer is number of contracts performed.

Submit
50. A designator determining detailed manpower and logistical support requirements that describes necessary personnel, skill levels, numbers, and equipment required for deployments is called a

Explanation

A unit type code is a designator that outlines the specific manpower and logistical support needed for deployments. It includes details such as the required personnel, skill levels, numbers, and equipment. This code helps in accurately determining the resources and capabilities required for a particular mission or operation.

Submit
51. Which of the following tools enable commanders to report the ability of an individual unit type code to perform its mission capability?

Explanation

The AEF Reporting Tool enables commanders to report the ability of an individual unit type code to perform its mission capability. This tool provides a platform for commanders to assess and report on the readiness and effectiveness of their units. It allows them to track and analyze various factors such as training, resources, and overall mission readiness. By using the AEF Reporting Tool, commanders can make informed decisions and take appropriate actions to ensure the readiness and effectiveness of their units.

Submit
52. Grounds for a protest include all of the following except

Explanation

The grounds for a protest include relaxing the announced criteria, failure to follow the existing criteria, and imposing additional unannounced criteria to increase the number of discriminators needed to include only the most highly rated proposals. However, excluding offerors from the competitive range that are not amongst the most highly rated proposals is not a valid ground for a protest.

Submit
53. Upon completion of a debriefing, offerors must be notified that

Explanation

Upon completion of a debriefing, offerors must be notified that no further questions are permissible. This means that after the debriefing, the offerors cannot ask any more questions or seek any further clarifications regarding the process or their proposal. It indicates that the debriefing session is the final opportunity for the offerors to gather information and seek clarification, and they cannot extend the process by asking additional questions.

Submit
54. When you as a supervisor, schedule a goal oriented plan for subordinate training, it builds confidence for the trainee by

Explanation

When a supervisor schedules a goal-oriented plan for subordinate training, it helps to build confidence for the trainee by allowing them to achieve each particular goal. This approach breaks down the overall training process into smaller, more manageable tasks, giving the trainee a sense of accomplishment as they successfully complete each goal. By achieving these goals, the trainee can see their progress and feel more confident in their abilities. This method also provides clear direction and structure to the training, making it easier for the trainee to understand and follow.

Submit
55. Which of the following is a contractor entitled to when the government fails to provide timely submittal approval?

Explanation

When the government fails to provide timely submittal approval, a contractor is entitled to both time and money. This means that the contractor can request an extension of the project timeline and also seek compensation for any additional costs incurred due to the delay. This is because the delay in submittal approval can disrupt the contractor's schedule and lead to financial losses, which the government is responsible for compensating.

Submit
56. Which statement does not apply when a contractor undertakes voluntary acceleration?

Explanation

When a contractor undertakes voluntary acceleration, it means that they are choosing to speed up the work on their own accord. In this situation, the acceleration is not always compensable if the government allows it to continue. This means that the contractor may not necessarily be entitled to additional compensation for the accelerated work, even if the government does not intervene or stop the acceleration.

Submit
57. When a protest is received before award, a contract may not be awarded unless

Explanation

When a protest is received before award, a contract may not be awarded unless it is justified in writing for urgent and compelling reasons and approved at a level above the CO. This means that the protest must be supported by a written justification that explains why the contract should be awarded despite the protest. Additionally, the approval must come from a higher authority than the contracting officer, ensuring that there is an objective review of the situation. This process helps to ensure fairness and transparency in the awarding of contracts.

Submit
58. The overall objective of negotiations is to

Explanation

The correct answer is to negotiate a contract type with a price providing the greatest incentive for efficient performance. This means that the objective of negotiations is to create a contract that motivates the contractor to perform their best and achieve the desired outcomes in a cost-effective manner. By aligning the contract price with performance incentives, the government aims to maximize value for money and ensure efficient delivery of goods or services.

Submit
59. Which of the following responsibilities is not identified in AFI 64–102, Operational Contracting Program, as a function to be overseen by the contracting squadron superintendent?

Explanation

The correct answer is "Competition advocate." In AFI 64-102, the responsibilities of the contracting squadron superintendent are outlined, and overseeing the competition advocate function is not mentioned as one of those responsibilities. The competition advocate is responsible for promoting and supporting competition in the acquisition process, but this role is not specifically assigned to the contracting squadron superintendent in this document.

Submit
60. Contracting Level I certification is identified by what special experience identifier (SEI)?

Explanation

Contracting Level I certification is identified by the special experience identifier (SEI) 129.

Submit
61. Which of the following may be disclosed when conducting a preaward debriefing?

Explanation

During a preaward debriefing, the rationale for eliminating an offeror from the competition may be disclosed. This means that the procuring agency can provide an explanation as to why a particular offeror was not selected or eliminated from the competition. This information helps the offeror understand the decision-making process and provides transparency in the procurement process. However, the number of offerors, the identity of other offerors, and the ranking of the offeror in comparison with others are typically not disclosed during a preaward debriefing.

Submit
62. When a preconstruction orientation is held, offerors must be informed of significant matters including all of the following except

Explanation

During a preconstruction orientation, offerors are provided with important information regarding the project. This includes contracting authority, statutory matters such as labor standards, and a review of performance and payment bonds. However, the pricing schedule is not typically discussed during this orientation. The pricing schedule is usually submitted by the offerors themselves as part of their proposal and is evaluated separately by the contracting authority. Therefore, it is not necessary to review the pricing schedule during the preconstruction orientation.

Submit
63. Benefits of strategic sourcing include all of the following except

Explanation

Strategic sourcing is a procurement strategy that aims to improve efficiency and effectiveness by optimizing the purchasing process. The benefits of strategic sourcing include reduced duplication of effort, as it helps eliminate redundant tasks and streamline operations. It also enhances supplier relationships by fostering collaboration and long-term partnerships. Additionally, it standardizes business processes, ensuring consistency and quality across the organization. However, increased consolidation of contracts is not a benefit of strategic sourcing. Instead, strategic sourcing focuses on optimizing supplier selection and contract management to achieve cost savings and improved performance.

Submit
64. The Contractor Performance Assessment Reporting System (CPARS) provides a centralized repository of contractor performance information for

Explanation

The correct answer is "unclassified use only." This means that the Contractor Performance Assessment Reporting System (CPARS) is intended for use with information that is not classified. It is a centralized repository where performance information about contractors can be stored and accessed, but this information does not contain any classified data.

Submit
65. An evaluation of contractor performance must be prepared for orders placed against Federal Supply Schedules (FSS) and that exceed what dollar threshold?

Explanation

not-available-via-ai

Submit
66. When submitting the contract officer's (CO) statement of facts to the Government Accountability Office (GAO), which of the following documents should not be included as supporting documentation?

Explanation

When submitting the CO's statement of facts to the GAO, legal reviews should not be included as supporting documentation. Legal reviews are internal evaluations conducted by the contracting officer's legal team and are not typically required to be shared with external entities like the GAO. The other options - source selection plan, abstract of bids or offers, and proposal analysis documents - are all relevant supporting documents that provide information on the contract process and decision-making.

Submit
67. When evaluating proposal revisions in a lowest price technically acceptable (LPTA) source selection 

Explanation

In a lowest price technically acceptable (LPTA) source selection, the evaluation criteria established in the Request for Proposal (RFP) must be used. This means that when evaluating proposal revisions, the government must compare the proposals against each other based on the criteria outlined in the RFP. The government cannot request final proposal revisions from any offerors and can only make tradeoffs between cost/price and non-cost/price factors as specified in the RFP.

Submit
68. Contractor progress schedules are reviewed to make sure

Explanation

Contractor progress schedules are reviewed to ensure that the length of time allotted for each task is reasonable based on the task being performed. This is important because if the time allotted for a task is too short, it may lead to delays and hinder the overall progress of the project. On the other hand, if the time allotted is too long, it may result in unnecessary delays and inefficiencies. Therefore, reviewing the length of time allotted for each task helps to ensure that the project stays on track and progresses smoothly.

Submit
69. Which of the following is true regarding awards made without discussions?

Explanation

The correct answer is that the government may hold discussions at any time regardless of the request for proposal (RFP) instructions. This means that even if the RFP does not explicitly state that discussions will be held, the government still has the option to hold discussions with offerors. This allows the government to gather additional information or negotiate terms with the offerors before making a final decision on the award.

Submit
70. Which of the follow priorities is assigned to students that do not occupy an acquisition coded position?

Explanation

Students who do not occupy an acquisition coded position are assigned Priority 4. This means that they have the lowest priority in terms of acquiring positions.

Submit
71. Which of the following actions is subject to business clearance approval?

Explanation

An action intended to result in the award of a competed contract is subject to business clearance approval. This means that before awarding a contract, the action must go through a clearance process to ensure that it aligns with the business objectives and meets all necessary requirements. This approval helps to ensure that the contract award is fair, competitive, and in the best interest of the business.

Submit
72. Which of the following is true regarding the evaluation of past performance?

Explanation

The correct answer is "Evaluations should take into account past performance information regarding predecessor companies." This means that when evaluating the past performance of an offeror, it is important to consider the performance of any predecessor companies that may have relevant experience or history. This information can provide valuable insights into the capabilities and track record of the offeror, even if they have undergone changes or reorganizations in the past.

Submit
73. Which of the following clauses allows for time extensions in the event of a delay due to fire, flood, or labor strikes?

Explanation

The default clause allows for time extensions in the event of a delay due to fire, flood, or labor strikes. This clause is typically included in contracts to provide protection for the contractor in case unforeseen circumstances occur that are beyond their control and result in project delays. By invoking the default clause, the contractor can request additional time to complete the project without facing penalties or liquidated damages.

Submit
74. A statement of facts must be prepared by the contract officer (CO) within how many business days after receiving notification of a protest to the Government Accountability Office (GAO)?

Explanation

The correct answer is 10 days. After receiving notification of a protest to the Government Accountability Office (GAO), the contract officer (CO) is required to prepare a statement of facts within 10 business days. This statement includes all relevant information and documentation related to the protest. It is crucial for the CO to adhere to this timeline to ensure a timely resolution of the protest and maintain transparency in the procurement process.

Submit
75. Which of the following statements regarding the source selection decision document (SSDD) is incorrect?

Explanation

The given correct answer is incorrect. The SSDD represents the Source Selection Evaluation Team’s independent, integrated, comparative assessment and decision. The SSDD is a document that outlines the rationale for the source selection decision, including the business judgments made and relied upon. It may use reports and analyses prepared by others as supporting rationale. The SSDD must also support the selection of the best value proposal consistent with the stated evaluation criteria.

Submit
76. The purpose of a Utilization and Training Workshop (U&TW) is to

Explanation

The purpose of a Utilization and Training Workshop (U&TW) is to develop a new training standard to accommodate changes in the field. This workshop aims to assess the current training procedures and identify any necessary modifications or updates to ensure that they align with the evolving needs and advancements in the field. By developing a new training standard, the U&TW helps to ensure that military personnel receive the most relevant and effective training to perform their duties efficiently and adapt to changes in their career field.

Submit
77. All of the following are options available to contractors upon receipt of the contract officer's (CO) final decision except

Explanation

Contractors have several options available to them upon receipt of the contract officer's final decision. These include accepting the decision "as is," appealing to the US Court of Federal Claims within 12 months, and appealing to the Armed Services Board of Contract Appeals within 90 days. However, seeking assistance from a third party using Alternate Dispute Resolution is not listed as one of the options available to contractors.

Submit
78. The unit personnel management roster (UPMR) lists available positions, personnel assigned, and

Explanation

The unit personnel management roster (UPMR) includes information on projected gains and losses. This means that it lists the number of personnel that are expected to join or leave the unit in the future. This information is important for planning and managing the unit's personnel resources effectively. By knowing the projected gains and losses, the unit can make necessary adjustments in terms of recruitment, training, and deployment to ensure that it has the right number of personnel with the required skills and qualifications.

Submit
79. All of the following actions can help eliminate the potential for protests, except

Explanation

The correct answer is "ensure all of an offeror’s questions are answered." This option does not help eliminate the potential for protests because it is important to address all questions and concerns raised by the offeror in order to ensure a fair and transparent process. By answering the questions, the offeror gains clarity and understanding, reducing the likelihood of filing a protest. Therefore, not answering the offeror's questions increases the potential for protests. On the other hand, providing timely debriefings, documenting exclusion notifications, and using source selection documents for debriefing material all contribute to transparency and fairness, reducing the potential for protests.

Submit
80. The ratification authority for unauthorized commitments less than $30,000 is the

Explanation

The chief of the contracting office is the ratification authority for unauthorized commitments less than $30,000. This means that if someone within the organization makes a commitment without proper authorization and the cost of that commitment is less than $30,000, the chief of the contracting office has the authority to ratify or approve that commitment. This ensures that the organization can still fulfill its obligations even in cases where unauthorized commitments are made, as long as they fall within the specified monetary limit.

Submit
81. Responsibilities as the enlisted advisor to squadron leadership does not include

Explanation

The correct answer is advising only the commander on enlisted matters. As the enlisted advisor to squadron leadership, one's responsibilities include overseeing awards and decorations, providing input on disciplinary actions, and ensuring civilians understand the enlisted evaluation system. However, it is not solely limited to advising the commander on enlisted matters, as the enlisted advisor is expected to provide guidance and support to the entire squadron leadership team.

Submit
82. The Material and Workmanship clause

Explanation

The Material and Workmanship clause establishes the submittal process. This means that it outlines the procedures and requirements for submitting documents, samples, and other materials related to the construction project. It ensures that contractors and suppliers provide the necessary information and documentation for review and approval before proceeding with the work.

Submit
83. What is the "contract" between the technical school and field personnel that is used to develop training courses called?

Explanation

The "contract" between the technical school and field personnel that is used to develop training courses is called Specialty Training Standard (STS). This standard outlines the specific requirements and objectives for the training courses and serves as a guide for both the technical school and field personnel to ensure that the training is comprehensive and meets the necessary standards. It helps to establish a common understanding and agreement between the two parties regarding the content and delivery of the training courses.

Submit
84. Material Approval Submittals must be approved

Explanation

The correct answer is "within a reasonable time." This means that Material Approval Submittals should be approved in a timely manner, taking into consideration the specific circumstances and requirements of the project. It does not specify a specific number of days, as the time frame may vary depending on the complexity and urgency of the submittal. The focus is on ensuring that the approval is done promptly and efficiently to avoid unnecessary delays in the project.

Submit
85. During the standup phase

Explanation

During the standup phase, one of the activities is to gather spend data from various sources such as Federal Procurement Data System-Next Generation (FPDS-NG), government purchase card (GPC) databases, and suppliers. This data is important for understanding the current spending patterns and trends, which can then be used to develop a commodity sourcing strategy (CSS) and formulate recommendations for policies. Additionally, high-level market research is conducted during this phase to gain a better understanding of the market.

Submit
86. Final approval authority for enlisted members to attend any Level III training course resides with

Explanation

The AFCFM (Air Force Career Field Manager) is responsible for managing and overseeing the career field of enlisted members in the Air Force. As such, they have the final approval authority for enlisted members to attend any Level III training course. The DAU (Defense Acquisition University) is not specifically mentioned as having this authority, and the unit commander and MAJCOM (Major Command) commander may have some authority but not the final approval authority. Therefore, the correct answer is AFCFM.

Submit
87. Who is responsible for establishing the Designated Operational Capability Statement for each unit tasked in support of an OPLAN?

Explanation

The MAJCOM Senior Contracting Official (SCO) is responsible for establishing the Designated Operational Capability Statement for each unit tasked in support of an OPLAN. This statement outlines the specific capabilities and resources that the unit will provide during the operation. The SCO plays a crucial role in ensuring that the necessary contracts and agreements are in place to support the unit's deployment and mission requirements. They work closely with the unit and other stakeholders to determine the operational capabilities needed and ensure that the necessary contractual arrangements are made.

Submit
88. When price analysis alone cannot determine a fair and reasonable price,

Explanation

When price analysis alone cannot determine a fair and reasonable price, it is necessary to use a cost analysis to evaluate data other than certified cost or pricing data. This means that other methods and factors need to be considered in order to determine a fair price for the requirement. The use of a cost analysis allows for a more comprehensive evaluation of the data, taking into account various cost factors that may not be captured in certified cost or pricing data.

Submit
89. The lowest price technically acceptable (LPTA) source selection method

Explanation

The correct answer is "may include non-price factors such as technical and past performance." This means that in the lowest price technically acceptable (LPTA) source selection method, non-price factors such as technical capabilities and past performance can be considered alongside the price factor. This allows the government to evaluate proposals based on a combination of price and other relevant factors, rather than solely on the lowest price. The LPTA method allows for tradeoffs between price and non-price factors, giving the government flexibility in selecting the most suitable proposal.

Submit
90. Contract clearance involves all of the following except

Explanation

Contract clearance involves obtaining the necessary approvals for various stages of the procurement process. This includes approval to request final proposal revisions, approval to make a source selection decision, and approval for the source selection authority to make the award. However, approval to issue a solicitation is not part of contract clearance. The solicitation is typically issued before the contract clearance process begins and is used to solicit proposals from potential vendors. Once the solicitation has been issued and the proposals have been received, the contract clearance process begins.

Submit
91. Which of the following methods is not used in support of price analysis?

Explanation

The use of weighted guidelines is not used in support of price analysis. Weighted guidelines are used in the evaluation of proposals and the determination of the most advantageous offer, but they are not specifically used in price analysis. Price analysis involves comparing proposed prices, using parametric estimating methods, and analyzing data other than certified cost or pricing data to determine the reasonableness of prices.

Submit
92. Lowest Price Technically Acceptable (LPTA) source selections consider

Explanation

LPTA source selections consider the acceptability of non-price evaluation factors or subfactors. This means that in LPTA, the selection is based on factors other than price, such as quality, performance, and technical capabilities. The lowest priced proposal that meets the minimum acceptability criteria for these non-price factors is chosen. Price is not the sole determining factor in LPTA, as the focus is on meeting the minimum requirements rather than selecting the lowest priced option.

Submit
93. Which of the following unit type codes represents an equipment package?

Explanation

The unit type code XFFK4 represents an equipment package. The code indicates that the unit is a package of equipment, possibly for a specific purpose or function. The other unit type codes do not indicate that they represent an equipment package.

Submit
94. Which of the following is not one of the phases of strategic sourcing?

Explanation

The correct answer is "Source selection strategy phase" because strategic sourcing typically involves four phases: analysis phase, sourcing strategy phase, negotiation phase, and supplier relationship management phase. The source selection strategy phase is not a recognized phase in strategic sourcing.

Submit
95. Which of the following is not true regarding negotiations?

Explanation

In negotiations, both parties expect movement by the other party, meaning that they anticipate some level of compromise and flexibility from each other. Before entering into competitive discussions, it is recommended to develop separate minimum, objective, and maximum positions for each proposal. In competitive discussions, minimum contract requirements cannot be changed unless all offerors remaining in the competitive range have an opportunity to revise their proposal. However, it is not true that when the price negotiation is based on price analysis, contract officers are required to analyze profit.

Submit
96. Which of the following is not allowable under the Suspension of Work clause?

Explanation

The Suspension of Work clause allows the government to suspend work under the contractor for a period of time as deemed appropriate by the CO (Contracting Officer). It also provides the contractor with an adjustment for any increase in cost of performance. However, it does not allow the contractor to be granted a time extension under this clause.

Submit
97. When opening competitive discussions, all of the following are emphasized to offerors except

Explanation

The correct answer is "the CO will negotiate with only those offerors whose proposals appear most favorable to the government." This statement contradicts the purpose of competitive discussions, which is to encourage open dialogue and allow all offerors to present their positions. The emphasis is on obtaining a win/win result through competition and allowing proposal revisions to clarify positions, rather than solely focusing on the most favorable proposals.

Submit
98. Which of the following management tools is used to ensure contract quality and compliance with established law and policy directives throughout the acquisition process?

Explanation

A contract review committee is a management tool used to ensure contract quality and compliance with established law and policy directives throughout the acquisition process. This committee is responsible for reviewing and evaluating contracts to ensure that they meet all legal and policy requirements. They also ensure that the terms and conditions of the contracts are reasonable and in the best interest of the organization. By conducting thorough reviews, the contract review committee helps to minimize risks and ensure that the organization is in compliance with all applicable laws and regulations.

Submit
99. The operational contracting commander is responsible for all of the following except

Explanation

The operational contracting commander is responsible for reviewing all tasked operational plans, accomplishing and documenting contingency contracting officer training, and developing and maintaining local procedures to support the Comprehensive Emergency Management Plan (CEMP). However, developing contracting support elements and UTC packages to meet the requirements of current policy directives is not one of their responsibilities.

Submit
100. Communications are held after receipt of proposals to

Explanation

After receiving proposals, communications are held to determine whether or not a proposal should be placed in the competitive range. This means that the purpose of the communication is to evaluate the proposals and decide which ones are eligible to proceed to the next stage of the selection process. The communication allows the contracting officer to assess the proposals and determine if they meet the necessary criteria to be considered for further negotiation and potential award.

Submit
101. Which of the following is incorrect regarding discussions?

Explanation

Discussions are not used to establish the competitive range. The competitive range is determined before discussions take place. Discussions are held with offerors who are already in the competitive range, in order to allow them to clarify aspects of their proposal that may be deficient and to make revisions to their proposals.

Submit
View My Results

Quiz Review Timeline (Updated): Mar 20, 2023 +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 20, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Mar 19, 2015
    Quiz Created by
    Pgreen946
Cancel
  • All
    All (101)
  • Unanswered
    Unanswered ()
  • Answered
    Answered ()
Who is required to receive job safety training?
Which of the following is used to update and post the percentage...
What procedure is available for use by contractors and the government...
What action might a contract officer (CO) take if an untimely request...
What process is used to request relief from deployment taskings due to...
What is not a benefit of the Self-Inspection Program?
It may become necessary to walk away from negotiations when
What document is used to support the price agreement in all negotiated...
Post-award debriefings must include
All of the following are responsibilities of the Quality Assurance...
In noncompetitive negotiations, which price position supports the...
What action must be taken if a proposal exceeds established page...
Simplified Acquisition of Base Engineer Requirements (SABER) contracts...
A proposal that meets requirements and indicates an exceptional...
How might the overall quality of awards packages be improved?
Simplified Acquisition of Base Engineer Requirements (SABER) is...
Which of the following is not a characteristic of the Acquisition...
The inability to compromise may be avoided by
Which section of a request for proposal (RFP) provides offerors with...
What type of Contractor Performance Assessment Reporting System...
How often must the contracting squadron commander brief the...
Which of the following is true when determining the competitive range?
Which of the following factors affect comparability during price...
What type of change improperly exceeds the scope of a procurement and...
What type of exchange does not allow for responses to identified...
When is a contractor required to certify a claim?
Which of the following is an example of an extra-organizational...
What option does a contract officer (CO) have to expedite fiscal...
Functional experts assigned to the exercise evaluation team are made...
Offerors without a record of relevant past performance will receive...
Contractor progress schedules are required
What strategic sourcing tool is used to assess data such as money...
Technical analysis of offeror proposals should
When a deficiency is found in an offeror's proposal, the government...
Providing career advice to enlisted personnel requires all of the...
How is pricing established in Simplified Acquisition of Base Engineer...
Contractor costs such as overhead, profit, design cost, bond premiums,...
Price or cost to the government
A preconstruction orientation
Payments against Simplified Acquisition of Base Engineer Requirements...
A contractor may submit a claim
An offeror's technical volume is used by offerors to
Which unit management program assists units in determining whether or...
What information is provided in Part II of the Career Field Education...
Which of the following is not an internal management control of the...
The Air Force Contracting Officer test
Solicitation evaluation factors are used to distinguish one proposal...
In order for an enlisted member to obtain the Acquisition Professional...
Common aspects of past performance relevancy include all of the...
A designator determining detailed manpower and logistical support...
Which of the following tools enable commanders to report the ability...
Grounds for a protest include all of the following except
Upon completion of a debriefing, offerors must be notified that
When you as a supervisor, schedule a goal oriented plan for...
Which of the following is a contractor entitled to when the government...
Which statement does not apply when a contractor undertakes voluntary...
When a protest is received before award, a contract may not be awarded...
The overall objective of negotiations is to
Which of the following responsibilities is not identified in AFI...
Contracting Level I certification is identified by what special...
Which of the following may be disclosed when conducting a preaward...
When a preconstruction orientation is held, offerors must be informed...
Benefits of strategic sourcing include all of the following except
The Contractor Performance Assessment Reporting System (CPARS)...
An evaluation of contractor performance must be prepared for orders...
When submitting the contract officer's (CO) statement of facts to the...
When evaluating proposal revisions in a lowest price technically...
Contractor progress schedules are reviewed to make sure
Which of the following is true regarding awards made without...
Which of the follow priorities is assigned to students that do not...
Which of the following actions is subject to business clearance...
Which of the following is true regarding the evaluation of past...
Which of the following clauses allows for time extensions in the event...
A statement of facts must be prepared by the contract officer (CO)...
Which of the following statements regarding the source selection...
The purpose of a Utilization and Training Workshop (U&TW) is to
All of the following are options available to contractors upon receipt...
The unit personnel management roster (UPMR) lists available positions,...
All of the following actions can help eliminate the potential for...
The ratification authority for unauthorized commitments less than...
Responsibilities as the enlisted advisor to squadron leadership does...
The Material and Workmanship clause
What is the "contract" between the technical school and field...
Material Approval Submittals must be approved
During the standup phase
Final approval authority for enlisted members to attend any Level III...
Who is responsible for establishing the Designated Operational...
When price analysis alone cannot determine a fair and reasonable...
The lowest price technically acceptable (LPTA) source selection method
Contract clearance involves all of the following except
Which of the following methods is not used in support of price...
Lowest Price Technically Acceptable (LPTA) source selections consider
Which of the following unit type codes represents an equipment...
Which of the following is not one of the phases of strategic sourcing?
Which of the following is not true regarding negotiations?
Which of the following is not allowable under the Suspension of Work...
When opening competitive discussions, all of the following are...
Which of the following management tools is used to ensure contract...
The operational contracting commander is responsible for all of the...
Communications are held after receipt of proposals to
Which of the following is incorrect regarding discussions?
Alert!

Advertisement