Managing Project Qualtiy

20 Questions | Attempts: 292
Share

SettingsSettingsSettings
Knowledge Management Quizzes & Trivia

This is about Qualtiy Management Knowledge Area for Project Management.


Questions and Answers
  • 1. 

    1. You are the project manager for the BBB Project. Stacy, a project team member,   is confused about what QA is. Which of the following best describes QA?

    • A.

      A. QA is quality assurance for the overall project performance.

    • B.

      B. QA is quality acceptance according to scope verification.

    • C.

      C. QA is quality assurance for the project deliverable.

    • D.

      D. QA is quality assurance for the project stakeholders.

    Correct Answer
    A. A. QA is quality assurance for the overall project performance.
    Explanation
    A. QA is concerned with overall project quality performance. B, C, and D are
    incorrect because they do not correctly explain quality assurance.

    Rate this question:

  • 2. 

    2. You are the project manager for the Photo Scanning Project. This project is   similar to another project you have completed. Your project is to electronically   store thousands of photos for your city’s historical society. Quality is paramount   on this project. Management approaches you and asks why you have devoted   so much of the project time to planning. Your response is which of the following?

    • A.

      A. This is a first-time, first-use project, so more time is needed for planning.

    • B.

      B. Planning for a project of this size, with this amount of quality, is mandatory. B. Planning for a project of this size, with this amount of quality, is mandatory. B. Planning for a project of this size, with this amount of quality, is mandatory. B. Planning for a project of this size, with this amount of quality, is mandatory.

    • C.

      C. Quality is planned into a project, not inspected in.

    • D.

      D. Quality audits are part of the planning time.

    Correct Answer
    C. C. Quality is planned into a project, not inspected in.
    Explanation
    C. Of all the choices presented, this is the best answer. Quality is planned into
    the project, and the planning requires time. A is incorrect because a project of this nature has been completed before. B is incorrect because there isn’t
    enough information provided to determine what the quality demands of the
    project are. D is incorrect because quality audits are not part of the planning
    processes.

    Rate this question:

  • 3. 

    3. You are the project manager for the Floor Installation Project. Today you plan   to meet with your project team to ensure that the project is completed with   no deviations from the project requirements. This process is which of the   following?

    • A.

      A. Quality Planning A. Quality planning

    • B.

      B.Quality Management

    • C.

      C. Quality control

    • D.

      D. Quality assurance

    Correct Answer
    A. A. Quality Planning A. Quality planning
    Explanation
    A. Quality planning should be completed prior to the work beginning—and
    should thereafter be revisited as needed. B is incorrect, since quality management
    is not an applicable answer to the scenario. C and D are incorrect because QC
    and QA are part of quality management.

    Rate this question:

  • 4. 

    4. You are the project manager for the ASE Project, which must map to industry   standards in order to be accepted by the customer. You and your team have   studied the requirements and have "created a plan" to implement the deliverables   with the appropriate level of quality. What is this process called?

    • A.

      A. Quality planning

    • B.

      B. Quality management

    • C.

      C. Quality control

    • D.

      D. Quality assurance

    Correct Answer
    A. A. Quality planning
    Explanation
    A. Quality planning is the process of creating a plan to meet the requirements
    of quality. B, C, and D are incorrect because they do not explain the process in
    the question’s scenario.

    Rate this question:

  • 5. 

    5. A fishbone diagram is the same as a(n) ______________________ diagram.

    • A.

      A. Ishikawa

    • B.

      B. Pareto

    • C.

      C. Flow

    • D.

      D. Control

    Correct Answer
    A. A. Ishikawa
    Explanation
    A. A fishbone diagram is the same as an Ishikawa diagram. B, C, and D are
    incorrect. These charts and diagrams accomplish goals other than the cause-
    and-effect outcome of the Ishikawa.

    Rate this question:

  • 6. 

    6. Management has asked you to define the correlation between quality and the   project scope. Which of the following is the best answer?

    • A.

      A. The project scope includes metrics for quality.

    • B.

      B. Quality metrics are applied to the project scope.

    • C.

      C. Quality is the process of completing the scope to meet stated or implied needs.

    • D.

      D. Quality is the process of evaluating the project scope to ensure that quality exists.

    Correct Answer
    C. C. Quality is the process of completing the scope to meet stated or implied needs.
    Explanation
    C. Quality, in regard to the project scope, is about completing the work
    as promised. A is incorrect because though the project scope will have
    requirements for acceptance, it may not have metrics for quality defined.
    B and D are also incorrect.

    Rate this question:

  • 7. 

    7. Which of the following is most true about quality?

    • A.

      A. It will cost more money to build quality into the project.

    • B.

      B. It will cost less money to build quality into the project process.

    • C.

      C. Quality is inspection driven.

    • D.

      D. Quality is prevention driven.

    Correct Answer
    D. D. Quality is prevention driven.
    Explanation
    D. Quality is prevention driven. Quality wants to complete the work correctly
    the first time to prevent poor results, a loss of time, and a loss of funds. A
    and B are incorrect. There is no guarantee that a project will cost more or less
    depending on the amount of expected quality. Incidentally, lack of quality will
    likely cost more than quality planning because of the cost of nonconformance.
    C is incorrect because quality is planned into a project, not inspected in.

    Rate this question:

  • 8. 

    8. You are the project manager for the KOY Project, which requires quality that   maps to federal guidelines. To ensure that you can meet these standards, you   have elected to put the project team through training specific to the federal   guidelines your project must adhere to. The costs of these classes can be   assigned to which of the following?

    • A.

      A. The cost of doing business

    • B.

      B. Cost of quality

    • C.

      C. Cost of adherence

    • D.

      D. Cost of nonconformance

    Correct Answer
    B. B. Cost of quality
    Explanation
    B. Training to meet the quality expectations is attributed to the cost of quality.
    A, C, and D are incorrect because these choices do not describe training as a
    cost of quality.

    Rate this question:

  • 9. 

    9. You are the project manager for the KOY Project, which requires quality that   maps to federal guidelines. During a quality audit, you discover that a portion   of the project work is faulty and must be done again. The requirement to do   the work is an example of which of the following?

    • A.

      A. Cost of quality

    • B.

      B. Cost of adherence

    • C.

      C. Cost of nonconformance

    • D.

      D. The cost of doing business

    Correct Answer
    C. C. Cost of nonconformance
    Explanation
    C. When project work results are faulty and must be done over, it is attributed
    to the cost of nonconformance to quality. A, B, and D are all incorrect. These
    values do not describe faulty work or the cost of nonconformance.

    Rate this question:

  • 10. 

       10. You are the project manager of the JKL Project, which currently has some    production flaws. Which analysis tool will allow you to determine the cause    and effect of the production faults?

    • A.

      A. A flowchart

    • B.

      B. A Pareto diagram

    • C.

      C. An Ishikawa diagram

    • D.

      D. A control chart

    Correct Answer
    C. C. An Ishikawa diagram
    Explanation
    C. The key words “cause and effect” equate to the Ishikawa diagram. A is
    incorrect. A flowchart will show how a process moves through the system,
    but not the cause and effect of the problems involved. B is incorrect as well. A
    Pareto diagram maps out the causes and frequency of problems. D, a control
    chart, plots the results of sampling, but it doesn’t show the cause and effect of
    problems.

    Rate this question:

  • 11. 

    11. Linda is the project manager of a manufacturing project. She and her project    team are using design of experiments to look for ways to improve quality.    Which of the following best describes design of experiments?

    • A.

      A. It allows the project manager to move the relationship of activities to complete the project work with the best resources available.

    • B.

      B. It allows the project manager to experiment with the project design to determine what variables are causing the flaws.

    • C.

      C. It allows the project manager to experiment with variables to attempt to improve quality.

    • D.

      D. It allows the project manager to experiment with the project design document to become more productive and to provide higher quality.

    Correct Answer
    C. C. It allows the project manager to experiment with variables to attempt to improve quality.
    Explanation
    C. Design of experiments uses experiments and “what-if” scenarios to determine
    what variables are affecting quality. A is incorrect because design of experiments,
    in regard to quality, is not interested in changing the relationship of activities to
    complete project work. B and D are also incorrect because design of experiments
    will not be changing project design to determine where flaws exist or to become
    more productive.

    Rate this question:

  • 12. 

    12. You are the project manager of the Global Upgrade Project. Your project team    consists of 75 project team members around the world. Each team member    will be upgrading a piece of equipment in many different facilities. Which of    the following could you implement to ensure that project team members are    completing all of the steps in the install procedure with quality?

    • A.

      A. Checklists

    • B.

      B. Work breakdown structure (WBS)

    • C.

      C. Project network diagram (PND)

    • D.

      D. The WBS dictionary

    Correct Answer
    A. A. Checklists
    Explanation
    A. Checklists are simple but effective quality management tools that the project
    manager can use to ensure that the project team is completing the required
    work. B, C, and D are all incorrect. The WBS, PND, and WBS dictionary are not
    tools the project team can necessarily use to prove they’ve completed required
    work. Checklists are the best approach for this scenario.

    Rate this question:

  • 13. 

    13. Mark is the project manager of the PMH Project. Quality audits of the    deliverables show several problems. Management has asked Mark to create a    chart showing the distribution of problems and their frequencies. Given this,    management wants which of the following?

    • A.

      A. A control chart

    • B.

      B. An Ishikawa diagram

    • C.

      C. A Pareto diagram

    • D.

      D. A flowchart

    Correct Answer
    C. C. A Pareto diagram
    Explanation
    C. Management wants Mark to create a Pareto diagram. Recall that a Pareto
    diagram maps out the causes of defects and illustrates their frequency. A is
    incorrect because a control chart does not identify the problems, only the
    relation of the results to the expected mean. B is incorrect because a cause-
    and-effect diagram does not map out the frequency of problems. D is also
    incorrect. Flowcharts show how a process moves through a system and how
    the components are related.

    Rate this question:

  • 14. 

    14. In the illustration to the    right, what does the circled    area represent? Can't insert diagram but you have a mean value with the a circle around data points.

    • A.

      A. Out-of-control data points

    • B.

      B. In-control data points

    • C.

      C. The Rule of Seven

    • D.

      D. Standard deviation

    Correct Answer
    C. C. The Rule of Seven
    Explanation
    C. The circled area shows seven consecutive sampling results, all on one side
    of the mean. This is known as the Rule of Seven and is an assignable cause.
    A is incorrect. These values are in control. B is correct, but it does not fully
    answer the question as choice C does. D is incorrect, since standard deviation
    is a predicted measure of the variance from the expected mean of a sampling.

    Rate this question:

  • 15. 

    15. You are an IT project manager and are working with the project team to    determine the best computer system for the project. You and the project team    decide to measure the performance of both systems to determine which one    performs best. This is an example of which one of the following?

    • A.

      A. A cost/Benefit Analysis

    • B.

      B. Benchmarking

    • C.

      C. Design of experiments

    • D.

      D. Determining the cost of quality

    Correct Answer
    B. B. Benchmarking
    Explanation
    16. A project manager has elected not to enforce safety measures on his construction
    project. One of the project team members has been injured because of this
    oversight, and the job site is closed until an investigation into the lack of
    safety measures is completed. The project will now likely be late, be fined for
    the error, and will lose credibility with the customer. This is an example of
    which one of the following?
    B. This is an example of benchmarking, as the project team is comparing
    one system to another. A, the cost-benefit analysis, would compare the costs
    and associated benefits of each system, rather than just how the two systems
    compare with each other. C, the design of experiments, is a method that
    determines which factors influence the variables of the project’s deliverable.
    D is not a valid answer, as the cost of quality is the dollar amount the project
    must invest to achieve the expected level of quality.

    Rate this question:

  • 16. 

    16. A project manager has elected not to enforce safety measures on his construction    project. One of the project team members has been injured because of this    oversight, and the job site is closed until an investigation into the lack of    safety measures is completed. The project will now likely be late, be fined for    the error, and will lose credibility with the customer. This is an example of    which one of the following?

    • A.

      A. Risk

    • B.

      B. Trigger

    • C.

      C. Cost of poor quality

    • D.

      D. Cost of quality

    Correct Answer
    C. C. Cost of poor quality
    Explanation
    C. This is an example of the cost of poor quality. The project manager should
    have followed the safety measures for the job site, and costs associated with
    the safety measures are considered part of D, the cost of quality. A is incorrect
    because risk is inherent to application work, while the ramifications of not
    enforcing the safety measures is an example of the cost of poor quality. B,
    trigger, is a risk management term that references a condition or warning sign
    that a risk is coming into the project.

    Rate this question:

  • 17. 

    17. Your organization uses total quality management as part of its quality    assurance program. Maria, a leader in your organization’s quality assurance    program, informs you that she will be reviewing your project to determine    if your project management activities comply with the total quality    management program. This is an example of which one of the following?

    • A.

      A. Process analysis

    • B.

      B. Quality control mechanism

    • C.

      C. Enterprise environmental factors

    • D.

      D. Quality audit

    Correct Answer
    D. D. Quality audit
    Explanation
    D. This is an example of a quality audit to confirm that your project is adhering
    to the quality assurance program established within your organization. A and B
    are incorrect choices for this question. C, enterprise environmental factors, may
    be a valid characteristic of the total quality management program, but it is not
    the best answer for the question, which centers on the audit process rather than
    on how the audit will be performed.

    Rate this question:

  • 18. 

    18. In the illustration to the    right, what does the circled    area represent?The circle shows that the graphic point is OFF the chart.

    • A.

      A. Out-of-control data points

    • B.

      B. In-control data points

    • C.

      C. The Rule of Seven

    • D.

      D. Standard deviation

    Correct Answer
    A. A. Out-of-control data points
    Explanation
    A. The circled area shows
    out-of-control data points.
    B is incorrect, as “in-control
    data points” does not best
    answer the question. C is
    incorrect, as the Rule of
    Seven refers to seven consecutive measurements, all on one side of the mean.
    D is incorrect, since standard deviation is a predicted measure of the variance
    from the expected mean of a sampling.

    Rate this question:

  • 19. 

    19. You are the project manager for a plastics manufacturer. You would like to    illustrate the categories of quality failure within your project so that you and    your project team can attack the largest areas of failure first. This type of chart    is known as which one of the following?

    • A.

      A. A control chart

    • B.

      B. An Ishikawa diagram

    • C.

      C. A Pareto diagram

    • D.

      D. A flowchart

    Correct Answer
    C. C. A Pareto diagram
    Explanation
    C. You want to create a Pareto diagram. A is incorrect because a control chart
    does not identify the problems, only the relation of the results to the expected
    mean. B is incorrect because a cause-and-effect diagram does not map out the
    frequency of problems. D is also incorrect. Flowcharts show how a process
    moves through a system and how the components are related.

    Rate this question:

  • 20. 

    20. What is the type of chart to    the right called?This chart shows point from decrease to increase.

    • A.

      A. Pareto Diagram

    • B.

      B. A Control Chart

    • C.

      C. Fishbone diagram

    • D.

      D. Ishikawa diagram

    Correct Answer
    A. A. Pareto Diagram
    Explanation
    A. This is a Pareto diagram.
    B is incorrect, as a control
    chart shows the results
    of measurements over
    time. C and D are both
    incorrect, as a fishbone
    diagram and an Ishikawa
    diagram are essentially the
    same type of chart.

    Rate this question:

Quiz Review Timeline +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Jan 21, 2013
    Quiz Edited by
    ProProfs Editorial Team
  • Dec 11, 2010
    Quiz Created by
    Mat1952
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.