Project Time Management MCQs Quiz Questions And Answers

Reviewed by Editorial Team
The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Babjam
B
Babjam
Community Contributor
Quizzes Created: 14 | Total Attempts: 31,929
| Attempts: 8,135 | Questions: 20
Please wait...
Question 1 / 20
0 %
0/100
Score 0/100
1.
Project schedules grow out of the basic documents that initiate a project. State true or false. 

Explanation

Project schedules are developed based on the basic documents that initiate a project, such as the project charter or project plan. These documents provide the necessary information about the project's objectives, scope, deliverables, and timeline, which are essential for creating a project schedule. Therefore, the statement is true.

Submit
Please wait...
About This Quiz
Project Time Management MCQs Quiz Questions And Answers - Quiz

Hey there! Prepare yourself for this short and awesome practice test on project time management MCQs that consists of well-researched questions and answers. Time can pass by quickly... see moreif one does not have a plan on how to use it, and a project manager is expected to have a detailed plan on what they should do in a given duration to complete a project. Take this quiz and learn the secrets behind effective time management. Ready? Let's start then! see less

2. The WBS is often dissected further during the activity definition process as the project team members further define the activities required for performing the work.

Explanation

During the activity definition process, the project team members break down the Work Breakdown Structure (WBS) into smaller components or activities. This is done to further define and identify the specific tasks and actions needed to complete the project work. Therefore, the statement that the WBS is often dissected further during the activity definition process is true.

Submit
3. Schedule performance can be estimated by subtracting the original time estimate from how long it really took to complete the project.

Explanation

The statement is true because schedule performance can be evaluated by comparing the original time estimate with the actual time taken to complete the project. By subtracting the original time estimate from the actual time, we can determine if the project was completed ahead of schedule or behind schedule. This calculation helps in assessing the efficiency and accuracy of the initial time estimation and allows for adjustments to be made in future projects.

Submit
4. Most projects have one path through a network diagram.

Explanation

The statement is false because most projects have multiple paths through a network diagram. A network diagram represents the flow of activities and dependencies in a project, and it is common for projects to have multiple parallel paths or alternative paths based on different dependencies and constraints. This allows for flexibility and the ability to handle unexpected changes or delays in the project schedule. Therefore, it is incorrect to say that most projects have only one path through a network diagram.

Submit
5.
____ involves doing activities in parallel that you would normally do in sequence.

Explanation

Fast tracking involves doing activities in parallel that you would normally do in sequence. This technique is used to expedite the project schedule by overlapping activities that would typically be done one after the other. By fast tracking, the project timeline can be shortened, allowing for faster completion and potentially saving time and resources.

Submit
6.
____ is a network diagramming technique used to predict total project duration.

Explanation

Critical path analysis is a network diagramming technique used to predict the total project duration. It identifies the critical path, which is the sequence of activities that determines the shortest possible duration for the project. By analyzing the dependencies and durations of each activity, critical path analysis helps project managers identify the activities that have the most impact on the project timeline. This technique allows for better planning, resource allocation, and risk management, ultimately leading to successful project completion within the desired timeframe.

Submit
7. The outputs to schedule development include activity duration estimates and updates to activity attributes.

Explanation

The outputs to schedule development include activity duration estimates and updates to activity attributes. This means that when developing a schedule, one of the outcomes is obtaining estimates for how long each activity will take to complete. Additionally, the activity attributes may be updated during this process, possibly to reflect any changes or adjustments made to the schedule. Therefore, the statement is true.

Submit
8. It is not necessary to complete all of the activities on the network diagram in order for the project to finish.

Explanation

The statement is false because in order for the project to finish, all of the activities on the network diagram must be completed. The network diagram represents the sequence and dependencies of activities, and any incomplete activity will cause a delay in the project. Therefore, it is necessary to complete all of the activities for the project to finish successfully.

Submit
9.
____ dependencies involve relationships between project and non-project activities.

Explanation

External dependencies involve relationships between project and non-project activities. These dependencies are typically outside the control of the project team and may include factors such as dependencies on external organizations, government regulations, or market conditions. These dependencies can have a significant impact on the project schedule and may require coordination and collaboration with external stakeholders to ensure successful project completion.

Submit
10.
A(n) ____ is a hierarchical structure that identifies the project's resources by category and type.

Explanation

A resource breakdown structure is a hierarchical structure that categorizes and identifies the project's resources by their type. It helps in organizing and managing the project's resources more effectively by providing a clear overview of the different types of resources required. This structure allows for better resource allocation, tracking, and coordination throughout the project lifecycle.

Submit
11.
The critical path is the ____ path through a network diagram, and it represents the ____ time it takes to complete a project.

Explanation

The critical path is the longest path through a network diagram, as it includes all the activities that must be completed in order to finish the project. It represents the shortest time it takes to complete a project because any delay in activities on the critical path will directly impact the overall project timeline.

Submit
12. When using the PERT weighted average for each activity duration estimate, the total project duration estimate does not account for the risk or uncertainty in the individual activity estimates.

Explanation

The statement is false because the PERT weighted average does account for the risk or uncertainty in the individual activity estimates. The PERT method uses three estimates for each activity duration - the optimistic, most likely, and pessimistic estimates - and calculates a weighted average that takes into consideration the probability of each estimate occurring. This approach allows for a more accurate estimation of the project duration by considering the uncertainties and risks associated with each activity.

Submit
13. Duration only includes the actual amount of time worked on an activity

Explanation

The statement is false. Duration not only includes the actual amount of time worked on an activity, but it also includes any additional time spent on preparation, breaks, or interruptions. Therefore, the duration of an activity is the total time from start to finish, including all the necessary components and interruptions.

Submit
14.
____ is the amount of time an activity can be delayed from its early start without delaying the planned project finish date.

Explanation

Total slack refers to the amount of time that an activity can be delayed from its early start without delaying the planned project finish date. It represents the flexibility or buffer time available for an activity before it affects the overall project schedule. The total slack is calculated by subtracting the early start time from the late start time or the early finish time from the late finish time of an activity. It helps project managers in identifying the activities that have the most flexibility in terms of scheduling and allows them to prioritize resources and make adjustments to the project timeline accordingly.

Submit
15. The ultimate goal of ____ is to create a realistic project schedule that provides a basis for monitoring project progress for the time dimension of the project.

Explanation

Schedule development is the process of creating a realistic project schedule that serves as a foundation for monitoring project progress in terms of time. It involves analyzing the project's activities, their sequencing, and estimating their durations to determine the most efficient and effective schedule. This process ensures that the project is completed within the specified timeframe and allows for tracking and controlling the project's progress against the schedule.

Submit
16.
The goal of the activity ____ process is to ensure that the project team has complete understanding of all the work they must do as part of the project scope so they can start scheduling the work.

Explanation

The correct answer is "Definition". In the context of project management, the definition process refers to the activity of clearly defining and documenting the project scope, objectives, deliverables, and requirements. This process ensures that the project team has a complete understanding of all the work they need to do in order to successfully complete the project. Once the definition process is complete, the team can then start scheduling the work and allocating resources accordingly.

Submit
17. The critical path always includes the most critical activities.

Explanation

The statement is false because the critical path includes the sequence of activities that have the longest total duration in a project. These activities are crucial for the project's timeline and any delay in them will directly impact the project's completion date. However, not all critical activities are necessarily the most critical. There may be other activities that are important but have shorter durations and are not part of the critical path.

Submit
18. The ____ provide(s) schedule-related information about each activity, such as predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions related to the activity.

Explanation

Activity attributes provide schedule-related information about each activity, such as predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions. These attributes are essential for planning and sequencing activities in a project schedule. They help in understanding the dependencies and relationships between different activities and assist in creating an accurate and realistic project schedule.

Submit
19. Project managers often illustrate progress with a(n) ____ showing key deliverables and activities

Explanation

A tracking Gantt chart is a visual tool used by project managers to illustrate the progress of a project. It shows key deliverables and activities, allowing the project manager to track the status of each task and identify any potential delays or issues. The tracking Gantt chart provides a clear overview of the project timeline and helps the project manager effectively manage resources and make informed decisions. It is an essential tool for monitoring and controlling the project's progress.

Submit
20. The main outputs of activity resource estimating include a project schedule network diagram, requested changes, and updates to the activity list and attributes.

Explanation

The main outputs of activity resource estimating do not include a project schedule network diagram, requested changes, and updates to the activity list and attributes. This statement is false.

Submit
View My Results

Quiz Review Timeline (Updated): Aug 20, 2023 +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Aug 20, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Dec 11, 2010
    Quiz Created by
    Babjam
Cancel
  • All
    All (20)
  • Unanswered
    Unanswered ()
  • Answered
    Answered ()
Project schedules grow out of the basic documents that initiate a...
The WBS is often dissected further during the ...
Schedule performance can be estimated by ...
Most projects have one path through a network diagram.
____ involves doing activities in parallel that you would ...
____ is a network diagramming technique used to predict ...
The outputs to schedule development include ...
It is not necessary to complete all of the ...
____ dependencies involve relationships between project ...
A(n) ____ is a hierarchical structure that identifies the ...
The critical path is the ____ path through a network ...
When using the PERT weighted average for each ...
Duration only includes the actual amount of time ...
____ is the amount of time an activity can be delayed from ...
The ultimate goal of ____ is to create a ...
The goal of the activity ____ process is to ensure that ...
The critical path always includes the most critical activities.
The ____ provide(s) schedule-related information ...
Project managers often illustrate progress with ...
The main outputs of activity resource estimating ...
Alert!

Advertisement