Important Questions On Project Time Management!

Reviewed by Editorial Team
The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Marchesl
M
Marchesl
Community Contributor
Quizzes Created: 6 | Total Attempts: 5,191
| Attempts: 478 | Questions: 10
Please wait...
Question 1 / 10
0 %
0/100
Score 0/100
1. Sequence Activities is the process of identifying and documenting relationships among the project activities. True or false?

Explanation

Sequence Activities is indeed the process of identifying and documenting relationships among project activities. This process involves determining the logical order in which activities should be performed to achieve project objectives. By establishing these relationships, project managers can create a project schedule that ensures activities are executed in the right sequence, minimizing delays and optimizing resource utilization. Therefore, the correct answer is true.

Submit
Please wait...
About This Quiz
Important Questions On Project Time Management! - Quiz

Are you looking for some important questions on project time management? There are a lot of activities that are undertaken when it comes to accomplishing a project, and... see morehaving a time set where each activity is to be finished has the power not only to increase productivity but effectiveness too. Take the questions below and get to see what more you may learn about ability. see less

2. Calculate the Activity Duration for a project with a work quantity of 450 computers and a production rate of 50 computers/day.

Explanation

The activity duration for the project can be calculated by dividing the work quantity (450 computers) by the production rate (50 computers/day). This will give us the number of days required to complete the work. In this case, 450 divided by 50 equals 9, so the activity duration is 9 days.

Submit
3. If start and finish dates are not realistic, project will most likely not finish as scheduled. Sure or false?

Explanation

If the start and finish dates of a project are not realistic, it means that the project is not properly planned and scheduled. This lack of realistic timeframes can lead to delays, resource constraints, and other issues that can prevent the project from finishing as scheduled. Therefore, it is likely that the project will not be completed on time if the start and finish dates are not realistic.

Submit
4. This is an example of a Critical _____ Diagram.

Explanation

This is an example of a Critical Path Diagram. A critical path diagram is a project management tool that shows the sequence of activities and the estimated duration of each activity. It helps identify the critical path, which is the longest sequence of activities that determines the project's overall duration. By analyzing the critical path, project managers can identify potential bottlenecks and prioritize activities to ensure the project is completed on time.

Submit
5. Which relationship type matches the following definition: "The successor can't start before the predecessor has started."

Explanation

The relationship type that matches the given definition is "Start to Start." This means that the successor activity cannot start until the predecessor activity has started. In other words, both activities must start at the same time or have a delay between their starts. This relationship ensures that the successor activity is dependent on the start of the predecessor activity.

Submit
6. Which of the following is NOT a component of Develop Schedule?

Explanation

Expert judgement is not a component of Develop Schedule because it is a technique used in various project management processes, including Develop Schedule, to gather input and insights from experts in order to make informed decisions. However, it is not a specific component or output of the Develop Schedule process itself. The other options listed (activity list, schedule network analysis, and project schedule) are all components of the Develop Schedule process, as they are directly involved in creating and finalizing the project schedule.

Submit
7. Match the corresponding Process with its place in the overall Project Time Management Process diagram.
Submit
8. Define _____: Identifying and documenting the actions to be performed to produce the deliverables.

Explanation

not-available-via-ai

Submit
9. Project Time Management defines how schedule contingencies will be reported and assessed.

Explanation

Project Time Management does not specifically define how schedule contingencies will be reported and assessed. It focuses on activities such as defining activities, sequencing them, estimating their durations, and developing a schedule. Reporting and assessing schedule contingencies fall under the domain of Project Risk Management. Therefore, the correct answer is False.

Submit
10. Check the options which are Tools & Techniques found in Estimate Activity Resources.

Explanation

The tools and techniques found in Estimate Activity Resources include expert judgement, alternative analysis, PM software, bottom-up estimating, and published estimated data. Expert judgement refers to the input and insights provided by individuals with specialized knowledge and experience in the field. Alternative analysis involves evaluating different options and approaches to estimate activity resources. PM software is used to assist in the estimation process. Bottom-up estimating involves breaking down the work into smaller components and estimating the resources required for each component. Published estimated data refers to industry-specific data or historical records that can be used as a reference for estimating resources.

Submit
View My Results

Quiz Review Timeline (Updated): Nov 16, 2023 +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Nov 16, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Dec 28, 2017
    Quiz Created by
    Marchesl
Cancel
  • All
    All (10)
  • Unanswered
    Unanswered ()
  • Answered
    Answered ()
Sequence Activities is the process of identifying and documenting...
Calculate the Activity Duration for a project with a work quantity of...
If start and finish dates are not realistic, project will most likely...
This is an example of a Critical _____ Diagram.
Which relationship type matches the following definition: "The...
Which of the following is NOT a component of Develop Schedule?
Match the corresponding Process with its place in the overall Project...
Define _____: Identifying and documenting the actions to be performed...
Project Time Management defines how schedule contingencies will be...
Check the options which are Tools & Techniques found in Estimate...
Alert!

Advertisement