Quiz: Important Questions On Project Time Management!

10 Questions | Total Attempts: 125

SettingsSettingsSettings
Please wait...
Quiz: Important Questions On Project Time Management!

Are you looking for some important questions on project time management? There are a lot of activities that are undertaken when it comes to accomplishing a project, and having a time set where each activity is to be finished has the power not only to increase productivity but effectiveness too. Take the questions below and get to see what more you may learn about ability.


Questions and Answers
  • 1. 
    Project Time Management defines how schedule contingencies will be reported and assessed.
    • A. 

      True

    • B. 

      False

  • 2. 
    Which relationship type matches the following definition: "The successor can't start before the predecessor has started."
    • A. 

      Finish to Start

    • B. 

      Start to Start

    • C. 

      Finish to Finish

    • D. 

      Start to Finish

  • 3. 
    Define [Blank]: Identifying and documenting the actions to be performed to produce the deliverables.
  • 4. 
    Which of the following is NOT a component of Develop Schedule?
    • A. 

      Activity list

    • B. 

      Schedule network analysis

    • C. 

      Project schedule

    • D. 

      Expert judgement

  • 5. 
    If start and finish dates are not realistic, project will most likely not finish as scheduled. Sure or false?
    • A. 

      True

    • B. 

      False

  • 6. 
    This is an example of a Critical [Blank] Diagram.
  • 7. 
    Calculate the Activity Duration for a project with a work quantity of 450 computers and a production rate of 50 computers/day.
    • A. 

      10 days

    • B. 

      5 days

    • C. 

      2 days

    • D. 

      9 days

  • 8. 
    Sequence Activities is the process of identifying and documenting relationships among the project activities. True or false?
    • A. 

      True

    • B. 

      False

  • 9. 
    Check the options which are Tools & Techniques found in Estimate Activity Resources.
    • A. 

      Expert judgement

    • B. 

      Alternative analysis

    • C. 

      Activity resource requirements

    • D. 

      EEF's

    • E. 

      PM Software

    • F. 

      OPA's

    • G. 

      Bottom-up estimating

    • H. 

      Published estimated data