The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Ahunter400
A
Ahunter400
Community Contributor
Quizzes Created: 3 | Total Attempts: 1,628
| Attempts: 342 | Questions: 15
Please wait...
Question 1 / 15
0 %
0/100
Score 0/100
1. The General Services Administration offers two on-line shoppping services.  One of these services is called ___________

Explanation

[source FAR 8.402(c)(1)]

Submit
Please wait...
About This Quiz
Far Parts 6 - 9 - Quiz

The questions in this quiz cover FAR Parts 6 - 9 and follow the material presented in the NCMA CFCM Study Guide.

2. A responsible contractor must be considered all of the below, except

Explanation

[source FAR 9.104-1(c)]

Submit
3. FAR 6.3 provides 7 exceptions for contracting without providing for full and open competition.  Which of the below is not one of those 7 exceptions?

Explanation

[source FAR 6.3]

Submit
4. The use of Sealed Bidding is appropriate when 4 criteria are met.  Which of the below is not one of those criteria?

Explanation

[source FAR 6.401(a)]

Submit
5. Competition advocates are responsible for

Explanation

[source FAR 6.502(a)]

Submit
6. The FAR provides that the purpose of acquisition planning is to ensure that the Government meets its needs

Explanation

[source FAR 7.102(b)]

Submit
7. The contracting officer shall develop special standards of responsibiliy when it is necessary for a particular acquisition or class of actions.  These special standards shall be set forth in:

Explanation

[source FAR 9.104-2]

Submit
8. FAR 9.103(a) provides that "purchases shall be made from, and contracts shall be awarded to, responsible propsective contractors only".  In order to be determined responsible, a prospective contractor is not required to have _________ .

Explanation

[source FAR 9.104-1]

Submit
9. Generally, ___________________ are responsible for determining the responsiblity of their prospective cubcontractors.

Explanation

[source FAR 9.104-4(a)]

Submit
10. Which of the below are not considered an AbilityOne participating nonprofit agency?

Explanation

[source FAR 8.701]

Submit
11. As used in subpart 7.1, "life-cycle cost" means the

Explanation

[source FAR 7.101]

Submit
12. FAR 8.704(a) provides that the Javits-Wagner-O'Day Act requires the Government to purchase supplies or services on the Procurement List....from AbilityOne participating nonprofit agencies if they are available within the period required.  When identicial supplies are on the Procurement List and the Schedule of Products issued by the Federal Prision Industries, Inc., the following entity whall have first priority:

Explanation

[source FAR 8.704(a)(1)]

Submit
13. FAR 8.704(a) provides that the Javits-Wagner-O'Day Act requires the Government to purchase supplies or services on the Procurement List....from AbilityOne participating nonprofit agencies if they are available within the period required.  When identicial services are on the Procurement List and the Schedule of Products issued by the Federal Prision Industries, Inc., the following entity whall have first priority:

Explanation

[source FAR 8.704(a)(2)]

Submit
14. Agencies may exclude a particular source from a contract action in order to establish or maintain an alternative source or sources for supplies or services being acquired if the agency head determines that doing so would do any of the following except:

Explanation

[source FAR 6.202]

Submit
15. The competitive procedures available for use in fulfilling the requirement for full and open competition do no include

Explanation

[source FAR 6.102]

Submit
View My Results

Quiz Review Timeline (Updated): Mar 19, 2023 +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 19, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Jun 02, 2011
    Quiz Created by
    Ahunter400
Cancel
  • All
    All (15)
  • Unanswered
    Unanswered ()
  • Answered
    Answered ()
The General Services Administration offers two on-line shoppping...
A responsible contractor must be considered all of the below, except
FAR 6.3 provides 7 exceptions for contracting without providing for...
The use of Sealed Bidding is appropriate when 4 criteria are...
Competition advocates are responsible for
The FAR provides that the purpose of acquisition planning is to ensure...
The contracting officer shall develop special standards of...
FAR 9.103(a) provides that "purchases shall be made from, and...
Generally, ___________________ are responsible for determining the...
Which of the below are not considered an AbilityOne participating...
As used in subpart 7.1, "life-cycle cost" means the
FAR 8.704(a) provides that the Javits-Wagner-O'Day Act requires...
FAR 8.704(a) provides that the Javits-Wagner-O'Day Act requires...
Agencies may exclude a particular source from a contract action in...
The competitive procedures available for use in fulfilling the...