6c051 - Volume 4

Reviewed by Editorial Team
The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Leishman
L
Leishman
Community Contributor
Quizzes Created: 1 | Total Attempts: 707
| Attempts: 707 | Questions: 80
Please wait...
Question 1 / 80
0 %
0/100
Score 0/100
1. Which Web-based system provides for electronic invoicing, receipt, and acceptance?

Explanation

Wide Area Workflow (WAWF) is the correct answer because it is a web-based system that allows for electronic invoicing, receipt, and acceptance. It is used by the Department of Defense and other federal agencies to streamline the procurement process and facilitate electronic transactions between vendors and the government. WAWF helps to automate the submission, processing, and acceptance of invoices, making it an efficient and convenient system for managing financial transactions.

Submit
Please wait...
About This Quiz
6c051 - Volume 4 - Quiz

Having a good contractor in the air force ensures that any contract prepared or entered into is beneficial to them. The contractor and prepares and negotiates bids. Are... see moreyou well qualified for that job as a contractor in the air force? Take the quiz below and let the results show you. see less

2. What term is defined in the Air Force Federal Acquisition Regulation Supplement (AFFARS) as an emergency involving military forces caused by natural disasters, terrorists, subversives, or required military operations?

Explanation

Contingency is the term defined in the Air Force Federal Acquisition Regulation Supplement (AFFARS) as an emergency involving military forces caused by natural disasters, terrorists, subversives, or required military operations.

Submit
3. If a contractor's failure to perform is due to actions of a subcontractor, will the contractor remain liable for excess costs of repurchase?

Explanation

If a contractor's failure to perform is due to actions of a subcontractor, the contractor will remain liable for excess costs of repurchase if supplies or services were available from other sources and sufficient time remained for the contractor to meet the required delivery schedule. In this scenario, the contractor had the opportunity to mitigate the failure by obtaining the necessary supplies or services from alternative sources within the given timeframe. Therefore, the contractor cannot avoid liability for the excess costs incurred due to the subcontractor's actions.

Submit
4. A cure notice is issued when

Explanation

A cure notice is issued when there is a specific condition that endangers contract performance. This means that there is a situation or circumstance that poses a risk or threat to the successful execution of the contract. The cure notice serves as a formal notification to the contractor, informing them of the issue and giving them an opportunity to rectify the situation and ensure that contract performance is not compromised.

Submit
5. Which has responsibility for the accuracy and the submission of individual contract action reports?

Explanation

The contracting officer has the responsibility for the accuracy and submission of individual contract action reports. They are responsible for ensuring that all contract actions are accurately documented and reported, including the submission of individual contract action reports. The contracting officer plays a crucial role in the contract management process and is accountable for maintaining the accuracy and completeness of contract records and reports.

Submit
6. Under the Contract Terms and Conditions–Commercial Items clause, the contractor is required to notify the contracting officer of an excusable delay

Explanation

The correct answer is "as soon as possible after commencement of an excusable delay" because under the Contract Terms and Conditions–Commercial Items clause, the contractor is required to notify the contracting officer of any excusable delay as soon as possible after it begins. This ensures that the contracting officer is promptly informed of any issues that may affect the scheduled delivery date.

Submit
7. Are you going to be ridiculousy releaved after you DESTROY this EOC test?

Explanation

The given statement suggests that the person will feel extremely relieved after destroying the EOC test. "Ridiculously relieved" implies a high level of relief, indicating that the person expects to perform exceptionally well on the test and feels confident about it. Therefore, the correct answer is True, as it aligns with the expectation of feeling relieved after successfully completing the test.

Submit
8. Ordinarily, what option is given to the contractor because of a notice of rejection for nonconformance?

Explanation

When a notice of rejection for nonconformance is given, the contractor is typically required to correct or replace any nonconforming supplies at no additional cost to the government. This means that the contractor must fix or replace the supplies that did not meet the required specifications without charging the government any extra fees. This ensures that the government receives the correct and conforming supplies without incurring any additional expenses.

Submit
9. The show cause notice

Explanation

The show cause notice is used to notify the contractor of the possibility of termination. This means that when a show cause notice is issued, it serves as a warning to the contractor that their contract may be terminated if they do not address the issues or concerns raised in the notice. It is a formal communication that alerts the contractor to the potential consequences they may face if they fail to rectify the situation.

Submit
10. Responsiveness to basic life support requirements (i.e. food services, potable water, etc.) is the main focus of what deployment phase?

Explanation

During the initial deployment phase, the main focus is on providing the basic life support requirements such as food services and potable water. This phase involves setting up the necessary infrastructure and resources to support the personnel and ensure their well-being. The goal is to establish a functional and sustainable environment for the deployed individuals. Once this phase is complete, the focus shifts to other aspects such as sustaining the operations and eventually terminating or redeploying the personnel.

Submit
11. To adhere to prompt payment guidelines, payment is due within how many days after government acceptance of supplies?

Explanation

According to the prompt payment guidelines, payment is due within 30 days after the government acceptance of supplies. This means that the government must make the payment within this timeframe to adhere to the guidelines.

Submit
12. Which system is used to report contract actions?

Explanation

FPDS-NG is the system used to report contract actions. It is a government-wide database that collects and provides access to information on federal procurement contracts. It is used to track and report on various contract actions such as awards, modifications, and terminations. This system helps to ensure transparency and accountability in the federal procurement process by providing a centralized platform for reporting and analyzing contract data.

Submit
13. Data transfer, storage, and retrieval procedures must record and reproduce the original document completely, accurately, and clearly. In addition, the procedures must

Explanation

The correct answer is "protect the original data from alteration". This is because data transfer, storage, and retrieval procedures should ensure that the original data remains unchanged and unaltered. This is important to maintain the integrity and authenticity of the data.

Submit
14. A contracting officer (CO) might use a post-award letter in lieu of a conference when

Explanation

A post-award letter may be used by a contracting officer (CO) instead of a conference when an incumbent contractor is awarded a new contract and the terms have not changed. This suggests that the CO may choose to communicate the necessary information and updates regarding the contract through a letter rather than conducting a conference. This could be because the contract terms remain the same and there is no need for a detailed discussion or clarification.

Submit
15. The contracting officer has grounds to terminate a contractor for default when

Explanation

When a contractor fails to meet their contractual obligations or shows a lack of progress in performing their duties, the contracting officer can terminate the contractor for default. This means that the contractor has not fulfilled their responsibilities as outlined in the contract, leading to a breach of agreement. This could include failing to meet deadlines, not delivering the required goods or services, or not meeting quality standards. The contracting officer has the right to terminate the contract and potentially seek legal action or find a replacement contractor.

Submit
16. Which contract action is not reportable?

Explanation

Purchases made at AbilityOne service stores are not reportable because AbilityOne is a federal program that provides employment opportunities for people who are blind or have significant disabilities. These purchases support the program's mission and are exempt from reporting requirements.

Submit
17. The contracting officer should exercise the government's right to terminate a contract for commercial items only when such a termination

Explanation

The correct answer is "would be in the best interest of the government." This means that the contracting officer should terminate a contract for commercial items only if it is determined that doing so would be beneficial for the government. This decision should be based on what is most advantageous for the government in terms of cost, performance, or other factors.

Submit
18. How would you close a contract if the contractor becomes bankrupt?

Explanation

If the contractor becomes bankrupt, it is necessary to coordinate with the Office of General Counsel to close the contract. This is because the Office of General Counsel is responsible for providing legal advice and guidance in matters related to contracts and legal issues. They will have the expertise and knowledge to handle the situation appropriately and ensure that all necessary steps are taken to properly close the contract in accordance with legal requirements.

Submit
19. Which task is not considered a key task in setting up a work center?

Explanation

Setting up a work center involves tasks that are directly related to the functioning and operation of the center. Obtaining an interpreter and making contact with the US Embassy are tasks that may be necessary depending on the specific requirements of the work center. Establishing a system for customers to submit purchase requests is also an important task as it ensures a smooth flow of communication and allows for efficient handling of purchase requests. However, establishing a cutoff date for end-of-year purchases is not directly related to the setup of a work center. It is more of a decision related to procurement and budgeting, which may be important for overall organizational planning but not specifically for setting up a work center.

Submit
20. Records of contractor performance are managed in the

Explanation

The correct answer is the Contractor Performance Assessment Reporting System (CPARS). This system is responsible for managing records of contractor performance. The other options mentioned, such as the Central Contractor Registration (CCR) database, Contractor Performance Evaluation System (CPES), and Federal Procurement Data System-Next Generation (FPDS-NG), are not specifically designed for managing contractor performance records.

Submit
21. What option does the government have if it fails to provide the necessary notifications required by the contract and still desires to exercise an option period?

Explanation

If the government fails to provide the necessary notifications required by the contract but still wants to exercise an option period, it can issue a bilateral modification and obtain contractor concurrence. This means that the government and the contractor will come to an agreement to modify the contract in order to exercise the option period, even though the necessary notifications were not provided. This allows both parties to continue the contract and fulfill their obligations.

Submit
22. Items that must be addressed in a preconstruction conference include all except

Explanation

A preconstruction conference is a meeting held before the start of a construction project to discuss various important aspects. During this meeting, the participants address various topics such as labor standards, contractual authority, accident prevention plans, and termination procedures. However, termination procedures are not typically discussed in a preconstruction conference. Therefore, termination procedures are the exception and do not need to be addressed in such a meeting.

Submit
23. What requires that all work under a construction contract be performed in a skillful manner?

Explanation

The Material and Workmanship clause requires that all work under a construction contract be performed in a skillful manner. This clause ensures that the materials used and the workmanship involved in the construction project meet the required standards and specifications. It holds the contractor responsible for delivering work that is of good quality and meets the expectations of the client.

Submit
24. A declared contingency may be designated by the

Explanation

The correct answer is the secretary of Defense. This is because the secretary of Defense has the authority to declare a contingency and designate it as such. The assistant secretary of the Air Force for Acquisition (Contracting) (SAF/AQC), Joint Theater Support Commander, and on-scene commander do not have the authority to declare a contingency.

Submit
25. When delivery is late on a commodities contract, the government may take any actions except

Explanation

When delivery is late on a commodities contract, the government has the option to take various actions. They can invoke liquidated damages in the agreed amount until delivery is made or the delivery schedule is renegotiated, but this is only applicable if liquidated damages are included in the contract. Another option is to extend the delivery date, but only if the government receives appropriate consideration for doing so. However, the correct answer is to terminate the contract for default in accordance with Part 12 of the Federal Acquisition Regulation (FAR). This means that if the delivery is significantly delayed, the government can choose to terminate the contract due to the supplier's default.

Submit
26. What document is used to guide discussions during a contract post-award conference?

Explanation

The correct answer is DD Form 1484, Post-Award Conference Record. This document is used to guide discussions during a contract post-award conference. It serves as a record of the conference, documenting important information such as the date, time, and location of the conference, as well as the attendees and topics discussed. It helps ensure that all parties involved have a clear understanding of the discussions and any decisions made during the conference.

Submit
27. What determines the appropriate certification level and training that contracting personnel should have prior to selection as a contingency contracting officer (CCO)?

Explanation

The appropriate certification level and training for contracting personnel prior to selection as a CCO is determined by the particular tasking. This means that the specific requirements and responsibilities of the role will dictate the level of certification and training needed. It is important for contracting personnel to have the necessary skills and knowledge to effectively carry out their duties in a contingency contracting environment.

Submit
28. What action must a contingency contracting officer (CCO) take to ensure the necessary resources are made available and appropriate policies are established to carry out contracting support at a deployed location?

Explanation

To ensure the necessary resources are made available and appropriate policies are established to carry out contracting support at a deployed location, a contingency contracting officer (CCO) must brief the deployed commander on support requirements and contract capabilities. This ensures that the commander is aware of the specific needs and capabilities related to contracting in the deployed location, allowing them to make informed decisions and allocate resources effectively.

Submit
29. Which individual has overall responsibility for overseeing the management of decentralized blanket purchase agreements (BPA)?

Explanation

The correct answer is the contracting officer. The contracting officer is responsible for overseeing the management of decentralized blanket purchase agreements (BPA). They are responsible for negotiating and awarding BPAs, as well as monitoring and evaluating their performance. The contracting officer ensures that the BPAs are in compliance with regulations and policies, and they have the authority to make decisions regarding the BPAs. The other options, such as ordering officers, deployed commander, and functional commander, do not have the same level of responsibility and authority as the contracting officer in managing BPAs.

Submit
30. When you are processing an administrative change, which is required?

Explanation

When processing an administrative change, it is necessary to check block 13B of the SF 30. This is important because block 13B contains information about the modification authority for the change. By checking this block, you can ensure that the change is being made in accordance with the appropriate authority and that all necessary steps are being taken.

Submit
31. The contracting officer shall issue a no-cost settlement instead of a termination notice when

Explanation

When the contracting officer knows that the contractor will accept a no-cost settlement, they will issue it instead of a termination notice. This suggests that the contractor and the contracting officer have already discussed and agreed upon the terms of the settlement, making it unnecessary to go through the termination process.

Submit
32. Who determines the priority of purchase requests in a contingency?

Explanation

The deployed commander is responsible for determining the priority of purchase requests in a contingency. As the commanding officer on the ground, they have the authority to assess the urgency and importance of each request and allocate resources accordingly. The deployed commander takes into account factors such as mission objectives, available resources, and the overall strategic situation to make informed decisions on the priority of purchase requests. This role is crucial in ensuring that the most critical needs are met in a contingency situation.

Submit
33. The authority to make changes to an existing contract is not extended to

Explanation

The correct answer is "qualified contracting officer representatives to make constructive changes to contracts." This means that the authority to make changes to an existing contract is given to qualified contracting officer representatives who can make constructive changes to the contracts. This authority is not extended to modifications executed by contracting officers in accordance with contract scope, contract changes made by a contracting officer at the request of the contractor, or modifications to contracts within the limitations specified on the contracting officer's warrant.

Submit
34. What amount of time is the contractor normally given to correct a failure

Explanation

The correct answer is "Ten days from the receipt of the cure notice." This means that the contractor has ten days to correct a failure starting from the day they receive the cure notice. The cure notice serves as a notification to the contractor that they have failed to meet the requirements of the contract and gives them a specified amount of time to rectify the issue. In this case, the contractor has ten days to address the failure once they have received the notice.

Submit
35. When delivery is late on a commodities contract, the government may take any of the actions except

Explanation

When delivery is late on a commodities contract, the government may take any of the actions mentioned, except for terminating the contract for default in accordance with Part 12 of the FAR. This means that the government cannot terminate the contract based on default according to Part 12 of the FAR. The other options, such as invoking liquidated damages, renegotiating the delivery schedule, or terminating the contract for default in accordance with Part 49 of the FAR, are still possible actions that the government can take in this situation.

Submit
36. What document is produced by contingency contracting officers (CCO) and contains information about special personnel requirements, host nation support, local customs, billeting arrangements, and other problems encountered in the contracting process at deployed locations?

Explanation

The correct answer is After-action report. An after-action report is produced by contingency contracting officers (CCO) and contains information about special personnel requirements, host nation support, local customs, billeting arrangements, and other problems encountered in the contracting process at deployed locations. This report is used to evaluate the effectiveness of the contracting process and identify areas for improvement in future operations.

Submit
37. Which statement regarding wage determinations is correct?

Explanation

Wage determinations must be incorporated at the time of award or by modification. This means that the wage rates and requirements specified in the wage determinations must be included in the contract either when it is initially awarded or through subsequent modifications. This ensures that the contract complies with the applicable wage standards and regulations.

Submit
38. When is the contractor's right to proceed further under the contract terminated?

Explanation

The contractor's right to proceed further under the contract is terminated upon receipt of the notice of termination. This means that once the contractor receives the notice stating that the contract has been terminated, they no longer have the right to continue with any further actions or work related to the contract. This could be due to various reasons such as a breach of contract or failure to meet the terms and conditions.

Submit
39. In-process inspection of commercial items by the government

Explanation

In-process inspection of commercial items by the government must be conducted in a manner consistent with commercial practice. This means that the government should follow the same inspection procedures and standards that are used by the commercial industry for similar items. This ensures that the inspection is fair and consistent, and that the government is not imposing additional requirements or burdens on the contractor beyond what is considered standard practice in the commercial sector.

Submit
40. Contract files using simplified acquisition procedures are considered closed when the contracting officer receives

Explanation

When contract files are closed using simplified acquisition procedures, it is necessary for the contracting officer to receive evidence of receipt of property and final payment. This means that the contractor must provide proof that the property has been received by the appropriate party, and that all payments have been made in full. This ensures that all obligations of the contract have been fulfilled and that the contract can be considered closed.

Submit
41. Who needs to be notified when a contract containing classified material is complete and ready to be closed?

Explanation

The Defense Security Service needs to be notified when a contract containing classified material is complete and ready to be closed. The Defense Security Service is responsible for ensuring the protection of classified information and ensuring that proper security measures are in place. They need to be informed so that they can properly handle and dispose of any classified material in accordance with security protocols.

Submit
42. When connectivity issues prevent the reporting of contract actions during a contingency, what action must a contingency contracting officer (CCO) take?

Explanation

When connectivity issues prevent the reporting of contract actions during a contingency, the contingency contracting officer (CCO) must take the action of reporting the actions upon redeployment. This means that once the connectivity issues are resolved and the CCO is able to access the necessary reporting systems, they should submit the reports for the contract actions that were unable to be reported during the contingency period. This ensures that the necessary documentation and reporting requirements are fulfilled.

Submit
43. Unless otherwise specified, the government typically must provide how many days notice of its intent to exercise an option period?

Explanation

The government typically must provide 60 days notice of its intent to exercise an option period. This means that if the government wants to extend a contract or exercise an option to continue a contract, they must notify the other party at least 60 days in advance. This allows the other party to prepare and make any necessary arrangements for the extended period of the contract.

Submit
44. When supplies or services are still required after termination for default, the contracting officer should

Explanation

When supplies or services are still required after termination for default, the contracting officer should repurchase the same or similar supplies or services against the contractor's account as soon as possible. This means that instead of issuing a new contract, the contracting officer will use the contractor's existing account to make the repurchase. This ensures that the required supplies or services are obtained promptly and efficiently.

Submit
45. The retention period for contracts at or below the simplified acquisition threshold (SAT) is

Explanation

The correct answer is three years after final payment. This means that contracts at or below the simplified acquisition threshold (SAT) should be retained for a period of three years after the final payment has been made. This retention period allows for the necessary documentation to be kept for a reasonable amount of time for auditing and record-keeping purposes.

Submit
46. Which action must be taken prior to providing a contractor with preliminary notice of the government's intent to exercise an option?

Explanation

Prior to providing a contractor with preliminary notice of the government's intent to exercise an option, it is necessary to validate the requirement. This means ensuring that the need for the option has been properly assessed and confirmed, and that it aligns with the project or contract objectives. By validating the requirement, the government can ensure that exercising the option is necessary and appropriate. This step helps to avoid unnecessary costs or complications that may arise from exercising an option that is not truly needed.

Submit
47. When bonds are required on a construction contract, the contractor's notice to proceed is issued after the

Explanation

The correct answer is "contracting officer has received all executed bonds". This means that the contracting officer has received all the necessary paperwork and documentation regarding the bonds required for the construction contract. This ensures that the contractor has fulfilled their obligation to secure the bonds before proceeding with the project. The notice to proceed is then issued to allow the contractor to begin work on the project.

Submit
48. Blanket purchase agreement ordering officer responsibilities include all except

Explanation

The responsibilities of a blanket purchase agreement ordering officer include competing purchases, maintaining ethical standards of conduct, and ensuring orders are placed for only those items on the approved price list. However, delegating authority to authorized users within their unit is not one of their responsibilities.

Submit
49. When termination is for the government's convenience, what may a contractor use to demonstrate charges resulting from the termination for which the contractor is entitled to be paid?

Explanation

Contractors may use records from their standard record keeping system to demonstrate charges resulting from a termination for the government's convenience. These records would provide evidence of the expenses and costs incurred by the contractor during the termination process, which they are entitled to be paid for. This could include documentation such as receipts, invoices, financial statements, and any other relevant records kept by the contractor.

Submit
50. Follow-up in simplified acquisitions is

Explanation

Follow-up in simplified acquisitions is typically done by exception. This means that it is not a mandatory requirement, but rather a discretionary action taken when necessary. It allows for flexibility in the acquisition process and is often used to address specific issues or concerns that arise during the acquisition process.

Submit
51. What document is typically used to initially fund a contingency operation?

Explanation

The AF IMT 616, Fund Cite Authorization, is typically used to initially fund a contingency operation. This document is used to authorize the allocation of funds for specific purposes, such as purchasing goods or services. It ensures that the necessary funds are available and properly allocated before any expenditures are made.

Submit
52. Which member of a US Embassy essentially operates a contracting office in the host nation and can provide information on local purchasing conditions?

Explanation

A Government Services Officer is a member of a US Embassy who operates a contracting office in the host nation. They are responsible for providing information on local purchasing conditions, making them the correct answer to the question.

Submit
53. What modification authority must be used when no specific clause can be cited?

Explanation

When no specific clause can be cited, the modification authority that must be used is the "Mutual Agreement of the Parties." This means that both parties involved in the agreement need to mutually agree on the modifications that need to be made, without relying on any specific clause or regulation. This allows for flexibility and customization in modifying the agreement to meet the specific needs and circumstances of the parties involved.

Submit
54. When you are processing administrative changes, all may be processed as administrative changes except

Explanation

When processing administrative changes, all types of changes can typically be processed except for correcting errors in unit price. This suggests that errors in unit price require a different process or procedure to correct, separate from the general administrative changes.

Submit
55. Which labor standards provisions require all laborers and mechanics employed or working upon the site of construction to be paid unconditionally and not less often than once a week?

Explanation

The Davis-Bacon Act requires all laborers and mechanics employed or working on a construction site to be paid unconditionally and not less often than once a week. This act ensures that workers are paid fairly and in a timely manner for their work on federally funded construction projects.

Submit
56. What type of labor interview is used after detecting errors in labor checks or receipt of a complaint alleging violations?

Explanation

A special compliance check is used after detecting errors in labor checks or receiving a complaint alleging violations. This type of labor interview is conducted to ensure that the organization is in compliance with labor laws and regulations. It involves a thorough examination of the labor practices and policies to identify any potential violations and take appropriate corrective actions. The purpose of this interview is to address specific concerns or issues raised and ensure that the organization is following all necessary labor regulations.

Submit
57. Which termination consideration is not considered when determining whether to terminate a contract for default?

Explanation

The value of contractor assets is not considered when determining whether to terminate a contract for default. This means that the decision to terminate the contract is not based on the financial worth or assets of the contractor. Other factors, such as specific excuses for the failure, urgency of the need for the supplies, and the ability of the contractor to liquidate guaranteed loans, may be taken into consideration.

Submit
58. Which labor standards provisions require the contractor to submit weekly copies of all payrolls to the contracting officer and maintain payroll and basic records for a period of three years?

Explanation

The correct answer is Payrolls and Basic Records. This provision requires the contractor to submit weekly copies of all payrolls to the contracting officer and maintain payroll and basic records for a period of three years. This ensures transparency and accountability in terms of wages and labor standards compliance.

Submit
59. Acceptance of noncomplex commercial items is prescribed in

Explanation

not-available-via-ai

Submit
60. All are corrective actions that may be taken by the contracting officer (CO) if a contractor falls behind the approved schedule except

Explanation

The correct answer is "retain a maximum of 20 percent of the amount of a progress payment." This option is not a corrective action that may be taken by the contracting officer if a contractor falls behind the approved schedule. The other options, such as direct acceleration of work, requesting voluntary acceleration, and excusing delays beyond the contractor's control, are all possible actions that the contracting officer may take in such a situation.

Submit
61. In a commodity contract that has a Variations in Quantity clause, the variations that are allowed by the government are those

Explanation

The correct answer is "caused by loading, shipping, packing, or allowances within manufacturing processes." This means that the government allows for variations in quantity in the commodity contract as long as they are caused by factors such as loading, shipping, packing, or allowances within the manufacturing processes. These variations are considered acceptable and beyond the reasonable control of the contractor.

Submit
62. What modification authority must be cited when making administrative changes to a contract using the SF 30?

Explanation

When making administrative changes to a contract using the SF 30, no further authority needs to be cited. This means that there is no specific modification authority that needs to be referenced for these types of changes. The SF 30 form itself serves as the authority for making administrative changes to the contract.

Submit
63. Changes authorized in fixed-price contracts for supplies include all except

Explanation

In fixed-price contracts for supplies, changes that are authorized typically include modifications to the place of delivery, methods of shipment or packing, and drawings, designs, or specifications. However, directed acceleration in performance of work is not typically authorized as a change in fixed-price contracts for supplies.

Submit
64. A contractor has notified the contracting officer of the intent not to accept a unilateral purchase order. In this situation, the contracting officer must

Explanation

When a contractor notifies the contracting officer of their intent not to accept a unilateral purchase order, the contracting officer must proceed with cancellation of the order. This means that the purchase order will be revoked and no longer valid. It indicates that the contractor has refused to accept the terms and conditions of the purchase order, and therefore, the contracting officer must take the necessary steps to cancel it.

Submit
65. The DD Form 1597, Contract Closeout Checklist, is used when closing out

Explanation

The correct answer is "contracts valued above the simplified acquisition threshold (SAT)". This is because the DD Form 1597, Contract Closeout Checklist, is specifically used when closing out contracts that are above the simplified acquisition threshold. It is not used for contracts below this threshold or for cost-type contracts exceeding the SAT. Therefore, the correct answer is contracts valued above the simplified acquisition threshold (SAT).

Submit
66. Which is not required to be accomplished by the contracting officer (CO) to exercise an option?

Explanation

To exercise an option, the contracting officer (CO) is not required to obtain representations and certifications. Representations and certifications are typically obtained during the initial contract award process, and they do not need to be re-obtained when exercising an option. The other options listed, such as ensuring funds are available, satisfying competition requirements, and checking the Excluded Parties List System, are all necessary steps that the CO must take before exercising an option.

Submit
67. A change order

Explanation

A change order may be issued unilaterally means that it can be implemented without the consent or agreement of the contractor. This implies that the party responsible for initiating the change order has the authority to do so without requiring the contractor's approval. This flexibility allows for adjustments or modifications to be made to the original contract without causing delays or disruptions in the project.

Submit
68. Acceptance may not take place

Explanation

Acceptance refers to the act of the buyer formally accepting the goods or services provided by the seller. In this context, the most logical time for acceptance to take place is after payment is made. This is because payment is typically the final step in a transaction, indicating that the buyer is satisfied with the goods or services and is willing to accept them. Therefore, it is reasonable to expect acceptance to occur after payment is made.

Submit
69. All are examples of existing authorities that may be used to provide flexibility in expediting requirements for contingency except

Explanation

The question is asking for an example that is not an existing authority that can be used to provide flexibility in expediting requirements for contingency. The correct answer, "using written solicitations for Requests for Proposal (RFP)", is not an existing authority because written solicitations for RFPs are a standard and common practice in the procurement process. The other options listed, such as increasing the simplified acquisition threshold, awarding letter contracts, and awarding contracts for emergency requirements before resolving a protest, are all examples of existing authorities that can be used to expedite requirements for contingency.

Submit
70. Unless otherwise specified in the contract, Federal Acquisition Regulation (FAR) clause 52.212–4, Contract Terms and Conditions—Commercial Items, states that risk of loss or damage to supplies remains with the contractor until the supplies are

Explanation

The correct answer is "delivered to a carrier, if transportation is free of board (FOB)". This is because the FAR clause 52.212-4 states that when the transportation is free of board (FOB), the risk of loss or damage to the supplies remains with the contractor until the supplies are delivered to a carrier. This means that the contractor is responsible for any loss or damage that may occur during transportation until it is delivered to the carrier.

Submit
71. Which types of copies of contractual instruments can become part of the official contract file?

Explanation

Original, authenticated copies or conformed copies can become part of the official contract file. This means that the original document, as well as copies that have been verified and confirmed to be true and accurate, can be included in the official contract file. Registered copies and certified copies are not mentioned as options, so they are not considered part of the official contract file.

Submit
72. A modification in which all adjustments regarding cost, time, scope, and other consideration have been decided and required no further modification to complete contract change is known as

Explanation

A definitized modification refers to a modification in a contract where all adjustments related to cost, time, scope, and other considerations have been finalized and no further changes are required to complete the contract change. This means that all the necessary details and requirements for the modification have been decided and agreed upon, making it a definitive and conclusive change to the contract.

Submit
73. What actions will the contracting officer take if the contractor fails to respond to a show cause notice?

Explanation

If the contractor fails to respond to a show cause notice, the contracting officer will proceed under the assumption that there is no valid explanation for the contractor's actions. This means that the contracting officer will continue with whatever actions or consequences were outlined in the show cause notice, such as termination for the convenience of the government or issuing a cure notice with an additional 10 days to rectify the failure.

Submit
74. A notice for termination can be rescinded if it is determined that the items had been completed or shipped before the contractor's receipt of notice by

Explanation

If it is determined that the items had been completed or shipped before the contractor's receipt of notice, the notice for termination can be rescinded by amending the notice. This means that the original notice is modified or changed to reflect the new information that the items were already completed or shipped. By amending the notice, the termination can be reversed and the contractor can continue their work.

Submit
75. What type of organizational structure requires contingency contracting officers (CCOs) augmenting the organization to follow another service's Defense Federal Acquisition Regulation Supplement (DFAS) when acquiring goods and services?

Explanation

The Lead Service Theater Contracting Organization is the type of organizational structure that requires contingency contracting officers (CCOs) to follow another service's Defense Federal Acquisition Regulation Supplement (DFAS) when acquiring goods and services. This structure is responsible for coordinating and overseeing contracting activities in a specific theater of operations, and the CCOs play a crucial role in ensuring compliance with DFAS guidelines.

Submit
76. Unilateral modifications may be used for all except

Explanation

Unilateral modifications refer to changes made by one party without the consent or agreement of the other party. They are typically used for various purposes such as issuing change orders, termination notices, and making administrative changes. However, making changes authorized by the Changes clause does not fall under unilateral modifications. The Changes clause allows both parties to negotiate and agree upon changes to the contract, rather than one party making changes without the other's consent. Therefore, making changes authorized by the Changes clause is not a unilateral modification.

Submit
77. How can a termination for convenience of a fixed-price contract be settled?

Explanation

A termination for convenience of a fixed-price contract can be settled using either the inventory basis or the total-cost basis. The inventory basis refers to settling based on the value of the inventory that has been delivered or produced up until the termination date. The total-cost basis, on the other hand, involves settling based on the total costs incurred by the contractor up until the termination date, including both direct and indirect costs. Both methods provide options for determining the appropriate settlement amount in a termination for convenience situation.

Submit
78. After execution by all parties, copies of contracts or modifications must be distributed within

Explanation

After execution by all parties, copies of contracts or modifications must be distributed within 10 days. This means that once all parties involved in the contract have signed it, they have a maximum of 10 days to distribute copies of the contract or any modifications to all relevant parties. This ensures that everyone involved has access to the same information and can refer to the contract if needed.

Submit
79. A new wage determination must be incorporated into service contracts

Explanation

When extending a contract pursuant to an option clause, a new wage determination must be incorporated into service contracts. This means that when the contract is being extended, a new determination of wages must be included in the contract. This ensures that the wages being paid to the workers are appropriate and in accordance with any changes or updates that may have occurred since the initial contract was signed.

Submit
80. When the government takes possession prior to completion of construction, and without final acceptance, the one-year warranty period begins

Explanation

The correct answer is when final acceptance occurs. This means that the one-year warranty period starts when the government officially accepts the completed construction project. This is the point at which the government acknowledges that the work has been done satisfactorily and meets all the required specifications. The other options, such as the date after final payment is made or when the government takes possession, are not necessarily indicative of the completion and acceptance of the project.

Submit
View My Results

Quiz Review Timeline (Updated): Mar 21, 2023 +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 21, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Jun 27, 2013
    Quiz Created by
    Leishman
Cancel
  • All
    All (80)
  • Unanswered
    Unanswered ()
  • Answered
    Answered ()
Which Web-based system provides for electronic invoicing, receipt, and...
What term is defined in the Air Force Federal Acquisition Regulation...
If a contractor's failure to perform is due to actions of a...
A cure notice is issued when
Which has responsibility for the accuracy and the submission of...
Under the Contract Terms and Conditions–Commercial Items clause,...
Are you going to be ridiculousy releaved after you DESTROY this EOC...
Ordinarily, what option is given to the contractor because of a notice...
The show cause notice
Responsiveness to basic life support requirements (i.e. food services,...
To adhere to prompt payment guidelines, payment is due within how many...
Which system is used to report contract actions?
Data transfer, storage, and retrieval procedures must record and...
A contracting officer (CO) might use a post-award letter in lieu of a...
The contracting officer has grounds to terminate a contractor for...
Which contract action is not reportable?
The contracting officer should exercise the government's right to...
How would you close a contract if the contractor becomes bankrupt?
Which task is not considered a key task in setting up a work center?
Records of contractor performance are managed in the
What option does the government have if it fails to provide the...
Items that must be addressed in a preconstruction conference include...
What requires that all work under a construction contract be performed...
A declared contingency may be designated by the
When delivery is late on a commodities contract, the government may...
What document is used to guide discussions during a contract...
What determines the appropriate certification level and training that...
What action must a contingency contracting officer (CCO) take to...
Which individual has overall responsibility for overseeing the...
When you are processing an administrative change, which is required?
The contracting officer shall issue a no-cost settlement instead of a...
Who determines the priority of purchase requests in a contingency?
The authority to make changes to an existing contract is not extended...
What amount of time is the contractor normally given to correct a...
When delivery is late on a commodities contract, the government may...
What document is produced by contingency contracting officers (CCO)...
Which statement regarding wage determinations is correct?
When is the contractor's right to proceed further under the contract...
In-process inspection of commercial items by the government
Contract files using simplified acquisition procedures are considered...
Who needs to be notified when a contract containing classified...
When connectivity issues prevent the reporting of contract actions...
Unless otherwise specified, the government typically must provide how...
When supplies or services are still required after termination for...
The retention period for contracts at or below the simplified...
Which action must be taken prior to providing a contractor with...
When bonds are required on a construction contract, the contractor's...
Blanket purchase agreement ordering officer responsibilities include...
When termination is for the government's convenience, what may a...
Follow-up in simplified acquisitions is
What document is typically used to initially fund a contingency...
Which member of a US Embassy essentially operates a contracting office...
What modification authority must be used when no specific clause can...
When you are processing administrative changes, all may be processed...
Which labor standards provisions require all laborers and mechanics...
What type of labor interview is used after detecting errors in labor...
Which termination consideration is not considered when determining...
Which labor standards provisions require the contractor to submit...
Acceptance of noncomplex commercial items is prescribed in
All are corrective actions that may be taken by the contracting...
In a commodity contract that has a Variations in Quantity clause, the...
What modification authority must be cited when making administrative...
Changes authorized in fixed-price contracts for supplies include all...
A contractor has notified the contracting officer of the intent not to...
The DD Form 1597, Contract Closeout Checklist, is used when closing...
Which is not required to be accomplished by the contracting officer...
A change order
Acceptance may not take place
All are examples of existing authorities that may be used to provide...
Unless otherwise specified in the contract, Federal Acquisition...
Which types of copies of contractual instruments can become part of...
A modification in which all adjustments regarding cost, time, scope,...
What actions will the contracting officer take if the contractor fails...
A notice for termination can be rescinded if it is determined that the...
What type of organizational structure requires contingency contracting...
Unilateral modifications may be used for all except
How can a termination for convenience of a fixed-price contract be...
After execution by all parties, copies of contracts or modifications...
A new wage determination must be incorporated into service contracts
When the government takes possession prior to completion of...
Alert!

Advertisement