The editorial team at ProProfs Quizzes consists of a select group of subject experts, trivia writers, and quiz masters who have authored over 10,000 quizzes taken by more than 100 million users. This team includes our in-house seasoned quiz moderators and subject matter experts. Our editorial experts, spread across the world, are rigorously trained using our comprehensive guidelines to ensure that you receive the highest quality quizzes.
Learn about Our Editorial Process
| By Quizcreationhelp
Q
Quizcreationhelp
Community Contributor
Quizzes Created: 3 | Total Attempts: 314
Questions: 33 | Attempts: 139

SettingsSettingsSettings
Network Quizzes & Trivia

Questions and Answers
  • 1. 

    The main outputs of estimating activity resources include the activity list and attributes, project scope statement, milestone list, and organizational process assets.

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    The main outputs of estimating activity resources do not include the project scope statement, milestone list, and organizational process assets. The correct answer is False.

    Rate this question:

  • 2. 

    Activity information is not a required input to the other time management processes.

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    Activity information is a required input to the other time management processes. This information includes details about the specific activities that need to be completed, their duration, dependencies, and sequencing. Without this information, it would be challenging to effectively plan and schedule activities, allocate resources, and manage the overall project timeline. Therefore, the statement that activity information is not a required input to the other time management processes is false.

    Rate this question:

  • 3. 

    Network diagrams are the preferred technique for showing activity discretionary dependencies.

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    Network diagrams are not the preferred technique for showing activity discretionary dependencies. Instead, activity-on-node diagrams or precedence diagrams are commonly used to represent these dependencies. Network diagrams primarily depict the sequence of activities and the relationships between them using nodes and arrows.

    Rate this question:

  • 4. 

    Every item on the WBS needs to be on the network diagram.

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    The statement is false because not every item on the Work Breakdown Structure (WBS) needs to be on the network diagram. The WBS is a hierarchical decomposition of the project scope, while the network diagram is a visual representation of the project activities and their dependencies. The network diagram only includes the activities that are necessary for completing the project, while the WBS includes all the deliverables and components of the project scope. Therefore, there may be items on the WBS that are not represented on the network diagram.

    Rate this question:

  • 5. 

    Start-to-finish relationships are the most common type of relationships.

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    The given statement claims that start-to-finish relationships are the most common type of relationships. However, there is no evidence or context provided to support this claim. Therefore, it cannot be concluded that start-to-finish relationships are the most common type of relationships. Hence, the correct answer is False.

    Rate this question:

  • 6. 

    In a Gantt chart created in Microsoft Project, a black diamond symbol represents a milestone.

    • A.

      True

    • B.

      False

    Correct Answer
    A. True
    Explanation
    A black diamond symbol in a Gantt chart represents a milestone. This means that it is used to indicate a significant event or achievement in the project timeline. Milestones are important points in the project that mark the completion of a major task or the achievement of a key objective. By using a black diamond symbol, Microsoft Project visually highlights these milestones in the Gantt chart, making it easier for project managers and team members to track progress and identify important project milestones.

    Rate this question:

  • 7. 

    By using the PERT weighted average for each activity duration estimate, the total project duration estimate does not account for the risk or uncertainty in the individual activity estimates.

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    The PERT weighted average for each activity duration estimate does account for the risk or uncertainty in the individual activity estimates. PERT takes into consideration three time estimates for each activity: the optimistic estimate, the most likely estimate, and the pessimistic estimate. By using a weighted average of these estimates, PERT incorporates the uncertainty and risk associated with each activity, resulting in a more accurate estimate for the total project duration. Therefore, the statement that the total project duration estimate does not account for the risk or uncertainty in the individual activity estimates is false.

    Rate this question:

  • 8. 

    ______ involves identifying the specific activities that the project team members and stakeholders must perform to produce the project deliverables.

    • A.

      Defining activities

    • B.

      Sequencing activities

    • C.

      Estimating activity resources

    • D.

      Estimating activity durations

    Correct Answer
    A. Defining activities
    Explanation
    Defining activities involves identifying the specific activities that the project team members and stakeholders must perform to produce the project deliverables. This includes breaking down the project scope into smaller, manageable tasks and creating a detailed list of activities that need to be completed. This helps in understanding the work required, assigning responsibilities, and developing a clear plan for executing the project.

    Rate this question:

  • 9. 

    The main outputs of the ____ process are an activity list, activity attributes, and milestone list.

    • A.

      Defining activities

    • B.

      Sequencing activities

    • C.

      Resource estimating activities

    • D.

      Duration estimating activities

    Correct Answer
    A. Defining activities
    Explanation
    The main outputs of the defining activities process are an activity list, activity attributes, and milestone list. This process involves identifying and documenting the specific activities that need to be performed in order to achieve the project objectives. The activity list provides a comprehensive list of all the activities, while the activity attributes provide additional information about each activity such as the activity ID, description, and predecessor/successor relationships. The milestone list identifies key points or events in the project timeline.

    Rate this question:

  • 10. 

    ____ involves analyzing activity sequences, activity resource estimates, and activity duration.

    • A.

      Estimating activity durations

    • B.

      Developing the schedule

    • C.

      Controlling the schedule

    • D.

      Estimating activity resources

    Correct Answer
    B. Developing the schedule
    Explanation
    Developing the schedule involves analyzing activity sequences, activity resource estimates, and activity duration. This process requires carefully examining the order in which activities need to be completed, estimating the resources required for each activity, and determining the duration of each activity. By considering these factors, a schedule can be created that outlines when each activity should start and finish, allowing for effective project planning and management.

    Rate this question:

  • 11. 

    ____ involves controlling and managing changes to the project schedule.

    • A.

      Estimating activity durations

    • B.

      Developing the schedule

    • C.

      Controlling the schedule

    • D.

      Estimating activity resources

    Correct Answer
    C. Controlling the schedule
    Explanation
    Controlling the schedule involves monitoring and adjusting the project schedule to ensure that it is on track and any changes or delays are properly managed. This includes tracking the progress of activities, identifying any variances or deviations from the planned schedule, and taking corrective actions to keep the project on schedule. It also involves communicating any schedule changes to stakeholders and updating the project schedule accordingly.

    Rate this question:

  • 12. 

    The ____ provide(s) schedule-related information about each activity, such as predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions related to the activity.

    • A.

      Activity list

    • B.

      Milestones

    • C.

      Activity descriptions

    • D.

      Activity attributes

    Correct Answer
    D. Activity attributes
    Explanation
    Activity attributes provide schedule-related information about each activity, such as predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions related to the activity. They are used to define and document the specific characteristics of each activity in a project schedule.

    Rate this question:

  • 13. 

    ____ occur when two or more activities follow a single node.

    • A.

      Combinations

    • B.

      Conflicts

    • C.

      Merges

    • D.

      Bursts

    Correct Answer
    D. Bursts
    Explanation
    Bursts occur when two or more activities follow a single node. This means that there is a sudden increase in the number of activities that need to be completed after a specific task or event. It can be seen as a burst of activities that need to be handled simultaneously or in quick succession.

    Rate this question:

  • 14. 

    The ____ is a network diagramming technique in which boxes represent activities.

    • A.

      PDM

    • B.

      AOA

    • C.

      ADM

    • D.

      POA

    Correct Answer
    A. PDM
    Explanation
    PDM stands for Precedence Diagramming Method, which is a network diagramming technique commonly used in project management. In PDM, activities are represented by boxes, and the relationships between activities are shown through arrows. This technique helps to visualize the sequence and dependencies of activities in a project, making it easier to plan and schedule tasks effectively. AOA (Activity-on-Arrow), ADM (Arrow Diagramming Method), and POA (Program of Activities) are other network diagramming techniques, but PDM specifically uses boxes to represent activities.

    Rate this question:

  • 15. 

    The activity list, activity attributes, activity resource requirements, resource calendars, project scope statement, enterprise environmental factors, and organizational process assets all include information that affect ____.

    • A.

      Definitions

    • B.

      Sequences

    • C.

      Resource estimates

    • D.

      Duration estimates

    Correct Answer
    D. Duration estimates
    Explanation
    The given answer, duration estimates, is correct because all the listed items in the question (activity list, activity attributes, activity resource requirements, resource calendars, project scope statement, enterprise environmental factors, and organizational process assets) provide information that can affect the estimation of the duration of activities in a project.

    Rate this question:

  • 16. 

    ____ is a network diagramming technique used to predict total project duration.

    • A.

      A Gantt chart

    • B.

      Critical path analysis

    • C.

      Critical chain scheduling

    • D.

      PERT analysis

    Correct Answer
    B. Critical path analysis
    Explanation
    Critical path analysis is a network diagramming technique used to predict the total project duration. It identifies the longest path of dependent activities in a project, known as the critical path. By determining the activities that have zero slack or float, critical path analysis helps project managers prioritize tasks and allocate resources effectively to ensure the project is completed within the shortest possible time frame. This technique is widely used in project management to optimize scheduling and minimize delays.

    Rate this question:

  • 17. 

    The critical path is the ____ path through a network diagram, and it represents the ____ time it takes to complete a project.

    • A.

      Longest; longest

    • B.

      Longest; shortest

    • C.

      Shortest; longest

    • D.

      Shortest; shortest

    Correct Answer
    B. Longest; shortest
    Explanation
    The critical path is the longest path through a network diagram, as it represents the maximum time it takes to complete a project. However, it also represents the shortest time it takes to complete the project because any delay in the critical path will directly impact the overall project duration. Therefore, the correct answer is "longest; shortest".

    Rate this question:

  • 18. 

    ____ is the amount of time an activity can be delayed without delaying the early start date of any immediately following activities.

    • A.

      Total slack

    • B.

      Total float

    • C.

      Free time

    • D.

      Free slack

    Correct Answer
    D. Free slack
    Explanation
    Free slack is the amount of time an activity can be delayed without delaying the early start date of any immediately following activities. It represents the flexibility in the project schedule and allows for some buffer time in case of unexpected delays or changes. It is important to monitor and manage free slack to ensure that the project stays on track and any potential risks or issues can be addressed in a timely manner.

    Rate this question:

  • 19. 

    ____ is the amount of time an activity can be delayed from its early start without delaying the planned project finish date.

    • A.

      Total slack

    • B.

      Free float

    • C.

      Total time

    • D.

      Free slack

    Correct Answer
    A. Total slack
    Explanation
    Total slack refers to the amount of time that an activity can be delayed from its early start without causing a delay in the overall project finish date. It represents the flexibility or cushion available in the project schedule. Activities with zero total slack are considered critical because any delay in these activities will directly impact the project's finish date. On the other hand, activities with positive total slack can be delayed without affecting the project's completion.

    Rate this question:

  • 20. 

    ____ is a technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost.

    • A.

      Crushing

    • B.

      Crashing

    • C.

      Fast tracking

    • D.

      Expediting

    Correct Answer
    B. Crashing
    Explanation
    Crashing is a technique used in project management to reduce the project duration by adding additional resources or increasing the intensity of work. It involves making trade-offs between cost and schedule to achieve the maximum amount of schedule compression at the least incremental cost. By crashing a project, the schedule can be shortened, allowing for faster completion and potentially saving time and resources.

    Rate this question:

  • 21. 

    ____ is a method of scheduling that considers limited resources when creating a project schedule and includes buffers to protect the project completion date.

    • A.

      A Gantt chart

    • B.

      Critical path analysis

    • C.

      Critical chain scheduling

    • D.

      PERT analysis

    Correct Answer
    C. Critical chain scheduling
    Explanation
    Critical chain scheduling is a method of scheduling that considers limited resources when creating a project schedule. It takes into account the availability of resources and ensures that they are allocated efficiently to avoid any bottlenecks or delays. Additionally, critical chain scheduling includes the use of buffers, which are extra time or resources added to the project schedule to protect the project completion date. These buffers help to account for any uncertainties or unexpected events that may occur during the project, allowing for a more realistic and achievable schedule.

    Rate this question:

  • 22. 

    Critical chain scheduling protects tasks on the critical chain from being delayed by using ____, which consist of additional time added before tasks on the critical chain that are preceded by non-critical-path tasks.

    • A.

      Critical paths

    • B.

      Feeding buffers

    • C.

      Dummy activities

    • D.

      Fast tracking

    Correct Answer
    B. Feeding buffers
    Explanation
    Feeding buffers are additional time added before tasks on the critical chain that are preceded by non-critical-path tasks. This protects the tasks on the critical chain from being delayed. Feeding buffers act as a buffer or cushion to absorb any delays that may occur in the non-critical-path tasks, ensuring that the tasks on the critical chain can start on time and proceed without any interruptions.

    Rate this question:

  • 23. 

    ____ states that work expands to fill the time allowed.

    • A.

      Murphy’s Law

    • B.

      Newton’s Law

    • C.

      Parkinson’s Law

    • D.

      Moore’s Law

    Correct Answer
    C. Parkinson’s Law
    Explanation
    Parkinson's Law states that work expands to fill the time allowed. This means that if there is a task or project with a deadline, people tend to use up all the available time to complete it, even if it could have been done in a shorter amount of time. This law highlights the tendency for work to become more complex and time-consuming than necessary, leading to inefficiency and procrastination.

    Rate this question:

  • 24. 

    Project managers often illustrate progress with a ____ showing key deliverables and activities.

    • A.

      Tracking Gantt chart

    • B.

      Gantt chart

    • C.

      Network diagram

    • D.

      PERT chart

    Correct Answer
    A. Tracking Gantt chart
    Explanation
    A Tracking Gantt chart is a type of Gantt chart that is commonly used by project managers to illustrate progress. It shows key deliverables and activities, allowing the project manager to track the progress of the project and identify any potential delays or issues. Unlike a regular Gantt chart, a Tracking Gantt chart also includes information on the actual progress made on each task, making it a useful tool for monitoring and controlling project progress.

    Rate this question:

  • 25. 

    The project scope statement provides the basis for planning and managing project schedules, costs, resources, and changes.

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    The project scope statement does provide the basis for planning and managing project schedules, costs, resources, and changes. Therefore, the correct answer is False.

    Rate this question:

  • 26. 

    A project team always organizes the WBS around project products.

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    The statement is false because a project team organizes the Work Breakdown Structure (WBS) around project deliverables, not project products. The WBS breaks down the project into smaller, manageable components called work packages, which are focused on the deliverables or outcomes of the project rather than the physical products themselves. This helps in organizing and planning the project activities more effectively.

    Rate this question:

  • 27. 

    A work package represents the level of work that the project manager monitors and controls.

    • A.

      True

    • B.

      False

    Correct Answer
    A. True
    Explanation
    A work package is a manageable unit of work within a project that can be assigned to a team or individual for execution. It is a way to break down the project into smaller, more manageable components. The project manager is responsible for monitoring and controlling the progress of these work packages to ensure that they are completed on time and within budget. Therefore, the statement that a work package represents the level of work that the project manager monitors and controls is true.

    Rate this question:

  • 28. 

    ____ involves reviewing the project charter, requirements documents, and organizational process assets to create a scope statement, adding more information as requirements are developed and change requests are approved.

    • A.

      Planning scope

    • B.

      Defining scope

    • C.

      Controlling scope

    • D.

      Verifying scope

    Correct Answer
    B. Defining scope
    Explanation
    Defining scope involves reviewing the project charter, requirements documents, and organizational process assets to create a scope statement. This process includes adding more information as requirements are developed and change requests are approved.

    Rate this question:

  • 29. 

    The main outputs of ____ are accepted deliverables and change requests.

    • A.

      Planning scope

    • B.

      Controlling scope

    • C.

      Defining scope

    • D.

      Verifying scope

    Correct Answer
    D. Verifying scope
    Explanation
    The main outputs of verifying scope are accepted deliverables and change requests. Verifying scope is the process of formalizing acceptance of the completed project deliverables. During this process, the project team and stakeholders review the deliverables to ensure they meet the requirements and specifications outlined in the project scope. If the deliverables are accepted, they are considered as outputs of the verification process. Additionally, any requested changes or modifications to the deliverables are also documented as change requests, which are another output of the verifying scope process.

    Rate this question:

  • 30. 

    An up-to-date ____ is an important document for developing and confirming a common understanding of the project scope.

    • A.

      Scope management plan

    • B.

      Project scope statement

    • C.

      WBS

    • D.

      Decomposition

    Correct Answer
    B. Project scope statement
    Explanation
    A project scope statement is an important document for developing and confirming a common understanding of the project scope. It outlines the project's objectives, deliverables, constraints, and assumptions. It provides a clear description of what is included and excluded from the project scope, ensuring that all stakeholders have a shared understanding of the project's boundaries and goals. This document is essential for effective scope management and helps to prevent scope creep and misunderstandings throughout the project lifecycle.

    Rate this question:

  • 31. 

    Of the following constraints, it is most difficult to describe, agree upon, and meet the ____ goal of many projects.

    • A.

      Scope

    • B.

      Time

    • C.

      Cost

    • D.

      Technical

    Correct Answer
    A. Scope
    Explanation
    The scope goal of many projects is the most difficult to describe, agree upon, and meet. This is because the scope defines the boundaries and deliverables of the project, and it can be challenging to clearly define and agree upon what should be included and excluded from the project. Additionally, as the project progresses, there may be changes or additions to the scope, making it even more difficult to meet this goal.

    Rate this question:

  • 32. 

    The ____ should list and describe all of the deliverables required for the project.

    • A.

      Project charter

    • B.

      Scope statement

    • C.

      WBS

    • D.

      Gantt chart

    Correct Answer
    B. Scope statement
    Explanation
    The scope statement is a document that outlines the objectives, deliverables, and boundaries of a project. It provides a clear understanding of what needs to be accomplished and the specific deliverables that are required. It describes the project's scope, objectives, constraints, and assumptions, helping to define the project's boundaries. The scope statement is an essential tool for project planning and ensures that all stakeholders have a common understanding of the project's requirements.

    Rate this question:

  • 33. 

    The ____ approach is best suited to project managers who have vast technical insight and a big-picture perspective.

    • A.

      Analogy

    • B.

      Bottom-up

    • C.

      Top-down

    • D.

      Mind mapping

    Correct Answer
    C. Top-down
    Explanation
    The top-down approach is best suited to project managers who have vast technical insight and a big-picture perspective. This approach involves starting with a broad overview of the project and then breaking it down into smaller, more manageable tasks. It allows project managers to set clear goals and objectives from the beginning and ensures that all team members are aligned with the overall vision. With their technical expertise and ability to see the project as a whole, project managers can effectively prioritize tasks and allocate resources accordingly.

    Rate this question:

Quiz Review Timeline +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 21, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Mar 05, 2012
    Quiz Created by
    Quizcreationhelp
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.