Professional Practice 03

22 Questions | Attempts: 3078
Share

SettingsSettingsSettings
Professional Practice Quizzes & Trivia

The term “professional practice” has a number of definitions, one of which being the act in which a student is required to further their knowledge and skills within a practical environment. What do you know about the following fields?


Questions and Answers
  • 1. 

    Not included in the scope of services for Interior Design of a music studio commissioned to an Architect

    • A.

      Prepares electronic equipment specifications

    • B.

      Prescribes interior finishes

    • C.

      Prepares furniture schedule

    • D.

      Assists negotiations with fabricators.

    Correct Answer
    A. Prepares electronic equipment specifications
  • 2. 

    Not included in the scope of services under Physical Planning.

    • A.

      Environmental studies

    • B.

      Impact analysis

    • C.

      Examination of laws, ordinances, rules and regulations

    • D.

      Engineering dawings and specifications

    Correct Answer
    B. Impact analysis
  • 3. 

    Which component is not considered in the formulation of the Master Development Plan under the Comprehensive Planning Services?

    • A.

      Site Development

    • B.

      Legal and Administrative

    • C.

      Economic

    • D.

      Transport

    Correct Answer
    A. Site Development
  • 4. 

    When the Architect as Environmental Planner is commissioned to do town and regional planning or urban renewal projects, he performs the following except one:

    • A.

      Undertakes demographic analysis

    • B.

      Prepares concept development plans

    • C.

      Identifies social behavior and interaction

    • D.

      Undertakes environmental impact assessment

    Correct Answer
    D. Undertakes environmental impact assessment
  • 5. 

    How are projects classified in determining the basis for the Architect's Basic Fee?

    • A.

      Material specifications

    • B.

      Total floor area

    • C.

      Degree of project complexity

    • D.

      Structural components

    Correct Answer
    C. Degree of project complexity
  • 6. 

    What is the minimum basic fee for public markets with a project construction cost of P50M.

    • A.

      P 2.5 M

    • B.

      P 3M

    • C.

      P 3.5 M

    • D.

      P 4M

    Correct Answer
    B. P 3M
  • 7. 

    What is the minimum basic fee for publishing plants with a project construction cost of P40M?

    • A.

      P 2.4 M

    • B.

      P 2.8M

    • C.

      P 3.2 M

    • D.

      P 3.6M

    Correct Answer
    B. P 2.8M
  • 8. 

    What is the minimum basic fee for public health centers with a project construction cost of P50M or less?

    • A.

      5%

    • B.

      6%

    • C.

      7%

    • D.

      8%

    Correct Answer
    D. 8%
  • 9. 

    When the design of the Architect is used again to build a sixth structure without amending the drawing and specifications, how much shall the Architect's fee be computed?

    • A.

      20% of basic fee

    • B.

      30% of basic fee

    • C.

      40% of basic fee

    • D.

      60% of basic fee

    Correct Answer
    C. 40% of basic fee
  • 10. 

    For a housing project exceeding 10 units, how much is the minimum fee chargeable for each additional unit, excluding the fees for the first 10 units?

    • A.

      20% of basic fee

    • B.

      30% of basic fee

    • C.

      40% of basic fee

    • D.

      60% of basic fee

    Correct Answer
    B. 30% of basic fee
  • 11. 

    Which group classification belongs projects involving extensive detail such furniture design, built-in equipment, special fittings, screens, counters, interiors and other detailed parts of appurtenances of buildings or structures and landscaping designs?

    • A.

      Group 6

    • B.

      Group 7

    • C.

      Group 8

    • D.

      Group 9

    Correct Answer
    C. Group 8
  • 12. 

    A method of selection for an Architect most often used by an individual person undertaking a relatively small project

    • A.

      Comparative selection

    • B.

      Design competition

    • C.

      Bidding

    • D.

      Direct selection

    Correct Answer
    D. Direct selection
  • 13. 

    Most expensive and time-consuming method of selecting the Architect.

    • A.

      Comparative selection

    • B.

      Design competition

    • C.

      Mixed method

    • D.

      Direct selection

    Correct Answer
    B. Design competition
  • 14. 

    Not a criteria for computing the Architect's compensation.

    • A.

      Talent and skill

    • B.

      Experience

    • C.

      Personal relations

    • D.

      Effort and time available

    Correct Answer
    C. Personal relations
  • 15. 

    The method of compensation should not have the following characteristic.

    • A.

      Fair to client and architect

    • B.

      Easy to understand

    • C.

      Not create legal problems

    • D.

      Focus client's attention to price

    Correct Answer
    D. Focus client's attention to price
  • 16. 

    A method of compensation that is flexible, easy to apply and is related to the size and the type of the project.

    • A.

      Multiple of direct personnel expense

    • B.

      Percentage of construction cost

    • C.

      Professional fee plus expenses

    • D.

      Lump sum or fixed fee

    Correct Answer
    B. Percentage of construction cost
  • 17. 

    The multiple of personnel direct expense is applicable only to what type of work?.

    • A.

      Research

    • B.

      Creative work

    • C.

      Government projects

    • D.

      Ocular site inspection

    Correct Answer
    A. Research
  • 18. 

    The multiplier applied in the multiple of direct personnel expense depends on the following except one:

    • A.

      Complexity of project office set-up

    • B.

      Office set-up

    • C.

      Experience of the Architect

    • D.

      Cost of transportation

    Correct Answer
    D. Cost of transportation
  • 19. 

    A method of compensation frequently used where there is a continuing relationship on a series of projects.:

    • A.

      Multiple of direct personnel expense

    • B.

      Percentage of construction cost

    • C.

      Professional fee plus expenses

    • D.

      Lump sum or fixed fee

    Correct Answer
    C. Professional fee plus expenses
  • 20. 

    A method of compensation that represents a risk situation to the Architect since his costs may exceed the agreed amount.

    • A.

      Multiple of direct personnel expense

    • B.

      Percentage of construction cost

    • C.

      Professional fee plus expenses

    • D.

      Lump sum or fixed fee

    Correct Answer
    D. Lump sum or fixed fee
  • 21. 

    An activity where the Architect may be paid on a per diem basis plus out-of-pocket expenses such as travel, accommodations and subsistence, long-distance telephone calls, secretarial service.

    • A.

      Confer with prospective investors

    • B.

      Data gathering

    • C.

      Feasibility study

    • D.

      Accounting

    Correct Answer
    A. Confer with prospective investors
  • 22. 

    Which work item is chargeable to the Owner and not included in the regular scope of services?

    • A.

      Miniature models of design studies

    • B.

      Extra drafting of changes made by Owner

    • C.

      Structural analysis

    • D.

      Electrical load calculation

    Correct Answer
    B. Extra drafting of changes made by Owner

Quiz Review Timeline +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Nov 13, 2017
    Quiz Edited by
    ProProfs Editorial Team
  • Feb 26, 2009
    Quiz Created by
    Raegab
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.