Dpm Spring 2016 Midterm

Approved & Edited by ProProfs Editorial Team
The editorial team at ProProfs Quizzes consists of a select group of subject experts, trivia writers, and quiz masters who have authored over 10,000 quizzes taken by more than 100 million users. This team includes our in-house seasoned quiz moderators and subject matter experts. Our editorial experts, spread across the world, are rigorously trained using our comprehensive guidelines to ensure that you receive the highest quality quizzes.
Learn about Our Editorial Process
| By Rosemary Olszewski
R
Rosemary Olszewski
Community Contributor
Quizzes Created: 1 | Total Attempts: 162
Questions: 15 | Attempts: 162

SettingsSettingsSettings
Budget Quizzes & Trivia

Questions and Answers
  • 1. 

    Which type of change is recognized by owner as a contract change?

    • A.

      Constructive

    • B.

      Directed

    Correct Answer
    B. Directed
    Explanation
    When the owner recognizes a change as a contract change, it means that the change was specifically requested or directed by the owner. This indicates that the owner has actively initiated the change and has given instructions or directives for it to be implemented. Therefore, the correct answer is "Directed."

    Rate this question:

  • 2. 

    What comprises a Revenue Budget?

    • A.

      Cost Budget + Margin

    • B.

      Non-Billable Budget

    • C.

      Management Reserve

    • D.

      Cost Budget + Non-billable Budget + Management Reserve

    Correct Answer
    A. Cost Budget + Margin
    Explanation
    A revenue budget comprises a cost budget and margin. The cost budget includes all the expenses and costs associated with generating revenue, such as production costs, overhead costs, and operating expenses. The margin represents the profit or revenue generated after deducting the cost budget from the total revenue. Therefore, the correct answer is cost budget + margin.

    Rate this question:

  • 3. 

    What are typical triggers for change? (Select all that apply)

    • A.

      Suspension of Work

    • B.

      Extra Scope

    • C.

      Eliminated Scope

    • D.

      Differing Site Condition

    Correct Answer(s)
    A. Suspension of Work
    B. Extra Scope
    C. Eliminated Scope
    D. Differing Site Condition
    Explanation
    Typical triggers for change in a project can include suspension of work, extra scope, eliminated scope, and differing site conditions. Suspension of work refers to a temporary halt in project activities, which may necessitate changes in the project plan. Extra scope refers to additional requirements or tasks that are added to the project, leading to changes in the project scope. Eliminated scope refers to the removal of certain requirements or tasks from the project, resulting in changes to the project plan. Differing site conditions refer to unexpected conditions or circumstances at the project site that require modifications to the project plan.

    Rate this question:

  • 4. 

    It is important to understand the client's procedures for addressing change?

    • A.

      True

    • B.

      False

    Correct Answer
    A. True
    Explanation
    Understanding the client's procedures for addressing change is important because it allows the service provider to align their own processes with the client's, ensuring smooth communication and collaboration. This understanding helps in effectively managing and implementing any changes requested by the client, minimizing disruptions and potential conflicts. It also helps in maintaining a good working relationship with the client by demonstrating a willingness to adapt and meet their specific needs. Overall, having knowledge of the client's change procedures enables a more efficient and successful project or service delivery.

    Rate this question:

  • 5. 

    Margin Erosion only occurs when the final margin is negative.

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    Margin erosion can occur even when the final margin is not negative. It refers to a situation where the profit margin of a company decreases over time due to various factors such as increased competition, rising costs, or pricing pressures. This can happen even if the final margin remains positive, as long as it is lower than the previous margin. Therefore, the statement that margin erosion only occurs when the final margin is negative is false.

    Rate this question:

  • 6. 

    Multiple compensation types can exist within the same project.

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    The statement is false because multiple compensation types cannot exist within the same project. Compensation types are usually mutually exclusive and are designed to address specific aspects of a project, such as cost, time, or quality. Each project typically adopts a single compensation type that aligns with its objectives and requirements. Using multiple compensation types simultaneously can introduce confusion, conflicts, and inefficiencies in project management. Therefore, it is generally recommended to choose and implement a single compensation type for a project.

    Rate this question:

  • 7. 

    How many WBS Levels does Data Query allow?

    • A.

      10

    • B.

      4

    • C.

      8

    • D.

      2

    Correct Answer
    B. 4
    Explanation
    Data Query allows for four WBS Levels.

    Rate this question:

  • 8. 

    Non-billable costs do not affect project margin

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    Non-billable costs actually do affect project margin. These costs refer to expenses that are not directly invoiced to the client, such as overhead costs, administrative expenses, or internal training costs. While these costs may not be directly billable to the client, they still impact the overall profitability of the project. Therefore, non-billable costs do have an effect on project margin, making the answer "False."

    Rate this question:

  • 9. 

    Physical % Complete should be updated monthly, at a minimum.

    • A.

      True

    • B.

      False

    Correct Answer
    A. True
    Explanation
    Physical % Complete should be updated monthly, at a minimum, because it provides an accurate measurement of the progress made on a project. By updating the physical % complete regularly, project managers can track the actual work completed against the planned work and identify any discrepancies or delays. This allows for better decision-making and adjustments to be made to keep the project on track. Regular updates also help in identifying potential issues or risks early on, enabling proactive measures to be taken. Therefore, updating physical % complete monthly or more frequently is essential for effective project management.

    Rate this question:

  • 10. 

    Earned Value is calculated as:

    • A.

      Physical % Complete * Cost Budget

    • B.

      Revenue at Completion - Cost at Completion

    • C.

      Collected - Net Cost

    • D.

      Revenue accumulated in PBIS since the beginning of the project

    Correct Answer
    A. Physical % Complete * Cost Budget
    Explanation
    Earned Value is a measure used in project management to assess the progress and performance of a project. It is calculated by multiplying the physical percentage complete (the actual progress made on the project) by the cost budget (the planned cost for the project). This calculation helps determine how much value has been earned or accomplished in relation to the planned budget. By multiplying these two factors, the earned value provides a quantitative measure of the work completed and the corresponding cost associated with it.

    Rate this question:

  • 11. 

    Earned Value should be based on schedule

    • A.

      True

    • B.

      False

    Correct Answer
    A. True
    Explanation
    Earned Value is a project management technique that measures the progress of a project in terms of the budgeted cost of work performed. It compares the actual work completed with the planned work and provides an objective assessment of project performance. In order to accurately measure the progress, Earned Value should be based on the project schedule. This means that the work completed should be compared to the planned schedule to determine if the project is ahead of schedule, on schedule, or behind schedule. Therefore, the statement "Earned Value should be based on schedule" is true.

    Rate this question:

  • 12. 

    Who can authorize project work to continue in advance of an executed contract modification?

    • A.

      Principal-In-Charge

    • B.

      Project Manager

    • C.

      Legal Department

    • D.

      Area Manager

    • E.

      A, C, and D above

    Correct Answer
    D. Area Manager
    Explanation
    The Area Manager can authorize project work to continue in advance of an executed contract modification. This implies that the Area Manager has the authority to make decisions regarding the project and has the power to give the go-ahead for work to proceed even without a formal contract modification. The Principal-In-Charge, Project Manager, and Legal Department may also have certain levels of authority, but the Area Manager is specifically mentioned as the one who can authorize work to continue.

    Rate this question:

  • 13. 

    Cost to Completion is simply the contract value minus the cost already spent

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    The explanation for the given answer (False) is that Cost to Completion is not simply the contract value minus the cost already spent. Cost to Completion refers to the estimated cost required to complete a project or contract, taking into account the work that still needs to be done and the resources required for it. It is not just the difference between the contract value and the cost already incurred, as it also considers the projected expenses for the remaining work.

    Rate this question:

  • 14. 

    The Management Reserve is to be spent at the PM's discretion.

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    The Management Reserve is not to be spent at the PM's discretion. The Management Reserve is a portion of the project budget that is set aside for unforeseen risks or changes that may occur during the project. It is intended to be used for approved changes or risks that were not initially accounted for in the project plan. The spending of the Management Reserve should be governed by the established change control process and approved by the appropriate stakeholders, rather than solely at the discretion of the project manager.

    Rate this question:

  • 15. 

    For a fixed price contract, PB invoices the client for the number of hours it actually expended to complete the work. 

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    For a fixed price contract, the client is invoiced a predetermined fixed amount for the completion of the work, regardless of the number of hours actually expended. In this case, the correct answer is False, as PB invoices the client for the fixed price agreed upon, not for the number of hours expended.

    Rate this question:

Quiz Review Timeline +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 21, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Mar 28, 2016
    Quiz Created by
    Rosemary Olszewski
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.