Take The Coles Express Contractor Induction! Quiz

Reviewed by Editorial Team
The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Charles Griffin
C
Charles Griffin
Community Contributor
Quizzes Created: 1 | Total Attempts: 45,491
| Attempts: 45,491 | Questions: 10
Please wait...
Question 1 / 10
0 %
0/100
Score 0/100
1. Contractors must comply with any requirement outlined in the Coles Express Contractor Work Permitting Requirements table

Explanation

Contractors are obligated to adhere to the specifications mentioned in the Coles Express Contractor Work Permitting Requirements table. This means that they must follow all the outlined requirements without exception.

Submit
Please wait...
About This Quiz
Take The Coles Express Contractor Induction! Quiz - Quiz

There are three levels of inductions for a Cole Group contractor. All the contractors are expected to complete the online induction before they are ready to go to... see moretheir designated sites. The quiz below is designed to test out how ready you are for the final test. Give it a shot!
see less

2. The contractor must first satisfy the site manager (or their delegate) that the site is being left in a safe condition, before the site manager will sign the 'Finish Time' section of an WPCG Work Clearance.

Explanation

The explanation for the given correct answer is that the contractor is required to ensure that the site is safe before the site manager will sign off on the "Finish Time" section of the WPCG Work Clearance. This implies that the contractor must take necessary measures to eliminate any potential hazards or dangers on the site, ensuring the safety of workers and others present.

Submit
3. If the work you perform requires you to electrically isolate a piece of mechanical equipment, you will need to first complete a Equipment Isolation Permit

Explanation

If the work requires electrical isolation of a piece of mechanical equipment, it is necessary to complete an Equipment Isolation Permit. This permit ensures that the equipment is safely disconnected from its power source, minimizing the risk of electrical accidents or damage. By completing this permit, the necessary precautions and procedures can be followed to ensure the safety of the workers and the equipment. Therefore, the statement is true.

Submit
4. 1.       Hot Work can be

Explanation

Hot work refers to any process or activity that generates heat, sparks, or an open flame. This can include the use of an open flame, work that creates a spark, and the use of cutting or grinding tools. Therefore, the correct answer is "All of the above" as all the options listed are examples of hot work.

Submit
5. 1.       For traffic management to be compliant with Coles Express requirements; the bollards, cones or barricade used:

Explanation

The bollards, cones, or barricades used for traffic management must be at least 700mm in height, made of high-visibility material, and possess a strip of Class 1 reflective material. This ensures that they are easily visible and compliant with Coles Express requirements.

Submit
6. An WPCG Work Clearance is not required on a Coles Express site if you are performing physical work inside the store

Explanation

At a Coles Express site, WPCG Work Clearance is required for physical work inside or outside the store.

Submit
7. Contractors do not need to discuss any details about their WPCG Work Clearance form with the manager on site, because completing that form is a contractor responsibility.

Explanation

Contractors are responsible for ensuring the WPCG Work Clearance is completed, however part of that responsibility is to discuss the key points of their risk assessment and work controls with the site manager or their delegate.

Submit
8. 1.       A Hot Works in Hazardous Zones Permit is

Explanation

The correct answer is that a Hot Works in Hazardous Zones Permit is written by a person who is on-site, who has successfully completed this online induction, and then needs to be authorized by a Coles Express approved Permit Authorizer before works commence. This means that the person writing the permit must be physically present at the worksite and have completed the necessary online training. Additionally, the permit must be authorized by an approved authorizer before any work can begin.

Submit
9. On Coles Express sites, the whole forecourt is considered to be a hazardous zone.

Explanation

The forecourt is certainly where hazardous zones tend to be; but at Coles Express sites, the whole forecourt is not a hazardous zone. Hazardous zones are areas within a certain distance from those assets that can be a source of flammable vapours. Check the Hazard Map for more details.

Submit
10. 1     On Coles Express sites, a Hot Work In Hazardous Zones Permit is required when you are performing

Explanation

Hot works in a hazardous zone marked on the Hazard Map, if you could not instead create temporary safe work area compliant with Coles Express requirements.

Submit
View My Results

Quiz Review Timeline (Updated): Mar 22, 2023 +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 22, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Mar 16, 2011
    Quiz Created by
    Charles Griffin
Cancel
  • All
    All (10)
  • Unanswered
    Unanswered ()
  • Answered
    Answered ()
Contractors must comply with any requirement outlined in the Coles...
The contractor must first satisfy the site manager (or their delegate)...
If the work you perform requires you to electrically isolate a piece...
1.       Hot Work can be
1.       For traffic management to be...
An WPCG Work Clearance is not required on a Coles Express site if you...
Contractors do not need to discuss any details about their WPCG...
1.       A Hot Works in Hazardous Zones...
On Coles Express sites, the whole forecourt is considered to be a...
1     On Coles Express sites, a Hot Work In...
Alert!

Advertisement