This Architect Registration Exam - CDS quiz assesses knowledge on building compliance, construction materials, and ADA regulations. It is designed for architects seeking to validate their understanding of professional standards and project management responsibilities.
Cast in Place Concrete
Precast Concrete
Reinforced Brick Masonry
Reinforced hollow unit masonry
Rate this question:
Yes, if the building is more than two stories
Yes, Unless compliance with the requirements would threaten or destroy the historic significance of the building.
No, historic buildings are exempt from ADA requirements
Yes, but only if the building already contains an elevator
Rate this question:
Nothing, because no violations have been noted by the inspector, and the architect has no evidence that the construction is not in conformance with the contract documents
Prepare a change order requiring the contractor to uncover the ceiling for the architect's inspection
Request the contractor to uncover the ceiling for the architect's inspection
Ask the owner to direct the contractor to uncover the ceiling, because the architect lacks such authority himself.
Rate this question:
Rate this question:
Schematic Design
Design Development
Construction Documents
Change in Services
Rate this question:
Inform the electrical engineer of the regulation and verify that appropriate poles are specified in the contract documents
Notify the owner of the regulation
Notify the contractor of the regulation as the light poles are being installed
Notify the contractor of the regulation before construction has begun
Rate this question:
High quality products usually have a greater long-term cost than products of lower quality
Construction costs represent about 15 percent of the long-term cost of a project
Financing costs may be decreased when a fast-track procedure is used.
Life Cycle costs include the costs of replacement and renovation
Rate this question:
Wind Loads
Seismic Forces
Hydrostatic Pressure
All of the above
Rate this question:
I and II
II and III
I and IV
I, II and III
Rate this question:
Review of product substitutions
Processing Application for payment
Review of Shop Drawings
Preparation of a punchlist
Rate this question:
I
I and II
II, III, and IV
All of the above
Rate this question:
The architect's fees will increase, but those consultants will remain the same
The architect's fees will remain the same, but the those of consultants will increase
Both the architect's and consultant's fess will increase
There will be no change in the cost of design services
Rate this question:
The architect
The structural engineer
The mechanical engineer
The landscape architect
Rate this question:
Standard conditions
General conditions
Special Conditions
Supplementary Conditions
Rate this question:
The product must be identical to the one specified
The product must match the quality and performance of the one specified, as determined by the architect
The product must be one of the products named in the specifications.
Open proprietary specifications are not usually permitted on publicly-funds projects
Rate this question:
Instruction to bidders
Supplementary Conditions
General Conditions
Special Conditions
Rate this question:
General Conditions
Owner-Contractor Agreement
Drawings and specifications
Instruction to bidders
Rate this question:
I, II and III
III & IV
I, II, III & IV
I, II, IV, and V
Rate this question:
Quality
Methods
Dimensions
Installation techniques
Rate this question:
Chapters
Sections
Parts
Divisions
Rate this question:
Rate this question:
Contractor
Building Department
Architect
Owner
Rate this question:
Show complete information in all details
Show complete information in one location and provide references to that location throughout the drawings
Draw no details but refer to manufacturer's product data
Do none of the above
Rate this question:
Open proprietary specification
Closed Proprietary specification
Performance specifications
Descriptive specification
Rate this question:
Reduce the quality of the building's materials and systems
Reduce the scope of the project
Notify the owner and lender and temporarily suspend work on the project until they reach a decision
Review the program with the owner to determine where cost savings should be made
Rate this question:
I only
II only
III only
II and III
Rate this question:
Operational costs
Taxes and financing
Maintenance costs
Replacement costs
Rate this question:
Area and volume estimates
Subsystem estimates
Cost per unit
Quality and cost method
Rate this question:
II, III, and IV
I, II, and V
I, II, III, and IV
All of the above
Rate this question:
Specifications
Drawings
Addenda
Shop drawings
Rate this question:
Due dilligence
Quality control
Project coodination
Quality assurance
Rate this question:
Light fixtures
HVAC ductwork
Plumbing fixtures
Concrete
Rate this question:
The contractor is responsible for scheduling the construction trades and the sequence of work
CPM schedule are superior to bar charts because they show relationships between activities, not just duration and sequences
The architect generally establishes the requirements for the construction schedule
In a CPM diagram, the path with the shortest required time is the critical path
Rate this question:
Supply piping
Public water lines
Fixtures
Sanitary piping
Rate this question:
Advise the owner
Advise the building department
Revise the construction schedule
Instruct the contractor to work overtime
Rate this question:
Floor Plans
Exterior elevations
Reflected Ceiling Plan
Wall sections and details
Rate this question:
Programming the requirements of the project
Providing comparatives studies of prospective sites
Providing a preliminary estimates of construction costs
Assisting the owner in obtaining negotiated proposals
Providing services for planning rental spaces
The electrican
The electrical subcontractor
The surety
The contractor
Rate this question:
At final completion
At substantial completion
When the architect determines that retainage is no longer need for the owner's protection
As called for in the owner-contractor agreement and if the contractor's surety consents
Rate this question:
Permit the substitution of aluminum wire if it has equal or greater current capacity and voltage drop, with any cost saving to be credited to the owner
Permit the substitution of aluminum wire if it has equal or greater current carrying capacity and equal or less voltage drop, with any cost saving to be credited to the owner
Require the contractor to install the specified copper wire regardless of the cost of copper
Confirm that the aluminum wire has equal or greater current carrying capacity and equal or less voltage drop, then prepare a change order reflecting any change in contract sum to the owner for approval
Rate this question:
Labor and Material payment bond
Bid Bond
Liquidated Damages clause
Performance Bond
Rate this question:
Ask the subcontractor who installed the flashing to correct the work at no cost to the owner
Ask the general contractor to correct the work at no cost to the owner
Hire a new contractor to remedy the situation and charge the owner
Hire a new contractor to remedy the situation and charge the original contractor's insurance company
Rate this question:
Immediately contact the architect for instructions
Act at his or her own discretion, but only if people are likely to be injured
Act at his or her owner discretion to prevent threatened damage, injury or loss
Immediately contact the building official
Rate this question:
I and IV
I or II
III & IV
I, III and IV
Rate this question:
Rate this question:
The architect should take responsibility for locating a brick which is in production
The owner should furnish the brick for installation by the contractor
The architect should advise the owner to select a substitute that is available
The contractor should be instructed to locate the substituted brick at any cost
Rate this question:
Issue a construction change directive if the change in the work, the contract sum, and the contract time are agreed to by the owner, contractor and architect
Issue a field order signed by the owner, contractor and architect
Issue a change order if the change in the work, the contract sum, and the contract time are agreed to by the owner, architect, and contractor
Order the contractor to proceed with the change and negotiate any adjustment in the contract sum or contract time later
Rate this question:
I, III, IV
II, III, V
II and III
III and IV
Rate this question:
Quiz Review Timeline (Updated): Jul 22, 2023 +
Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.
Wait!
Here's an interesting quiz for you.