Architect Registration Exam - Cds

Reviewed by Editorial Team
The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Jimc5408
J
Jimc5408
Community Contributor
Quizzes Created: 1 | Total Attempts: 173
| Attempts: 173
SettingsSettings
Please wait...
  • 1/93 Questions

    The juristiction where a project is proposed to be built requires that all parking lot light poles be limited to 25 feet in height. In order to best ensure that this regulations is met, the architect should

    • Inform the electrical engineer of the regulation and verify that appropriate poles are specified in the contract documents
    • Notify the owner of the regulation
    • Notify the contractor of the regulation as the light poles are being installed
    • Notify the contractor of the regulation before construction has begun
Please wait...
About This Quiz

This Architect Registration Exam - CDS quiz assesses knowledge on building compliance, construction materials, and ADA regulations. It is designed for architects seeking to validate their understanding of professional standards and project management responsibilities.

Architect Registration Exam - Cds - Quiz

Quiz Preview

  • 2. 

    In addition to vertical loads, building structures must also be designed to resist which of the following

    • Wind Loads

    • Seismic Forces

    • Hydrostatic Pressure

    • All of the above

    Correct Answer
    A. All of the above
    Explanation
    Building structures must be designed to resist not only vertical loads but also lateral loads. Wind loads refer to the force exerted by wind on the building, which can cause lateral movement and put stress on the structure. Seismic forces are the vibrations and movements caused by earthquakes, which can also generate lateral forces that the building must withstand. Hydrostatic pressure refers to the pressure exerted by water, which can create horizontal forces on the structure. Therefore, all of the above options are correct as building structures must be designed to resist wind loads, seismic forces, and hydrostatic pressure in addition to vertical loads.

    Rate this question:

  • 3. 

    Which of following is a consultant that might be employed in a sustainable design project?I. Wetland EngineerII. Energy CommissionerIII. Landscape ArchitectIV. Energy Modeling Engineer

    • I

    • I and II

    • II, III, and IV

    • All of the above

    Correct Answer
    A. All of the above
    Explanation
    All of the mentioned consultants can be employed in a sustainable design project. A wetland engineer can provide expertise in managing and designing wetland systems to enhance sustainability. An energy commissioner can offer guidance and advice on energy policies and regulations to ensure sustainable energy practices. A landscape architect can design outdoor spaces that are environmentally friendly and sustainable. An energy modeling engineer can use computer simulations to optimize energy efficiency and sustainability in building design. Therefore, all of these consultants can contribute to a sustainable design project.

    Rate this question:

  • 4. 

    In an effort to save money during a project, the owner elects to use a brick which is less expensive than the one originally specified. The contractor determines that the new brick is out of production and unavailable. In order to avoid delays

    • The architect should take responsibility for locating a brick which is in production

    • The owner should furnish the brick for installation by the contractor

    • The architect should advise the owner to select a substitute that is available

    • The contractor should be instructed to locate the substituted brick at any cost

    Correct Answer
    A. The architect should advise the owner to select a substitute that is available
    Explanation
    The architect should advise the owner to select a substitute that is available. Since the new brick specified by the owner is out of production and unavailable, it would cause delays in the project if the contractor cannot find it. Therefore, the architect should take responsibility for advising the owner to choose a substitute that is readily available, ensuring that the project can proceed without any delays.

    Rate this question:

  • 5. 

    A change order must be approved by all of the following EXCEPT the 

    • Architect

    • Owner

    • Building department

    • Contractor

    Correct Answer
    A. Building department
    Explanation
    A change order is a document that outlines any modifications or additions to the original construction contract. It typically requires approval from various parties involved in the project. In this case, the question asks for the exception to the approval requirement. The architect, owner, and contractor are all directly involved in the project and have a vested interest in any changes. However, the building department, which is a government agency responsible for enforcing building codes and regulations, may not need to approve a change order as it is not directly involved in the contractual aspects of the project.

    Rate this question:

  • 6. 

    To expedite construction, the ceiling subcontractor installs a portion of the suspended ceiling prior to the building department's above ceiling HVAC inspection. The building inspector subsequently requests that the ceiling be removed in order to facilitate his inspection. Who must pay the cost of removing and reinstalling the ceiling?

    • The building inspector

    • The ceiling subcontractor

    • The contractor

    • The owner

    Correct Answer
    A. The contractor
    Explanation
    The contractor must pay the cost of removing and reinstalling the ceiling. As the general contractor responsible for the overall construction project, it is their responsibility to ensure that all necessary inspections are completed before proceeding with further construction. In this case, the contractor should have coordinated with the building department to schedule the above ceiling HVAC inspection before allowing the ceiling subcontractor to install a portion of the suspended ceiling. Since the contractor failed to do so, they are liable for the cost of removing and reinstalling the ceiling to facilitate the inspection.

    Rate this question:

  • 7. 

    On a project, the contractor's superintendent and the architect notice that the scaffolding is wobbly and may be unsafe. What is the best course of action?

    • The architect should instruct the superintendent on how to strength the scaffolding

    • The superintendent should contact the nearest OSHA office for instructions

    • The subcontractor who installed the scaffolding should determine if it is safe

    • The superintendent should not allow the scaffolding to be used until it has been made safe

    Correct Answer
    A. The superintendent should not allow the scaffolding to be used until it has been made safe
    Explanation
    The best course of action in this situation is for the superintendent to not allow the scaffolding to be used until it has been made safe. This is the most responsible and cautious approach to ensure the safety of the workers. By not allowing its use, the superintendent can prevent any potential accidents or injuries that could occur due to the wobbly and unsafe scaffolding. It is important to prioritize safety and address any concerns promptly before proceeding with the project.

    Rate this question:

  • 8. 

    You are the architect for a hotel project which has been completed and for which you have been completed and for which you have been paid in full. The owner informs you that he is so gratified with the plans and specifications that he intends to reuse them for an identical facility on a different site. What should be your response?

    • Thank the owner and allow him to reuse the documents, since he legally has the right anyway

    • Bill the owner for 50% of the original fee, in accordance with the General Conditions

    • Submit the case for arbitration to determine whether the owner may reuse the documents

    • Inform the owner that the documents are your property and may not be used on any other project

    Correct Answer
    A. Inform the owner that the documents are your property and may not be used on any other project
    Explanation
    The correct answer is to inform the owner that the documents are your property and may not be used on any other project. As the architect, you have the legal right to retain ownership of the plans and specifications. The owner cannot reuse them without your permission, even if they have paid you in full for the project.

    Rate this question:

  • 9. 

    Upon final completion of a building, the building inspector discovers that the toilet fixtures do not comply with CABO/ANSI A11.7.1, as required by the building code. After an investigation, it is determined that the installed toilet fixtures comply with the project specifications. Who is responsible for the cost of removing and replacing the fixtures?

    • The Architect

    • The Owner

    • The Contractor

    • The Building Department

    Correct Answer
    A. The Architect
    Explanation
    The architect is responsible for the cost of removing and replacing the fixtures. As the professional who designed the building and specified the toilet fixtures, it is their responsibility to ensure that the fixtures comply with the building code requirements. If the installed fixtures do not meet the code, it indicates a failure on the part of the architect to properly specify the correct fixtures. Therefore, they should bear the cost of rectifying the situation.

    Rate this question:

  • 10. 

    An architect is hired to renovate a building listed on the National Register of Historic Places. Is the building requires to have an elevator complying with American with Disabilities Acts (ADA) regulations. 

    • Yes, if the building is more than two stories

    • Yes, Unless compliance with the requirements would threaten or destroy the historic significance of the building.

    • No, historic buildings are exempt from ADA requirements

    • Yes, but only if the building already contains an elevator

    Correct Answer
    A. Yes, Unless compliance with the requirements would threaten or destroy the historic significance of the building.
    Explanation
    The correct answer is "Yes, Unless compliance with the requirements would threaten or destroy the historic significance of the building." This means that the building is required to have an elevator complying with ADA regulations, unless installing one would harm the historic significance of the building. This recognizes the importance of preserving historic buildings while also ensuring accessibility for individuals with disabilities.

    Rate this question:

  • 11. 

    The working drawing for a project show lateral bracing of the suspended ceiling for earthquake resistance. Although the architect did not inspect the ceiling construction before it was covered up, he suspects that the lateral bracing was not properly installed. The building inspector has not noted any violations. What should the architect do?

    • Nothing, because no violations have been noted by the inspector, and the architect has no evidence that the construction is not in conformance with the contract documents

    • Prepare a change order requiring the contractor to uncover the ceiling for the architect's inspection

    • Request the contractor to uncover the ceiling for the architect's inspection

    • Ask the owner to direct the contractor to uncover the ceiling, because the architect lacks such authority himself.

    Correct Answer
    A. Request the contractor to uncover the ceiling for the architect's inspection
    Explanation
    The architect should request the contractor to uncover the ceiling for inspection because they suspect that the lateral bracing was not properly installed. Even though the building inspector has not noted any violations, the architect has concerns about the construction. By requesting the contractor to uncover the ceiling, the architect can personally inspect the installation and ensure that it complies with the contract documents. This proactive approach allows the architect to address any potential issues before they become a problem.

    Rate this question:

  • 12. 

    The phrase "Sick Building Syndrome" is used primarily to describe poor indoor air quality (IAQ). This phenomenon can result fromI. inadequate ventilationII. off-gassing from fabrics and coatingIII. tabacoo smokeIV. wind

    • I and II

    • II and III

    • I and IV

    • I, II and III

    Correct Answer
    A. I, II and III
    Explanation
    The correct answer is I, II and III. The phrase "Sick Building Syndrome" refers to poor indoor air quality, which can be caused by inadequate ventilation, off-gassing from fabrics and coatings, and tobacco smoke. Wind, on the other hand, is not mentioned as a cause of Sick Building Syndrome in the given information.

    Rate this question:

  • 13. 

    Sustainable design projects seeking LEED certification require more stringent architectural supervision. Which of the following tasks would most likely require the GREATEST additional attention to ensure that original design standards are met?

    • Review of product substitutions

    • Processing Application for payment

    • Review of Shop Drawings

    • Preparation of a punchlist

    Correct Answer
    A. Review of product substitutions
    Explanation
    The review of product substitutions would most likely require the greatest additional attention to ensure that original design standards are met in sustainable design projects seeking LEED certification. This is because product substitutions can have a significant impact on the overall sustainability and environmental performance of a project. It is important to carefully review and assess any proposed substitutions to ensure that they meet the required standards and do not compromise the sustainability goals of the project.

    Rate this question:

  • 14. 

    The owners of a new office building have indicated they wish to have their building LEED certified. What effect might this decision have on the cost of design services?

    • The architect's fees will increase, but those consultants will remain the same

    • The architect's fees will remain the same, but the those of consultants will increase

    • Both the architect's and consultant's fess will increase

    • There will be no change in the cost of design services

    Correct Answer
    A. Both the architect's and consultant's fess will increase
    Explanation
    By seeking LEED certification for their building, the owners are indicating their commitment to sustainable and environmentally friendly design. Achieving LEED certification requires additional expertise and knowledge in green building practices, which may result in increased fees for both the architect and the consultants involved in the project. This is because they will need to invest more time and resources to meet the specific requirements and standards set by LEED. Therefore, both the architect's and consultant's fees are likely to increase as a result of this decision.

    Rate this question:

  • 15. 

    During the schematic design phase, the architect determines that the budget for a project is inadequate. What is his best course of action?

    • Reduce the quality of the building's materials and systems

    • Reduce the scope of the project

    • Notify the owner and lender and temporarily suspend work on the project until they reach a decision

    • Review the program with the owner to determine where cost savings should be made

    Correct Answer
    A. Review the program with the owner to determine where cost savings should be made
    Explanation
    During the schematic design phase, if the architect determines that the budget for a project is inadequate, their best course of action is to review the program with the owner to determine where cost savings should be made. This means that the architect should collaborate with the owner to identify areas where expenses can be reduced without compromising the overall quality or scope of the project. By doing so, they can find alternative solutions and make adjustments to ensure that the project can be completed within the available budget.

    Rate this question:

  • 16. 

    Which of the following components of life-cycle costs for a building are NOT within the architect's direct control?

    • Operational costs

    • Taxes and financing

    • Maintenance costs

    • Replacement costs

    Correct Answer
    A. Taxes and financing
    Explanation
    The architect is responsible for designing and planning the building, but they do not have direct control over taxes and financing. Taxes and financing are determined by external factors such as government regulations, market conditions, and the client's financial resources. The architect's role is to provide cost estimates and recommendations, but the final decision on taxes and financing is made by the client or other stakeholders involved in the project.

    Rate this question:

  • 17. 

    Which of the following are part of the contract documents? Check all that apply.

    • Specifications

    • Drawings

    • Addenda

    • Shop drawings

    Correct Answer(s)
    A. Specifications
    A. Drawings
    A. Addenda
    Explanation
    The contract documents typically include specifications, drawings, and addenda. Specifications outline the technical requirements and materials to be used in the project. Drawings provide visual representations of the project design and layout. Addenda are additional documents that modify or clarify the original contract documents. Shop drawings, on the other hand, are not typically part of the contract documents as they are detailed drawings produced by contractors, subcontractors, or suppliers to illustrate how specific components or systems will be fabricated or installed.

    Rate this question:

  • 18. 

    When should money retained by the owner be paid to the contractor?

    • At final completion

    • At substantial completion

    • When the architect determines that retainage is no longer need for the owner's protection

    • As called for in the owner-contractor agreement and if the contractor's surety consents

    Correct Answer
    A. As called for in the owner-contractor agreement and if the contractor's surety consents
    Explanation
    The correct answer is "As called for in the owner-contractor agreement and if the contractor's surety consents." This means that the payment of money retained by the owner should be made according to the terms specified in the agreement between the owner and the contractor. Additionally, the consent of the contractor's surety is required for the payment to be made. This ensures that all necessary conditions and agreements are met before the money is released to the contractor.

    Rate this question:

  • 19. 

    The specifications for a project call for the use of copper wire, and an escalation clause provides that any increase in the price of copper is to be passed onto the owner. The contractor informs the architect and owner that there has been a large increase in the price of copper since the contract date, and he proposes to use aluminum wire instead of copper. What action should the architect take?

    • Permit the substitution of aluminum wire if it has equal or greater current capacity and voltage drop, with any cost saving to be credited to the owner

    • Permit the substitution of aluminum wire if it has equal or greater current carrying capacity and equal or less voltage drop, with any cost saving to be credited to the owner

    • Require the contractor to install the specified copper wire regardless of the cost of copper

    • Confirm that the aluminum wire has equal or greater current carrying capacity and equal or less voltage drop, then prepare a change order reflecting any change in contract sum to the owner for approval

    Correct Answer
    A. Confirm that the aluminum wire has equal or greater current carrying capacity and equal or less voltage drop, then prepare a change order reflecting any change in contract sum to the owner for approval
    Explanation
    The architect should confirm that the aluminum wire meets the required specifications by checking if it has equal or greater current carrying capacity and equal or less voltage drop. If it does, the architect should then prepare a change order reflecting any change in the contract sum and submit it to the owner for approval. This ensures that any cost saving resulting from the substitution of aluminum wire is credited to the owner.

    Rate this question:

  • 20. 

    Six months after completion and acceptance of a building, leakage during a rainstorm causes staining of the ceiling. It is determines that the flashing was not installed in accordance with the drawings and specifications. What should the owner do?

    • Ask the subcontractor who installed the flashing to correct the work at no cost to the owner

    • Ask the general contractor to correct the work at no cost to the owner

    • Hire a new contractor to remedy the situation and charge the owner

    • Hire a new contractor to remedy the situation and charge the original contractor's insurance company

    Correct Answer
    A. Ask the general contractor to correct the work at no cost to the owner
    Explanation
    The owner should ask the general contractor to correct the work at no cost to the owner because the general contractor is responsible for ensuring that the building is constructed according to the drawings and specifications. Since the flashing was not installed correctly, it is the general contractor's responsibility to fix the issue without any additional cost to the owner.

    Rate this question:

  • 21. 

    During construction of a corporate headquarters building for an insurance company, two of the company's department merge, necessitating a change in the floor plans and related drawings. Which of the following is the best procedures for the architect to follow to effect this change?

    • Issue a construction change directive if the change in the work, the contract sum, and the contract time are agreed to by the owner, contractor and architect

    • Issue a field order signed by the owner, contractor and architect

    • Issue a change order if the change in the work, the contract sum, and the contract time are agreed to by the owner, architect, and contractor

    • Order the contractor to proceed with the change and negotiate any adjustment in the contract sum or contract time later

    Correct Answer
    A. Issue a change order if the change in the work, the contract sum, and the contract time are agreed to by the owner, architect, and contractor
    Explanation
    The best procedure for the architect to follow in this situation is to issue a change order if the change in the work, the contract sum, and the contract time are agreed to by the owner, architect, and contractor. This ensures that all parties involved are in agreement and that the necessary adjustments to the plans and drawings are documented and authorized. It also helps to maintain transparency and accountability throughout the construction process.

    Rate this question:

  • 22. 

    Prior to the placing of concrete for footings, you observe that the footing excavation is frozen. What is the best procedures to follow?

    • Place the concrete on the frozen ground

    • Provide a temporary heated enclosure for the excavation and then place the concrete

    • Thaw the frozen ground by steaming

    • Excavate the frozen ground and place the concrete against earth which is not frozen

    Correct Answer
    A. Excavate the frozen ground and place the concrete against earth which is not frozen
  • 23. 

    The standard AIA Owner-Architect agreement (B141) requires which party to interpret the drawings and specifications and make decisions on matters in question between the owner and contractor?

    • Owner's Representative

    • Mediator

    • Arbitrator

    • Architect

    Correct Answer
    A. Architect
    Explanation
    The correct answer is Architect. According to the standard AIA Owner-Architect agreement (B141), the architect is responsible for interpreting the drawings and specifications and making decisions on matters in question between the owner and contractor. The architect acts as a liaison between the two parties, ensuring that the project is executed according to the agreed-upon plans and specifications. They play a crucial role in resolving any disputes or issues that may arise during the construction process.

    Rate this question:

  • 24. 

    The instrument by which one relinquishes a lien right against the property of another is called a

    • Mechanic's Liens

    • Release of Lien

    • Lien affidavit

    • Statutory Lien

    Correct Answer
    A. Release of Lien
    Explanation
    A release of lien is the instrument used to relinquish a lien right against someone else's property. This document is typically filed by the party who placed the lien to formally acknowledge that the debt or obligation has been satisfied and that the lien is no longer valid. It serves as proof that the lien has been released and allows the property owner to clear the title and sell or transfer the property without any encumbrances.

    Rate this question:

  • 25. 

    A contractor submits the low bid on a project, which is accepted by the owner. However, the contractor refuses to sign the owner-contractor agreement until the owner provides reasonable evidence to the contractor that financial arrangement have been made to fulfill the owner's obligations under the contract. In this situation, what would be the most appropriate response by the owner?

    • Provide the evidence requested by the contractor

    • Refuse the contractor's request, because financial information of this kind is confidential

    • Arrange for the surety that issued the performance bond to perform the work

    • Notify the issuer of the bid bond, who is liable for any extra costs incurred by the owner to enter into a contract with a different contractor

    Correct Answer
    A. Provide the evidence requested by the contractor
    Explanation
    The most appropriate response by the owner would be to provide the evidence requested by the contractor. This is because the contractor is asking for reasonable evidence that financial arrangements have been made to fulfill the owner's obligations under the contract. By providing this evidence, the owner can assure the contractor that they are capable of fulfilling their obligations and can proceed with signing the owner-contractor agreement.

    Rate this question:

  • 26. 

    Six months after completion of a project, the owner notifies the architect that the cooling cycle of the air conditioning system unable to cope with the heat gain in the building, resulting in temperatures above the comfort zone. Upon careful investigation, the architect's mechanical engineering consultant determines that the mechanical subcontractor did not install the air handling units in accordance withe drawings and specifications. Which is the most likely course of action the architect would follow?

    • Advise the owner to submit a written notice to the general contractor asking him to make the necessary correction to the work

    • Try to work with his consultant to find a means to modify the system in order to provide the necessary cooling

    • Sue the mechanical engineering consultant for lack of supervision on the job

    • Recommend that the owner seek the funds from the general contractor to make the necessary changes to the system

    Correct Answer
    A. Advise the owner to submit a written notice to the general contractor asking him to make the necessary correction to the work
    Explanation
    The most likely course of action the architect would follow is to advise the owner to submit a written notice to the general contractor asking him to make the necessary correction to the work. This is because the issue with the air conditioning system is a result of the mechanical subcontractor not following the drawings and specifications. By notifying the general contractor, the architect can ensure that the responsible party is made aware of the problem and can take the necessary steps to rectify the situation.

    Rate this question:

  • 27. 

    During the course of construction, temporary framework erected by the contractor collapses, injuring a workman. The injured workman files suit against the architect, claiming that the architect was negligent in supervising the work, since he did not notice or call attention to the faulty forms. Which of the following is the most correct statement concerning this situation?

    • The suit will be dismissed, because no contractual arrangement exists between the architect and the workman

    • Whether or not the suit has merit, the architect's professional liability insurance company will defend the architect, thus avoiding any out of pocket expense to him

    • The claim of the injured worker will be paid by the contractor's worker's compensation insurance, rather than the architect's professional liablities insurance

    • Although the General conditions place responsibility for construction methods on the contractor and not the architect, the architect is not automatically absolved of negligence and he must still defend himself against the suit

    Correct Answer
    A. Although the General conditions place responsibility for construction methods on the contractor and not the architect, the architect is not automatically absolved of negligence and he must still defend himself against the suit
    Explanation
    The correct answer is that although the General conditions place responsibility for construction methods on the contractor and not the architect, the architect is not automatically absolved of negligence and he must still defend himself against the suit. This means that even though the architect may not be directly responsible for the construction methods, they can still be held liable for negligence if they failed to supervise the work properly. The architect will have to defend themselves in court against the claim made by the injured worker.

    Rate this question:

  • 28. 

    Mechanic's Liens (liens laws) exist by statute in each state to

    • Provide security for payment for labor supplied to construct the building

    • Provide security for payment for material supplied to construct the building

    • Provide security for payment for labor and materials supplied to construct the building

    • Insurance vehicle operators on job sites

    Correct Answer
    A. Provide security for payment for labor and materials supplied to construct the building
    Explanation
    Mechanic's liens exist to provide security for payment for both labor and materials supplied to construct a building. These liens are created by statute in each state and serve as a legal claim against the property in question. By allowing contractors, subcontractors, and suppliers to place a lien on the property, they have a way to ensure they will be paid for their work and materials. This provides a level of financial protection and security for those involved in the construction process.

    Rate this question:

  • 29. 

    Which of the following architectural services is considered additional services?I. Services in connection with change orders and construction change directives, if required by circumstances beyond the architect's controlII. Submitting a preliminary estimates of construction cost to the ownerIII. Assisting the owner in the preparation of the bidding forms, the conditions of the contract, and the form of agreement between owner and contractorIV. Providing administration of the construction contract

    • I and IV

    • II and III

    • I and III

    • I Only

    Correct Answer
    A. I Only
    Explanation
    Services in connection with change orders and construction change directives, if required by circumstances beyond the architect's control, are considered additional services. This means that if there are unforeseen circumstances that require changes to the original plans or specifications, the architect may need to provide additional services to accommodate these changes. This could include revising drawings, coordinating with contractors, and ensuring that the changes are implemented correctly. However, submitting a preliminary estimate of construction cost to the owner, assisting the owner in the preparation of bidding forms, conditions of the contract, and form of agreement between owner and contractor, and providing administration of the construction contract are all considered part of the architect's basic services and not additional services.

    Rate this question:

  • 30. 

    Which of the following statement about substantial completion is INCORRECT?

    • It is contractor's responsibility to consider when a project is substantaily complete

    • When a project is considered substantially complete, the contractor prepares the punchlist of items to be completed and corrected.

    • If items are not included on the punchlist, the contractor is still required to comply with the contract documents

    • The contractor is entitled to final payment when the project is substantially complete

    Correct Answer
    A. The contractor is entitled to final payment when the project is substantially complete
    Explanation
    The contractor is not entitled to final payment when the project is substantially complete. Final payment is typically made after the punchlist items have been completed and corrected.

    Rate this question:

  • 31. 

    What AIA document contains contractual provisions that define the relationship between the owner, contractor, and the architects?

    • General condition

    • Bid form

    • Special condition

    • Supplementary Condition

    Correct Answer
    A. General condition
    Explanation
    The correct answer is General condition. General conditions are a part of the AIA (American Institute of Architects) document that contains contractual provisions defining the relationship between the owner, contractor, and architects. These provisions outline the responsibilities, rights, and obligations of each party involved in a construction project. They cover various aspects such as payment terms, project schedule, dispute resolution procedures, and insurance requirements. General conditions help ensure that all parties are aware of their roles and responsibilities, promoting a smooth and efficient project execution.

    Rate this question:

  • 32. 

    According to AIA Standard form of agreement (B-141), which party owns the construction documents?

    • Owner

    • Architect

    • Contractor

    • Building Department

    Correct Answer
    A. Architect
    Explanation
    According to the AIA Standard form of agreement (B-141), the architect owns the construction documents. This means that the architect retains ownership and control over the drawings, specifications, and other documents that are created during the design and construction process. This allows the architect to protect their intellectual property and ensures that they have control over any modifications or changes made to the documents. The architect may also use these documents for future reference or for other projects.

    Rate this question:

  • 33. 

    Soil characteristics and bearing capacities are usually determined by which of the following?

    • Architect

    • Structural engineer

    • Geo technical Engineer

    • Owner

    Correct Answer
    A. Geo technical Engineer
    Explanation
    A geotechnical engineer is responsible for determining soil characteristics and bearing capacities. They study the properties of soil and rock, assess their stability, and provide recommendations for construction projects. This involves conducting tests and analyzing data to understand the behavior of the soil under different conditions. Architects focus more on the design and aesthetics of the structure, while structural engineers deal with the overall integrity and strength of the building. The owner may have input on the project, but the geotechnical engineer is the one with the expertise to assess the soil and determine its suitability for construction.

    Rate this question:

  • 34. 

    Statements or drawings which modify the basic contract documents after they have been issued to the bidders, but prior to taking of bids, are known as 

    Correct Answer
    Addenda
    Addendum
    Explanation
    Addenda and Addendum are both correct answers to the question. These terms refer to statements or drawings that modify the basic contract documents after they have been issued to the bidders but before the bids are taken. Addenda is the plural form of Addendum, so both terms can be used interchangeably in this context.

    Rate this question:

  • 35. 

    The contractor is entitled to payment of the entire contract sum upon 

    Correct Answer
    Final Completion
    Explanation
    Upon Final Completion of a construction project, the contractor is entitled to payment of the entire contract sum. This means that all work outlined in the contract has been completed, inspected, and approved by the client or relevant authorities. Final Completion signifies the successful conclusion of the project, including any necessary documentation, warranties, and handover of the finished product. At this point, the contractor has fulfilled their obligations and is eligible to receive the full payment as agreed upon in the contract.

    Rate this question:

  • 36. 

    An elevation symbol indicated on a grading plan and identifying the proposed elevation at a single location is called a

    Correct Answer
    Spot Elevation
    Explanation
    A spot elevation is a symbol on a grading plan that represents the proposed elevation at a specific location. It is used to indicate the height or level of a particular point on the site. Spot elevations are commonly used in construction and engineering to provide precise measurements and ensure accurate grading and leveling of the land.

    Rate this question:

  • 37. 

    The provisions that describes the rights, responsibilities, and relations of the parties to the construction contract are called the 

    • Standard conditions

    • General conditions

    • Special Conditions

    • Supplementary Conditions

    Correct Answer
    A. General conditions
    Explanation
    General conditions are provisions that describe the rights, responsibilities, and relations of the parties involved in a construction contract. These conditions are typically standard and apply to all construction contracts. They cover various aspects such as project scope, payment terms, insurance requirements, dispute resolution procedures, and termination clauses. General conditions provide a framework for the project and help ensure that both parties are aware of their obligations and rights throughout the construction process.

    Rate this question:

  • 38. 

    An open proprietary specification allows the substitution of approved equal products for those specified. In the regard, which of the following statements is correct?

    • The product must be identical to the one specified

    • The product must match the quality and performance of the one specified, as determined by the architect

    • The product must be one of the products named in the specifications.

    • Open proprietary specifications are not usually permitted on publicly-funds projects

    Correct Answer
    A. The product must match the quality and performance of the one specified, as determined by the architect
    Explanation
    An open proprietary specification allows for the substitution of approved equal products, meaning that the product does not have to be identical to the one specified. However, it must still meet the same quality and performance standards as the specified product, as determined by the architect. This allows for flexibility in product selection while ensuring that the overall quality and performance requirements are met.

    Rate this question:

  • 39. 

    Which of the following documents are contained in a typical project manual?I. The bid formII. The instruction to biddersIII. The general conditionsIV. The specificationsV. The working drawings

    • I, II and III

    • III & IV

    • I, II, III & IV

    • I, II, IV, and V

    Correct Answer
    A. I, II, III & IV
    Explanation
    A typical project manual in construction projects usually includes the bid form, instruction to bidders, general conditions, and specifications. The bid form is used by contractors to submit their pricing information. The instruction to bidders provides guidelines and requirements for the bidding process. The general conditions outline the legal and administrative aspects of the project. The specifications detail the technical requirements and standards for the project. Therefore, the correct answer is I, II, III & IV.

    Rate this question:

  • 40. 

    While construction drawings define physical relationships between materials and building systems, specifications define all of the following EXCEPT

    • Quality

    • Methods

    • Dimensions

    • Installation techniques

    Correct Answer
    A. Dimensions
    Explanation
    Specifications define all aspects of a construction project, including quality, methods, installation techniques, and other details. However, dimensions are not typically included in specifications. Instead, dimensions are usually provided in construction drawings, which show the physical relationships between materials and building systems. Therefore, the correct answer is dimensions.

    Rate this question:

  • 41. 

    Which party is responsible for determining whether a completed assembly meets the design intent of the contract documents?

    • Contractor

    • Building Department

    • Architect

    • Owner

    Correct Answer
    A. Architect
    Explanation
    The architect is responsible for determining whether a completed assembly meets the design intent of the contract documents. As the professional who designs the project and oversees its construction, the architect has the expertise and knowledge to assess whether the assembly aligns with the specifications and requirements outlined in the contract documents. They play a crucial role in ensuring that the final product matches the intended design and meets the expectations set forth in the contract.

    Rate this question:

  • 42. 

    In striving to prepare construction documents which are as complete and clear as possible, the best practices is to

    • Show complete information in all details

    • Show complete information in one location and provide references to that location throughout the drawings

    • Draw no details but refer to manufacturer's product data

    • Do none of the above

    Correct Answer
    A. Show complete information in one location and provide references to that location throughout the drawings
    Explanation
    The best practice in preparing construction documents is to show complete information in one location and provide references to that location throughout the drawings. This ensures that all necessary information is included in a clear and organized manner, making it easier for contractors and other stakeholders to understand the project requirements. By providing references, it allows for efficient navigation and reduces the risk of missing important details. This approach promotes clarity and completeness in the construction documents, enhancing the overall quality of the project.

    Rate this question:

  • 43. 

    Which of the following may affect the cost of construction?I. Legal and administrative requirementsII. Complexity of the projectIII. Construction materials and methodsIV. Location of the projectV. Construction Schedule

    • II, III, and IV

    • I, II, and V

    • I, II, III, and IV

    • All of the above

    Correct Answer
    A. All of the above
    Explanation
    Legal and administrative requirements can affect the cost of construction as they may involve additional permits, inspections, and compliance measures that can increase expenses. The complexity of the project can also impact costs, as more intricate designs or unique features may require specialized skills or materials. The choice of construction materials and methods can significantly affect costs, as certain materials may be more expensive or require additional labor. The location of the project can also impact costs, as factors such as accessibility, availability of resources, and local regulations can vary from place to place. Finally, the construction schedule can affect costs, as delays or expedited timelines may require additional resources or incur additional expenses.

    Rate this question:

  • 44. 

    Which of the following construction items is Most likely to be shop fabricated?

    • Light fixtures

    • HVAC ductwork

    • Plumbing fixtures

    • Concrete

    Correct Answer
    A. HVAC ductwork
    Explanation
    HVAC ductwork is most likely to be shop fabricated because it involves the manufacturing and assembly of ducts in a controlled environment, such as a factory or workshop. This allows for precise measurements, quality control, and efficient production. On the other hand, light fixtures, plumbing fixtures, and concrete are typically installed on-site and may require custom fitting or pouring, making them less likely to be shop fabricated.

    Rate this question:

  • 45. 

    Halfway through construction of a shopping mall, the contractor removes his workers from the project and refuses to continue work because of financial problems. Which of the following guarantees that the work will be completed?

    • Labor and Material payment bond

    • Bid Bond

    • Liquidated Damages clause

    • Performance Bond

    Correct Answer
    A. Performance Bond
    Explanation
    A performance bond is a type of guarantee that ensures the completion of a project. In this scenario, the contractor's financial problems have caused them to halt the work. However, if a performance bond is in place, it means that another party (usually a bonding company) has agreed to step in and complete the project if the original contractor fails to do so. This bond provides assurance to the project owner that the work will be completed, even if the original contractor is unable to fulfill their obligations.

    Rate this question:

  • 46. 

    Within seven days after receipt of the contractor's application for payment, the architect must do which of the following?I. Issue a certificate for payment to the ownerII. Notify the contractor and owner of the architect's reasons for withholding a certificate for paymentIII. Prepare a schedule of valueIV. Notify the surety that the architect has received an application for payment

    • I and IV

    • I or II

    • III & IV

    • I, III and IV

    Correct Answer
    A. I or II
    Explanation
    The correct answer is I or II. This means that within seven days after receiving the contractor's application for payment, the architect must either issue a certificate for payment to the owner or notify the contractor and owner of the architect's reasons for withholding a certificate for payment. This allows for flexibility depending on the circumstances and the architect's evaluation of the payment application.

    Rate this question:

  • 47. 

    A bidder on a project proposes to substitute a different roofing system than the one specified. He claims that the substitute roofing is equal to the specified roofing, but less expensive. In this regard, which of the following statement is correct?I. The bidder proposing the substitution must submit technical documentation to the architect for review and evaluation. II. The architect may notify all bidders orally if the substitution is acceptableIII. The bidder may base his bid on the substitute roofing, but must guarantee its performanceIV. If the substitution is acceptable, an addendum is issued to all bidders by the architect

    • I and IV

    • I and II

    • I and III

    • IV only

    Correct Answer
    A. I and IV
    Explanation
    The correct answer is I and IV. The bidder proposing the substitution must submit technical documentation to the architect for review and evaluation. This is necessary to ensure that the substitute roofing system is indeed equal to the specified roofing system. If the substitution is deemed acceptable, an addendum is issued to all bidders by the architect, informing them of the approved substitution. This ensures that all bidders are aware of the change and can adjust their bids accordingly.

    Rate this question:

  • 48. 

    A change order may include all of the following EXCEPT 

    • Time extension

    • Labor costs

    • Material costs

    • Design and engineering fees

    Correct Answer
    A. Design and engineering fees
    Explanation
    A change order is a document that outlines any modifications or additions to the original scope of work in a construction project. It typically includes adjustments to time, labor costs, and material costs to accommodate the changes. However, design and engineering fees are not typically included in a change order as they are separate costs that are usually agreed upon and paid for separately.

    Rate this question:

  • 49. 

    The owner generally maintains all of the following types of insurance, EXCEPT

    • All-risk insurance

    • Property insurance

    • Worker's compensation insurance

    • Loss of use insurance

    Correct Answer
    A. Worker's compensation insurance
    Explanation
    The owner generally maintains all of the mentioned types of insurance except for worker's compensation insurance. Worker's compensation insurance is typically obtained by employers to provide coverage for medical expenses and lost wages for employees who are injured or become ill on the job. While the owner may have other types of insurance to protect their property, assets, and business operations, worker's compensation insurance specifically applies to employees and is not applicable to the owner themselves.

    Rate this question:

Quiz Review Timeline (Updated): Jul 22, 2023 +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Jul 22, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Feb 28, 2015
    Quiz Created by
    Jimc5408
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.