Test Strategizing & Test Planning

Approved & Edited by ProProfs Editorial Team
The editorial team at ProProfs Quizzes consists of a select group of subject experts, trivia writers, and quiz masters who have authored over 10,000 quizzes taken by more than 100 million users. This team includes our in-house seasoned quiz moderators and subject matter experts. Our editorial experts, spread across the world, are rigorously trained using our comprehensive guidelines to ensure that you receive the highest quality quizzes.
Learn about Our Editorial Process
| By Catherine Halcomb
C
Catherine Halcomb
Community Contributor
Quizzes Created: 1428 | Total Attempts: 5,897,934
Questions: 30 | Attempts: 5,461

SettingsSettingsSettings
Test Strategizing & Test Planning - Quiz

Mock3


Questions and Answers
  • 1. 

    What type of testing is included in scope of test strategy? a) Manual b) automation c) performance d) integration

    • A.

      All the above

    • B.

      A & b

    • C.

      B & c

    • D.

      A&b&c

    Correct Answer
    D. A&b&c
    Explanation
    The correct answer is a&b&c, which means that manual, automation, and performance testing are all included in the scope of the test strategy. This implies that the test strategy includes a combination of manual testing, where testing is done manually by human testers, automation testing, where testing is done using automated tools and scripts, and performance testing, where the performance and scalability of the system are tested. This comprehensive approach ensures that all aspects of testing are covered in the test strategy.

    Rate this question:

  • 2. 

    The test cases are signed off by whom?

    • A.

      Tam lead

    • B.

      Developer

    • C.

      Business Analyst

    • D.

      Project manager

    Correct Answer
    C. Business Analyst
    Explanation
    The test cases are signed off by the Business Analyst. The Business Analyst is responsible for ensuring that the test cases are accurate and meet the requirements of the project. They review and approve the test cases before they are executed to ensure that they cover all necessary scenarios and that the system functions as expected. The Business Analyst also works closely with the project manager and other stakeholders to ensure that the test cases align with the overall project goals and objectives.

    Rate this question:

  • 3. 

    Performance testing will be carried out only after ?

    • A.

      Stress testing

    • B.

      Integration testing

    • C.

      System testing

    • D.

      Component testing

    Correct Answer
    C. System testing
    Explanation
    Performance testing is typically conducted after system testing. System testing ensures that the entire system is functioning correctly and all components are working together as expected. Once the system has been validated through system testing, performance testing can be carried out to measure and evaluate the system's performance under various loads and conditions. This allows for the identification of any performance issues or bottlenecks that may need to be addressed before the system is deployed.

    Rate this question:

  • 4. 

     4. Defect management methodology contains___________ a) definition of a defect b) definition of severity and priority of a defect c) defect life cycle

    • A.

      I)a&b

    • B.

      A&c

    • C.

      B&c

    • D.

      All the above

    Correct Answer
    D. All the above
    Explanation
    The correct answer is "all the above." Defect management methodology includes the definition of a defect, the definition of severity and priority of a defect, and the defect life cycle. This means that all of the given options (a, b, and c) are included in the defect management methodology.

    Rate this question:

  • 5. 

     5. Based on _______ and _________ schedule is planned.

    • A.

      A) resource planning and activities

    • B.

      B) effort estimation and resource planning

    • C.

      C) environment set and database

    • D.

      D)activities and testcase

    Correct Answer
    B. B) effort estimation and resource planning
    Explanation
    Effort estimation and resource planning are crucial factors in determining the schedule for a project. Effort estimation involves estimating the amount of time and resources required to complete each task or activity. Resource planning involves identifying and allocating the necessary resources, such as manpower, equipment, and materials, to carry out the project. By considering both effort estimation and resource planning, a realistic and achievable schedule can be developed, ensuring that the project is completed on time and within budget.

    Rate this question:

  • 6. 

     6.RACI means ______________________

    • A.

      A) responsible, activities, consulted, information chart

    • B.

      B) report, accountable, count, interface chart

    • C.

      C) responsible, accountable, consulted, informed chart

    • D.

      D) none

    Correct Answer
    C. C) responsible, accountable, consulted, informed chart
    Explanation
    RACI stands for responsible, accountable, consulted, informed chart. This chart is a project management tool that helps clarify roles and responsibilities within a team or organization. The RACI chart identifies who is responsible for completing specific tasks (responsible), who is ultimately answerable for the outcome (accountable), who needs to be consulted for input (consulted), and who needs to be kept informed of progress (informed). This chart helps ensure that everyone understands their roles and promotes effective communication and collaboration within the team.

    Rate this question:

  • 7. 

     7.A plan to overcome the risk called as

    • A.

      A) migration plan

    • B.

      B) master plan

    • C.

      C) maintenance plan

    • D.

      D) mitigation plan

    Correct Answer
    D. D) mitigation plan
    Explanation
    A plan to overcome the risk is called a mitigation plan. This plan outlines strategies and actions to reduce or eliminate the potential negative impact of risks. It involves identifying potential risks, assessing their likelihood and potential impact, and implementing measures to minimize their effects. The goal of a mitigation plan is to proactively address risks and prevent or minimize their impact on a project or organization.

    Rate this question:

  • 8. 

     8.What are the key factors to be understood before Test strategy

    • A.

      Development methodology

    • B.

      Implementation methodology

    • C.

      Infrastructural availability

    • D.

      All the above

    Correct Answer
    D. All the above
    Explanation
    Before creating a test strategy, it is important to understand the development methodology being used for the project. This will help in determining the testing approach and techniques that are suitable for the project. Similarly, understanding the implementation methodology will provide insights into the deployment process and how it may impact testing. Lastly, considering the availability of infrastructure is crucial as it affects the test environment setup and execution. Therefore, all these factors need to be understood before formulating a test strategy.

    Rate this question:

  • 9. 

     9.strategy and Planning can be ________ by tester

    • A.

      Prepared

    • B.

      Viewed

    • C.

      Edited

    • D.

      None of the above

    Correct Answer
    B. Viewed
    Explanation
    The correct answer is "Viewed". Strategy and planning can be viewed by a tester. This suggests that testers have the ability to access and review the strategy and planning documents, which can help them understand the overall goals and objectives of the project. This knowledge can then be used to inform their testing approach and ensure that their testing efforts align with the overall strategy of the project.

    Rate this question:

  • 10. 

     10. Out of Scope include A.not be tested by the testing team B.due to other stakeholders taking responsibility C.due to request from customer during estimation D.None of the above

    • A.

      Only (I)

    • B.

      Both (I) and (III)

    • C.

      Both (II) and (III)

    • D.

      All (I),(II) and (III)

    Correct Answer
    D. All (I),(II) and (III)
    Explanation
    The correct answer is All (I), (II), and (III). This means that all of the options mentioned in the question are examples of situations that would be considered out of scope. Option (I) states that if a task cannot be tested by the testing team, it is out of scope. Option (II) states that if other stakeholders take responsibility for a task, it is out of scope. Option (III) states that if a customer requests a change during estimation, it is out of scope. Therefore, all three options are valid examples of out of scope situations.

    Rate this question:

  • 11. 

     11.What are the inputs for Test Planning

    • A.

      Req. Documents

    • B.

      Test Strategy

    • C.

      Both (a) and (b)

    • D.

      None of the Above

    Correct Answer
    C. Both (a) and (b)
    Explanation
    The inputs for Test Planning are both Requirement Documents and Test Strategy. Requirement Documents provide information about the project requirements, while Test Strategy outlines the approach and scope of testing. Both these inputs are essential for effective test planning as they provide the necessary information and guidelines to create a comprehensive test plan.

    Rate this question:

  • 12. 

     12. select the odd one/

    • A.

      A. Nature of the application

    • B.

      B. External interface of the application

    • C.

      C. Application/system needs to be understand

    • D.

      D.assumptions and dependencies

    Correct Answer
    D. D.assumptions and dependencies
    Explanation
    The options a, b, and c are all related to the application itself and its characteristics, while option d stands out as it refers to external factors that can affect the application. Assumptions and dependencies are factors that are outside the control of the application and can impact its functionality. Therefore, d. assumptions and dependencies is the odd one out as it is not directly related to the nature, interface, or understanding of the application.

    Rate this question:

  • 13. 

     13. As part of which test process do you determine the exit criteria?

    • A.

      A. Test planning.

    • B.

      B. Evaluating exit criteria and reporting.

    • C.

      C. Test closure.

    • D.

      D. Test control

    Correct Answer
    A. A. Test planning.
    Explanation
    In the test planning process, one of the important tasks is to determine the exit criteria. Exit criteria are the conditions or requirements that must be met in order to consider the testing process complete and to exit the current phase of testing. This includes factors such as test coverage, test case execution, defect resolution, and overall quality goals. By determining the exit criteria during the test planning phase, the testing team can have a clear understanding of when they have achieved the desired level of quality and can move on to the next phase or release the product.

    Rate this question:

  • 14. 

     14. Which activities form part of test planning? i) Developing test cases. ii) Defining the overall approach to testing. iii) Assigning resources. iv) Building the test environment v) Writing test conditions.

    • A.

      A. i, ii & iv are true, iii & v are false.

    • B.

      B. ii & iii are true, i, iv & v are false.

    • C.

      C. iv & v are true, i, ii & iii are false.

    • D.

      D. i, ii & iii are true iv & v are false

    Correct Answer
    B. B. ii & iii are true, i, iv & v are false.
    Explanation
    The correct answer is B. ii & iii are true, i, iv & v are false. This is because test planning involves defining the overall approach to testing and assigning resources, but it does not involve developing test cases, building the test environment, or writing test conditions.

    Rate this question:

  • 15. 

     15. A project that is in the implementation phase is six weeks behind schedule. —The delivery date for the product is four months away. The project is not allowed to slip —the delivery date or compromise on the quality standards established for his product. Which —of the following actions would bring this project back on schedule?

    • A.

      A. Eliminate some of the requirements that have not yet been implemented.

    • B.

      B. Add more engineers to the project to make up for lost work.

    • C.

      C. Ask the current developers to work overtime until the lost work is recovered.

    • D.

      D. Hire more software quality assurance personnel

    Correct Answer
    A. A. Eliminate some of the requirements that have not yet been implemented.
    Explanation
    By eliminating some of the requirements that have not yet been implemented, the project can reduce the workload and catch up on the schedule. This action allows the project to prioritize essential requirements and focus on completing them within the given timeframe. Adding more engineers or asking the current developers to work overtime may not be feasible or effective in the short term, and hiring more software quality assurance personnel does not directly address the delay in the implementation phase.

    Rate this question:

  • 16. 

     16. Which of the following would NOT normally form part of a test plan?

    • A.

      A. Features to be tested

    • B.

      B. Incident reports

    • C.

      C. Risks

    • D.

      D. Schedule

    Correct Answer
    B. B. Incident reports
    Explanation
    Incident reports would not normally form part of a test plan because incident reports are typically used to document and track issues that occur during testing or production. They are not typically used to outline the scope or approach of the testing process, which is the main purpose of a test plan. The other options, such as features to be tested, risks, and schedule, are all components that are commonly included in a test plan.

    Rate this question:

  • 17. 

     20. Which of the following combinations correctly describes a valid approach tocomponent testing: i) Functional testing of the component in isolation. ii) Structure-based testing of the code without recording incidents. iii) Automated tests that are run until the component passes. iv) Functional testing of the interfaces between modules.

    • A.

      A. i and ii.

    • B.

      B. I, ii and iii

    • C.

      C. iii.

    • D.

      D. ii and iv

    Correct Answer
    B. B. I, ii and iii
    Explanation
    A valid approach to component testing includes functional testing of the component in isolation, structure-based testing of the code without recording incidents, and automated tests that are run until the component passes. This combination ensures that the component is tested for its functionality, code structure, and automated testing to ensure it meets the desired criteria.

    Rate this question:

  • 18. 

     18. True or False Small projects or regular release based project, both strategy and plan are not documented together

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    False. In small projects or regular release based projects, both the strategy and plan are documented together. This is because even though these projects may be smaller in scale, they still require a clear strategy and plan to ensure successful execution and achieve the desired outcomes. Documenting both the strategy and plan helps in aligning the team's efforts, setting clear objectives, and tracking progress throughout the project.

    Rate this question:

  • 19. 

    19. True or False For larger project test strategy and test plan could be documented seperately

    • A.

      True

    • B.

      False

    Correct Answer
    A. True
    Explanation
    For larger projects, it is recommended to document the test strategy and test plan separately. This is because a test strategy outlines the overall approach and objectives for testing, including the scope, test levels, and test types to be performed. On the other hand, a test plan provides detailed information on how testing will be carried out, including the specific activities, resources, schedules, and test cases to be executed. By documenting them separately, it allows for better organization, clarity, and easier communication among the project team members.

    Rate this question:

  • 20. 

     20. What is the purpose of exit criteria?

    • A.

      A. To define when a test level is complete.

    • B.

      B. To determine when a test has completed.

    • C.

      C. To identify when a software system should be retired.

    • D.

      D. To determine whether a test has passed.

    Correct Answer
    A. A. To define when a test level is complete.
    Explanation
    The purpose of exit criteria is to define when a test level is complete. Exit criteria are used to determine whether the objectives of a particular test level have been achieved and if it is appropriate to proceed to the next level or phase of testing. It helps in ensuring that all necessary activities and tasks have been completed and the testing process can be considered finished for that specific level.

    Rate this question:

  • 21. 

    21. Roles and responsibility of Developement lead?

    • A.

      A.clarification of desidn

    • B.

      B.test analyst

    • C.

      C.root cause analysis

    • D.

      D.participation in defect triage

    Correct Answer(s)
    A. A.clarification of desidn
    C. C.root cause analysis
    D. D.participation in defect triage
    Explanation
    The role of a Development Lead includes various responsibilities such as clarifying the design of a project, conducting root cause analysis to identify the underlying issues, and participating in defect triage to prioritize and resolve bugs. These tasks are crucial for ensuring the smooth development and delivery of a software project.

    Rate this question:

  • 22. 

    22. Testing related roles?

    • A.

      A.Test analyst

    • B.

      B.system suport engg

    • C.

      C.database admin

    • D.

      D.manager

    Correct Answer
    A. A.Test analyst
    Explanation
    Test analysts are responsible for planning, designing, and executing tests to ensure the quality and functionality of software systems. They analyze requirements, create test cases, conduct test executions, and report any defects found. Test analysts work closely with developers, project managers, and business analysts to ensure that the software meets the desired quality standards. They play a crucial role in identifying and resolving issues during the testing phase, ensuring that the final product is reliable and meets the user's expectations.

    Rate this question:

  • 23. 

    23. During the test planning, review of test strategy is done before test planning. [t or f]

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    During the test planning process, the review of test strategy is not done before test planning. Test strategy is typically reviewed and finalized before the test planning phase begins. Test strategy outlines the overall approach and objectives of the testing effort, while test planning involves creating a detailed plan that includes test objectives, scope, resources, and timelines. Therefore, the correct answer is False.

    Rate this question:

  • 24. 

    24. Is resource plaaning includes connectivity requirement, Os, testing tools? 

    • A.

      True

    • B.

      False

    Correct Answer
    A. True
    Explanation
    Resource planning includes considering the connectivity requirements, operating system, and testing tools needed for a project. This involves identifying the necessary hardware and software resources, as well as determining the network and connectivity requirements for the project. By including these factors in the resource planning process, organizations can ensure that they have the necessary resources in place to successfully execute the project.

    Rate this question:

  • 25. 

    Does testing governance include, hardware, software?

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    Testing governance does not include hardware and software. Testing governance refers to the processes and practices that ensure effective and efficient testing of software applications. It focuses on establishing policies, guidelines, and standards for testing activities, managing resources, and ensuring compliance with regulatory requirements. While hardware and software are essential components of testing, they are not directly included in testing governance.

    Rate this question:

  • 26. 

    26. Components of test planning?

    • A.

      A.testing schedule

    • B.

      B.test deliverables

    • C.

      C.run plan creation

    • D.

      D.roles & responsibility

    Correct Answer(s)
    A. A.testing schedule
    C. C.run plan creation
    D. D.roles & responsibility
    Explanation
    The components of test planning include a testing schedule, which outlines the timeline and sequence of testing activities, ensuring that testing is completed within the allocated time frame. Run plan creation is also a component, which involves creating a detailed plan for executing test cases and documenting the steps to be followed during testing. Lastly, roles and responsibilities are defined in test planning, assigning tasks and responsibilities to the team members involved in the testing process.

    Rate this question:

  • 27. 

    27. who are development organization stakeholder?

    • A.

      A.developer

    • B.

      B.business user

    • C.

      C.development manager

    • D.

      D.customer SME's

    Correct Answer(s)
    A. A.developer
    C. C.development manager
    Explanation
    Developers and development managers are considered stakeholders in a development organization because they play key roles in the development process. Developers are responsible for writing the code and creating the software or application, while development managers oversee the entire development process and ensure that it is carried out efficiently and effectively. Both developers and development managers have a vested interest in the success of the development project and are therefore considered stakeholders.

    Rate this question:

  • 28. 

    28. Is business user are creating UAT test case and carried out UAT?

    • A.

      True

    • B.

      False

    Correct Answer
    A. True
    Explanation
    The given answer is true because it states that business users are creating UAT (User Acceptance Testing) test cases and carrying out UAT. UAT is typically performed by end-users or business representatives to ensure that the system meets their requirements and is ready for production. Therefore, it is logical to assume that business users are responsible for creating UAT test cases and conducting UAT.

    Rate this question:

  • 29. 

    29. HR policy is planned to revised new type of leave that is personal leave. This kind of req is comes under ??

    • A.

      A.functional requirement

    • B.

      B. system requirement

    • C.

      C.future requirement

    Correct Answer
    C. C.future requirement
    Explanation
    The correct answer is c. future requirement. This is because the HR policy is being planned to revise a new type of leave, which indicates a requirement for the future. This requirement is not related to the functionality or system of the organization, but rather a future need or demand for a personal leave policy.

    Rate this question:

  • 30. 

    30. test automation is identified to ensure that

    • A.

      A.easy

    • B.

      B.error free

    • C.

      C.faster

    Correct Answer(s)
    B. B.error free
    C. C.faster
    Explanation
    Test automation is identified to ensure that the testing process is error-free and faster. By automating tests, the chances of human errors are minimized, as automation tools can execute tests with precision and accuracy. Additionally, automation allows for faster execution of tests, as it eliminates the need for manual intervention and can run tests simultaneously or repeatedly. This helps in saving time and effort, enabling faster delivery of software products while maintaining the quality and reliability of the testing process.

    Rate this question:

Quiz Review Timeline +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 26, 2024
    Quiz Edited by
    ProProfs Editorial Team
  • Jan 09, 2012
    Quiz Created by
    Catherine Halcomb
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.