This full length practice exam is a simulation of what you will see when you take the real PMP exam. This exam contains 200 questions and you must complete the exam in a 4-hour time limit. This practice exam uses the same process group percentages as the actual PMP exam. NOTE: Unlike the real See morePMP Exam, this simulation exam does not allow you to go back to the previous questions until you complete all the questions. Please do NOT use the browser "Back" button or the "Backspace" key to go back to the previous questions. At the end of the exam, you will be given an opportunity to review and change the answers of any questions before submitting the exam. When you are ready to take the exam, please enter your First and Last name. Then press "Start" to begin.
To formally authorize a project or a phase and document initial requirements which satisfy the stakeholder’s needs and expectations.
To document how the project will be planned, executed, monitored/controlled, and closed.
To link the project, which is going to be planned, executed, and monitored/controlled to the ongoing work of the organization.
To describe the process of performing the work defined in the project management plan in order to achieve the project’s objectives.
Rate this question:
Three-point estimation
Triple constraint
Three wise men
Three needs theory
Rate this question:
Analyze the impact of the change
Inform stakeholders of the change approval
Update the project plan to reflect the change
Manage the project based on the approved change
Rate this question:
Report him to the PMI
Do nothing, you are not responsible for the integrity of others
Report him to management, because he is violating company policy
Meet with him to try to talk some sense into him
Rate this question:
Requirements documentation
Project charter
Requirements management plan
Project statement of work
Rate this question:
Understanding who might impact or might be impacted by the project
Determining a strategy for how to best manage various stakeholders
Understanding who will be responsible for completing the work
Understanding stakeholder attitudes
Rate this question:
Inform the stakeholder that due to the tight schedule you cannot make the change
Issue a change request immediately and let the change control board decide
Begin working on the change, because this is a key stakeholder and you should keep her happy
Analyze the impact of the change
Rate this question:
Cost of change increases
Risk increases
Stakeholder influence decreases
Cumulative project spend increases
Rate this question:
$470,588
$370,588
$240,000
$340,000
Rate this question:
It organizes the project team and shows reporting structures
It assigns work to individual team members
It makes the project easier to estimate and manage
It describes in detail the project's deliverables
Rate this question:
A product that doesn't have any documented defects
A product that last for 25 years
A product that passes all quality tests
A product that satisfies the quality requirements
Rate this question:
Reporting structures within the organization
Escalation path for resolving issues
Stakeholder communication requirements
Reasons for information distribution
Rate this question:
To prevent changes from occurring
To help the project manager make tough decisions
To provide a framework to approve, reject, and manage changes
To eliminate scope creep
Rate this question:
Select the lowest bid, regardless of the potential quality issues
Select the highest bid (your cousin's bid), because you'll personally gain from it
Select the second lowest bid, because it's the best quality and only costs 1% more
Ask the second highest bidder to revise their bid to match the lowest price
Rate this question:
Quality audits
Inspection
Cause and effect diagram
Pareto chart
Rate this question:
Pay the police for the escort, because it could be dangerous not to
Refuse the police escort service, because it is a bribe
Postpone your meeting, so that you can ask management for advice
Cancel the meeting
Rate this question:
Withdrawel
Compromise
Confronting
Smoothing
Rate this question:
Perform Quality Control
Perform Integrated Change Control
Perform Quality Assurance
Close Project or Phase
Rate this question:
Repair the product to include the missing component at no charge to the customer, because the customer is always right.
Perform the work and bill the customer for the added cost.
Meet with the customer to document the missing component, and then issue a change request to complete the required work.
Inform the customer that since the product passed all quality tests and passed scope verification, it is complete.
Rate this question:
Call a team meeting to discuss the risk
Transfer the risk by hiring an external vendor to do the work
Reprimand the team member for even bringing up the risk
Document the risk in the risk register
Rate this question:
Analogous estimating
Decomposition
Templates
Rolling wave planning
Rate this question:
It defines the project scope
It authorizes work to begin on the project
It completely describes the work to be done on the project
It describes the business case and reason for doing the project
Rate this question:
Go to the accounting director's manager and ask for the senior resources you need
Do the best you can with the junior team members
Ask your manager to talk with the accounting director
Call a meeting with the accounting director, so that you can explain more clearly the need for senior resources on your project
Rate this question:
A contingency reserve is a separately planned quantity used to allow for unplanned but potentially required changes that can result from realized risks identified in the risk register
Contingency reserves may be set aside for known unknowns
Contingency reserves may be set aside for unknown unknowns
Contingency reserves are normally included in the project's cost and schedule baselines
Rate this question:
Formal verbal
Formal written
Informal verbal
Informal written
Rate this question:
Accept the offer and use the software to complete your project on time
Purchase the software from an authorized vendor
Decline the offer and accept that the project may be late
Report your team member to the software vendor for software piracy
Rate this question:
Your project is over budget and behind schedule
Your project is over budget and ahead of schedule
Your project is under budget and behind schedule
Your project is under budget and ahead of schedule
Rate this question:
This is unethical, because it violates the personal gain clause of the PMI code of ethics.
This is unethical, because it violates the conflict of interest clause of the PMI code of ethics.
This is unethical, because it violates both the personal gain and conflict of interest clauses of the PMI code of ethics.
This is not a violation of the PMI code of ethics; you are simply trying to help out a local bank.
Rate this question:
Accept the work as completed
Have a mediator help resolve the issue
File a lawsuit to force the vendor to complete the work or pay you damages
Follow the claims administration procedures for resolving such conflicts
Rate this question:
Documenting lessons learned
Conducting a procurement audit
Inspection
Decomposition
Rate this question:
Firm Fixed Price (FFP)
Fixed Price with Economic Prices Adjustment (FP-EPA)
Cost plus fixed fee (CPFF)
Time and Material (T&M)
Rate this question:
Scope creep
Gold plating
Prototypes
Alternatives identification
Rate this question:
Exploit
Accept
Transfer
Mitigate
Rate this question:
Reserves
Residual risks
Threats
Watchlist
Rate this question:
Gantt chart
Collection of subsidiary plans
Must be approved by the sponsor and stakeholders
Progressive elaboration
Rate this question:
It is the process of ensuring the WBS is completely defined
It is the process of formalizing acceptance of the completed project deliverables
It is the process of breaking down the project work into smaller, more manageable components
It is a key part of the requirements analysis process
Rate this question:
A weighted average method of estimating costs or durations
Using a previous project as a starting point and making adjustments for know differences to calculate the cost or duration
Using a statistical relationship (such as cost per unit) to calculate the cost or duration
Breaking an activity down into smaller components that are easier to estimate, then aggregating the costs or durations
Rate this question:
A data point that is just above the upper control limit
Seven consecutive data points above the mean, but within the control limits
A data point that is just below the lower control limit
Seven consecutive data points on either side of the mean, but within the control limits
Rate this question:
Call the client and explain that you will not be able to attend because you lost your wallet, even if it means delaying your project
Postpone the meeting
Use your co-worker's ID and board the flight
Make up an excuse, such as a death in the family, to cover up for your mistake
Rate this question:
Staff acquisition and release
Compliance and safety
Roles and responsibilities
Rewards and recognition
Rate this question:
At the start of the project
At the start of the planning process group
At the start of each phase
After gathering the requirements
Rate this question:
The schedule baseline
Work performance information
Schedule network diagram
Reserve analysis
Rate this question:
Fix the flaw immediately
Inform the customer of the design flaw
Create a change request
Determine the impact of the change
Rate this question:
Bureaucracies
Constraints
Workarounds
Assumptions
Rate this question:
22
24
25
28
Rate this question:
Storming
Performing
Forming
Norming
Rate this question:
Stretch your work out, so that you complete the project at the end of December as scheduled to ensure that your contract gets renewed.
Complete the project on December 13, even if it means losing the contract.
Ask the customer for an early completion bonus.
Complete the project on December 13, but continue working on additional features so that the customer will get more than they expected.
Rate this question:
Ignore the stakeholder
Meet with the stakeholder to inform them of your project
Meet with the stakeholder to gather their requirements
Find someone to blame for not identifying the stakeholder earlier
Rate this question:
Quiz Review Timeline (Updated): Feb 7, 2024 +
Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.
Wait!
Here's an interesting quiz for you.