The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Thames
T
Thames
Community Contributor
Quizzes Created: 7153 | Total Attempts: 9,522,946
| Questions: 9 | Updated: Aug 4, 2025
Please wait...
Question 1 / 9
0 %
0/100
Score 0/100
1. Which type of project cost estimate is the most accurate?

Explanation

A definitive cost estimate provides the most accurate projection of costs as it involves detailed project planning and analysis compared to the other types which are more preliminary or high-level estimates.

Submit
Please wait...
About This Quiz
Project Cost Management Mastery For PMP Certification - Quiz

This focused evaluation enhances understanding of Project Cost Management, crucial for PMP exam preparation. It assesses key skills in budgeting, cost estimating, and financial control, essential for effective project management and certification success.

2.
We’ll put your name on your report, certificate, and leaderboard.
2. Which type of contracts is most preferable to the contractor doing the project work?

Explanation

Cost plus fixed fee contracts provide the contractor with reimbursement for all allowable expenses plus a fixed fee which incentivizes efficient and cost-effective work. Fixed price contracts may not account for unexpected costs, while fixed price plus incentive fee contracts can be risky as they may encourage cutting corners to maximize profit.

Submit
3. To assist in budget control, it is suggested that the estimate occur at the _______ level of the WBS

Explanation

In order to accurately estimate costs for each work package, it is recommended to do so at the lowest level of the WBS where the work is broken down into manageable components.

Submit
4. Cost Variance (CV) is which of the following equations?

Explanation

Cost Variance (CV) is calculated by subtracting Actual Cost of Work Performed (ACWP) from Budgeted Cost of Work Performed (BCWP). This formula provides insight into whether a project is under or over budget in terms of costs.

Submit
5. Cost budgeting can be best described by which of the following?

Explanation

Cost budgeting is primarily about setting budgets, standards, and systems to measure and manage project costs effectively.

Submit
6. Which of the following is a direct project cost?

Explanation

Direct project costs are expenses that can be specifically attributed to a particular project. In this case, piping for an irrigation project is a direct project cost as it is directly related to the specific project being undertaken. On the other hand, lighting and heating for the corporate office, workers compensation insurance, and options that combine both are not direct project costs as they are more general expenses that may not be directly tied to the project itself.

Submit
7. Cost controls can be best described by which of the following?

Explanation

Cost controls involve the ongoing process of gathering, accumulating, analyzing, reporting, and managing the costs of a project to ensure it stays within budget and on track.

Submit
8. The BCWS = $250, the ACWP = $350, and the BCWP = $200. Calculate the Cost Variance?

Explanation

Cost Variance is calculated as BCWP - ACWP. In this case, the BCWP is $200 and the ACWP is $350. Thus, Cost Variance = $200 - $350 = -$150.

Submit
9. Life Cycle Costing is a term that is:

Explanation

Life Cycle Costing is a term that is used when making decisions between alternatives and employed principally by the government, making options A and B the correct answer.

Submit
View My Results
Cancel
  • All
    All (9)
  • Unanswered
    Unanswered ()
  • Answered
    Answered ()
Which type of project cost estimate is the most accurate?
Which type of contracts is most preferable to the contractor doing the...
To assist in budget control, it is suggested that the estimate occur...
Cost Variance (CV) is which of the following equations?
Cost budgeting can be best described by which of the following?
Which of the following is a direct project cost?
Cost controls can be best described by which of the following?
The BCWS = $250, the ACWP = $350, and the BCWP = $200. Calculate the...
Life Cycle Costing is a term that is: