Mastering PMP: A Comprehensive Project Management Quiz

  • PMBOK
  • ISO 21500
Reviewed by Editorial Team
The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Thames
T
Thames
Community Contributor
Quizzes Created: 7049 | Total Attempts: 9,519,298
| Questions: 19
Please wait...
Question 1 / 19
0 %
0/100
Score 0/100
1. In which document will you find the code of account identifier, description of work, responsible organization, and list of schedule milestones?

Explanation

The correct answer is WBS Dictionary because it contains detailed information about the work elements in the Work Breakdown Structure (WBS) such as the code of account identifier, description of work, responsible organization, and list of schedule milestones. The WBS itself just outlines the hierarchy of project tasks, PERT/CPM Charts show project time dependencies, and Roles and Responsibilities Matrix outlines who is responsible for what.

Submit
Please wait...
About This Quiz
Mastering PMP: A Comprehensive Project Management Quiz - Quiz

Enhance your project management skills with this focused quiz designed to test your knowledge on PMP principles. Ideal for professionals seeking to validate their expertise in managing projects effectively, this quiz covers key concepts and methodologies outlined in PMBOK, preparing you for PMP certification.

2.
We’ll put your name on your report, certificate, and leaderboard.
2. When referring to inputs for Develop Schedule process, responsibility (i.e., who will perform the work), activity type (i.e., summary or detailed), and WBS classification are :

Explanation

Activity attributes can be used to identify the person responsible for executing the work, geographic area, or place where the work has to be performed, and activity type such as level of effort (LOE), discrete effort, and apportioned effort (AE). Activity attributes are used for schedule development and for selecting, ordering, and sorting the planned schedule activities in various ways within reports.

Submit
3. In your project, you are estimating schedule activity costs by determining the unit cost rates, e.g., staff costs per hour. All the following could be used to determine resource cost rates EXCEPT:

Explanation

Parametric estimating uses a statistical relationship between historical data and other variables.

Submit
4. You are the project manager responsible for manufacturing a particular variety of soap. You decide to do a statistical sampling for this project, because surveying the entire population involves all the following problems EXCEPT:

Explanation

Survey of the entire population yields accurate data.

Submit
5. When you started creating a work breakdown structure for your project, you realized that it was too complicated to be done on a single piece of paper. You then started using a work breakdown structure numbering system to:

Explanation

The correct answer is to determine the level at which individual WBS elements are found. This numbering system allows for a hierarchical representation of project elements, aiding in organizing and understanding the project structure.

Submit
6. Please refer to the diagram given below (all units are in days): What is the project float if management wants to complete this project within 13 days?

Explanation

The correct answer is -3 days as the project float is calculated by subtracting the project duration from the desired completion time. In this case, with the critical path of 16 days and a desired completion time of 13 days, the project float is -3 days.

Submit
7. In your project, you are using cost aggregation, expert judgment, and historical relationships to establish a cost performance baseline. This is performed during:

Explanation

Determine Budget is the process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline. Cost aggregation, expert judgment, and historical relationships are some of the tools used in this process.

Submit
8. You are a project manager. At the executing stage of the project, all the following statements are correct EXCEPT:

Explanation

When closing the project, the project manager will review all prior information from the previous phase closures to ensure that all project work is complete and that the project has met its objectives.

Submit
9. Determining and delivering the required levels of quality for the project is the responsibility of:

Explanation

The project manager and the project management team are responsible for managing the tradeoffs involved to deliver the required levels of both quality and grade.

Submit
10. In your project, you need to verify whether deliverables meet requirements and product acceptance criteria. For this purpose, which of the following would you rely on?
Submit
11. What is the conflict resolution strategy characterized by facing conflict directly and working through disagreements with a problem-solving approach?

Explanation

Confrontation involves directly addressing and working through conflicts, unlike withdrawal, smoothing, or forcing which involve avoiding, de-emphasizing, or exerting viewpoints at the expense of others.

Submit
12. You are creating a cost performance baseline for your project. In this context, all the following statements related to cost performance baseline are correct EXCEPT:

Explanation

In the earned value management technique, the cost performance baseline is referred to as the performance measurement baseline (PMB).

Submit
13. You have been managing a project to construct a flyover on Interstate 10. You have divided the project into phases to provide better management control. Which of the following is a characteristic of a project phase?

Explanation

Formal phase completion does not necessarily include authorization for the subsequent phase. For instance, if the risk is deemed to be too great for the project to continue or if the objectives are no longer required, a phase can be closed with the decision not to initiate any other phase.

Submit
14. In your new project, you have to provide a critical deliverable within five months and do not have time to go through the Conduct Procurements process. You decide to sign a contract with a supplier with whom your company has done some work in the past. The risk you are accepting in this situation is:

Explanation

The risk here is that even though the supplier has worked with the company in the past, they may not have the required skills for the current project.

Submit
15. In your project, you are using Report Performance process to organize and summarize the information gathered. Later, you present the results of the analysis as a comparison to the performance measurement baseline. Some common formats for performance reports that you could use are:

Explanation

Common formats for performance reports include bar charts, S-curves, histograms, and tables. Option 1: Pareto charts are used in Perform Quality Control process. Option 2: Responsibility assignment matrices are used in Develop Human Resource Plan process. Option 4: Control charts are used in Perform Quality Control process.

Submit
16. You are in the process of performing Develop Schedule process to determine planned start and finish dates for project activities. Which of the following inputs will be helpful in this process?

Explanation

In Develop Schedule process, planned start and finish dates for project activities are determined by using activity attributes, project scope statement, and activity list as inputs. Schedule data and schedule baseline are outputs of Develop Schedule process; and work performance information is an input to Control Schedule process.

Submit
17. In your project, you have been sub-contracting your IT development work to four consultancy firms. In this context, all the following statements relating to transferring of risk to a contractor are true EXCEPT:

Explanation

A fixed-price contract may transfer risk to the seller if requirements are well defined and seller has the capacity to handle the risk.

Submit
18. In your project, you wish to identify and document the specific actions to be performed to produce the deliverables. This is done as part of:

Explanation

Define Activities is the process of identifying the specific actions to be performed to produce the project deliverables.

Submit
19. In your project, you have conducted a communication requirements analysis to determine the total number of possible communication channels. What is the relationship between the number of communication channels and the number of people involved?

Explanation

The number of communication channels in a project increases exponentially as the number of people involved in the project increases, leading to a higher potential for miscommunication and complexity.

Submit
View My Results

Quiz Review Timeline (Updated): Aug 4, 2025 +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Aug 04, 2025
    Quiz Edited by
    ProProfs Editorial Team
  • Aug 04, 2025
    Quiz Created by
    Thames
Cancel
  • All
    All (19)
  • Unanswered
    Unanswered ()
  • Answered
    Answered ()
In which document will you find the code of account identifier,...
When referring to inputs for Develop Schedule process, responsibility...
In your project, you are estimating schedule activity costs by...
You are the project manager responsible for manufacturing a particular...
When you started creating a work breakdown structure for your project,...
Please refer to the diagram given below (all units are in days): What...
In your project, you are using cost aggregation, expert judgment, and...
You are a project manager. At the executing stage of the project, all...
Determining and delivering the required levels of quality for the...
In your project, you need to verify whether deliverables meet...
What is the conflict resolution strategy characterized by facing...
You are creating a cost performance baseline for your project. In this...
You have been managing a project to construct a flyover on Interstate...
In your new project, you have to provide a critical deliverable within...
In your project, you are using Report Performance process to organize...
You are in the process of performing Develop Schedule process to...
In your project, you have been sub-contracting your IT development...
In your project, you wish to identify and document the specific...
In your project, you have conducted a communication requirements...