This quiz, part of ALE Day 1 HOA-TOA-PP series, assesses knowledge in historical architecture and construction management. It covers key figures, historical buildings, and procedural requirements in construction, enhancing understanding of architectural evolution and project management.
Basilica of St. Denis
Chartres Cathedral
Notre Dame de Paris
Cologne Cathedral
Rate this question:
Bramante
Maderna
Bernini
Buonarrotti
Rate this question:
10 days
15 days
3 weeks
1 month
Rate this question:
Philadelphia; Jayne Estate Building
New York; New York World Building
Chicago; John Hancock Center
Chicago; Home Insurance Building
Rate this question:
New York World Building
Flat Iron Building
Vanderbilt Hotel
Chrysler Building
Rate this question:
3 days
5 days
1 week
2 weeks
Rate this question:
Owner
Contractor
Architect
Foreman
Rate this question:
3 days
1 week
15 days
1 month
Rate this question:
Hierarchy
Contrast
Rhythm
Scale
Rate this question:
7 days
1 fortnight
1 month
Doesn't matter. Owner gets to choose
Rate this question:
IAPOA certificate
PRC ID
PTR
CTC
Rate this question:
One World Trade Center
Willis Tower
432 Park Tower
Empire State
Rate this question:
710 mm
800 mm
900 mm
1200mm
Rate this question:
SEC registered, non-profit, non-stock
DTI registered, non-profit, non-stock
SEC registered, profit, stock
DTI registered, profit, stock
Rate this question:
Fire Code of the Philippines
National Building Code
Socialized Housing
Accessibility Law
Rate this question:
Metope
Acroterium
Tympanum
Triglyphs
Rate this question:
AN ACT PROVIDING FOR A MORE RESPONSIVE AND COMPREHENSIVE REGULATION FOR THE REGISTRATION, LICENSING AND PRACTICE OF ARCHITECTURE
AN ACT TO REGULATE THE PRACTICE OF ARCHITECTURE IN THE PHILIPPINES
AN ACT TO ENHANCE THE MOBILITY OF DISABLED PERSONS BY REQUIRING CERTAIN BUILDINGS, INSTITUTIONS, ESTABLISHMENTS AND PUBLIC UTILITIES TO INSTALL FACILITIES AND OTHER DEVICES
AN ACT ESTABLISHING A COMPREHENSIVE FIRE CODE OF THE PHILIPPINES
Rate this question:
Detailed Specs
General Specs
Drawing
Doesn't Matter
Rate this question:
Critical Path
Project Duration
Time Limit
Deadline
Rate this question:
Payment Bond
Proposal Bond
Contract Bond
Performance Bond
Rate this question:
If the Owner should fail to pay the Contractor any sum within 30 days after its award by arbitration
If the Owner should fail to act upon the Request for Payment or Certificate of Payment within fourteen days after its certification by the Architect
If the Architect should fail to act upon the Request for Payment within fifteen days after it is presented in accordance with the General Conditions of the Contract
If an order of any court or other public authority caused the work to be stopped or suspended for a period of 90 days through no act or fault of the contractor or his employees
Rate this question:
Declare bankruptcy, become insolvent or assign his assets for the benefit of his creditors.
Disregard or violate Engineer’s instructions, or failed to execute the work according to the agreed Schedule of Completion, including extensions thereof.
Fail to provide a qualified superintendent, competent workmen or sub-contractors or proper materials
Fail to make prompt payment to sub-contractors, workmen or material dealers
Rate this question:
Ophistodomos
Pronaos
Nave
Cella
Rate this question:
Caryatids
Atlantes
Telamons
Canephora
Rate this question:
Quiz Review Timeline (Updated): Mar 21, 2023 +
Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.
Wait!
Here's an interesting quiz for you.