Time And Work, Pipes And Cistern

Approved & Edited by ProProfs Editorial Team
The editorial team at ProProfs Quizzes consists of a select group of subject experts, trivia writers, and quiz masters who have authored over 10,000 quizzes taken by more than 100 million users. This team includes our in-house seasoned quiz moderators and subject matter experts. Our editorial experts, spread across the world, are rigorously trained using our comprehensive guidelines to ensure that you receive the highest quality quizzes.
Learn about Our Editorial Process
| By Traininghosur123
T
Traininghosur123
Community Contributor
Quizzes Created: 4 | Total Attempts: 1,728
Questions: 20 | Attempts: 177

SettingsSettingsSettings
Time And Work, Pipes And Cistern - Quiz


Questions and Answers
  • 1. 

    A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in :

    • A.

      8

    • B.

      10

    • C.

      12

    • D.

      15

    Correct Answer
    C. 12
    Explanation
    A and B can complete the work in 15 and 10 days respectively. In 2 days, they would have completed a fraction of the work, which can be calculated as (2/15 + 2/10). To find the remaining work, we subtract this fraction from 1 (1 - 2/15 - 2/10). Simplifying this gives us 11/30. Since A can complete 1/15th of the work in a day, it would take him 11/30 * 15 = 5.5 days to complete the remaining work. Therefore, the total time taken to complete the work is 2 + 5.5 = 7.5 days, which is approximately 8 days. However, since the options do not include 7.5, the closest option is 12 days.

    Rate this question:

  • 2. 

    A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:

    • A.

      4

    • B.

      6

    • C.

      8

    • D.

      12

    Correct Answer
    B. 6
    Explanation
    Since A takes twice as much time as B to finish the work, and A, B, and C can finish the work together in 2 days, it means that B's contribution to the work is half of A's contribution. Therefore, B can finish the work alone in half the time it takes A, which is 6 days.

    Rate this question:

  • 3. 

    A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work in :

    • A.

      4

    • B.

      6

    • C.

      8

    • D.

      18

    Correct Answer
    A. 4
    Explanation
    Since B can complete the work in 12 days independently, A can complete the same work in half the time, which is 6 days. Therefore, if A and B work together, they can complete the work in less time than either of them individually. The time taken to complete the work together can be found by taking the reciprocal of the sum of the reciprocals of their individual times. In this case, the reciprocal of 6 is 1/6 and the reciprocal of 12 is 1/12. Adding these reciprocals gives 1/6 + 1/12 = 1/4. Taking the reciprocal of 1/4 gives 4, which means A and B can complete the work together in 4 days.

    Rate this question:

  • 4. 

    Twenty women can do a work in sixteen days. Sixteen men can complete the same work in fifteen days. What is the ratio between the capacity of a man and a woman?

    • A.

      3:4

    • B.

      4:3

    • C.

      5:3

    • D.

      Data Inadequate

    Correct Answer
    B. 4:3
    Explanation
    The given information states that twenty women can complete a work in sixteen days, while sixteen men can complete the same work in fifteen days. This implies that the capacity of a woman is greater than that of a man, as fewer women can complete the work in the same amount of time. Therefore, the ratio between the capacity of a man and a woman is 4:3.

    Rate this question:

  • 5. 

    A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?

    • A.

      12

    • B.

      16

    • C.

      18

    • D.

      15

    Correct Answer
    D. 15
    Explanation
    A can do the work alone in 20 days, while B and C can do the work together in (30+60) = 90 days. Since A is assisted by B and C on every third day, it means that A will work alone for 2 days and then with B and C on the third day. This pattern will continue. So, in every 3 days, A will do 2/20 = 1/10th of the work alone, and with B and C, they will do 1/90th of the work. Therefore, in 30 days (10 sets of 3 days), A will do 10*(1/10) + 10*(1/90) = 1 + 1/9 = 10/9th of the work. To complete the remaining 1/9th of the work, A will take 1 more day. Hence, A can do the work in 30+1 = 31 days.

    Rate this question:

  • 6. 

    A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:

    • A.

      20 days

    • B.

      22.5 days

    • C.

      25 days

    • D.

      30 days

    Correct Answer
    B. 22.5 days
    Explanation
    A is thrice as good as workman as B means that A is three times more efficient than B. This implies that A can complete 3 units of work in the same time it takes B to complete 1 unit of work.

    Let's assume that B takes x days to complete the job alone. Therefore, A takes x/3 days to complete the job alone.

    According to the given information, A is able to finish the job in 60 days less than B. This means that A takes x - 60 days to complete the job alone.

    When they work together, their combined efficiency is 1/x + 1/(x-60) units of work per day.

    To find the time taken when they work together, we need to find the reciprocal of their combined efficiency, which is (x(x-60))/(2x-60).

    We need to find the value of x that makes the equation equal to 1/20 (since they can do the job together in 20 days).

    By solving the equation (x(x-60))/(2x-60) = 1/20, we find that x = 75.

    Therefore, when they work together, they can complete the job in 75 days.

    Since the answer options are not in terms of 75, we need to calculate the actual time.

    When x = 75, the time taken is (75(75-60))/(2(75)-60) = 22.5 days.

    Therefore, the correct answer is 22.5 days.

    Rate this question:

  • 7. 

    If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:

    • A.

      4 days

    • B.

      5 days

    • C.

      6 days

    • D.

      7 days

    Correct Answer
    A. 4 days
    Explanation
    The given question is based on the concept of the inverse variation of work and time. It states that the number of people required to complete a piece of work is inversely proportional to the time taken to complete the work. Therefore, if the number of people increases, the time taken will decrease and vice versa.

    From the given information, we can form the equation: (6 men + 8 boys) * 10 days = (26 men + 48 boys) * 2 days.

    Simplifying this equation, we find that (3 men + 4 boys) = (13 men + 24 boys).

    Now, we need to find the time taken by 15 men and 20 boys.

    Using the same logic, we can form the equation: (3 men + 4 boys) * 10 days = (15 men + 20 boys) * x days.

    Simplifying this equation, we find that x = 4 days.

    Therefore, the time taken by 15 men and 20 boys in doing the same type of work will be 4 days.

    Rate this question:

  • 8. 

    A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines are started at 9 A.M. while machine P is closed at 11 A.M. and the remaining two machines complete work. Approximately at what time will the work (to print one lakh books) be finished ?

    • A.

      1:30 A.M

    • B.

      12 Noon

    • C.

      12:30 P.M

    • D.

      1:00 P.M

    Correct Answer
    D. 1:00 P.M
    Explanation
    Machine P can print one lakh books in 8 hours, so it can print 12,500 books per hour. Machine Q can print the same number of books in 10 hours, so it can print 10,000 books per hour. Machine R can print the same number of books in 12 hours, so it can print 8,333 books per hour.

    Machine P is closed at 11 A.M., which means it has worked for 2 hours and printed 25,000 books. The remaining two machines, Q and R, need to print the remaining 75,000 books. Together, they can print 18,333 books per hour.

    To print 75,000 books, it will take approximately 4.1 hours. Adding this to the 2 hours that machine P worked, the work will be finished at approximately 1:00 P.M.

    Rate this question:

  • 9. 

    A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?

    • A.

      23 days

    • B.

      37 days

    • C.

      37.5 days

    • D.

      40 days

    Correct Answer
    C. 37.5 days
    Explanation
    A completes 80% of the work in 20 days, which means he can complete the entire work in 25 days. Then, A and B together finish the remaining 20% of the work in 3 days. This implies that they can complete the entire work in 3/20 * 100 = 15 days. Since A takes 25 days to complete the work alone, B alone would take 15 - 25 = -10 days to complete the work, which is not possible. Therefore, B alone would take longer than A, so the correct answer is 37.5 days.

    Rate this question:

  • 10. 

    A cistern has two taps (which fill it in 12 min and 15 min, respectively) and an exhaust tap. When all three taps are opened together, it takes 20 min to fill the empty cistern. How long will the exhaust tap take to empty it? 

    • A.

      20 mins

    • B.

      16 mins

    • C.

      10 mins

    • D.

      7 mins

    Correct Answer
    C. 10 mins
    Explanation
    When all three taps are opened together, they fill the cistern in 20 minutes. This means that in 1 minute, they fill 1/20th of the cistern's capacity. The first tap fills the cistern in 12 minutes, so in 1 minute it fills 1/12th of the cistern's capacity. Similarly, the second tap fills 1/15th of the cistern's capacity in 1 minute. Therefore, the combined rate of the first two taps is 1/12 + 1/15 = 9/60 + 4/60 = 13/60. Subtracting this rate from the overall rate of filling the cistern (1/20), we get the rate of the exhaust tap, which is 1/20 - 13/60 = 7/60. Inverting this rate, we find that the exhaust tap takes 60/7 minutes to empty the cistern, which is approximately 8.57 minutes or 9 minutes rounded to the nearest whole number. Therefore, the correct answer is 10 minutes.

    Rate this question:

  • 11. 

    Two pipes can fill a tank in 10 hours and 12 hours respectively, while the third can empty it in 20 hours. If all the pipes are opened together, the tank will be filled in: 

    • A.

      7.5

    • B.

      7

    • C.

      6.5

    • D.

      8

    Correct Answer
    A. 7.5
    Explanation
    The first pipe can fill 1/10 of the tank per hour, the second pipe can fill 1/12 of the tank per hour, and the third pipe can empty 1/20 of the tank per hour. When all three pipes are opened together, the net amount of water being added to the tank per hour is (1/10 + 1/12 - 1/20). Simplifying this expression gives (6/60 + 5/60 - 3/60) = 8/60 = 1/7.5. Therefore, it will take 7.5 hours to fill the tank when all three pipes are opened together.

    Rate this question:

  • 12. 

    Two pipes P and Q would fill a cistern in 24 and 32 minutes, respectively. Both pipes are kept open. When should the first pipe be turned off so that the cistern may be just filled in 16 minutes? 

    • A.

      After 10 mins

    • B.

      After 12

    • C.

      After 14

    • D.

      After 16

    Correct Answer
    B. After 12
    Explanation
    To find the time at which the first pipe should be turned off, we need to determine the rate at which each pipe fills the cistern. Pipe P fills 1/24 of the cistern per minute, while pipe Q fills 1/32 of the cistern per minute. When both pipes are open, the combined rate of filling is (1/24) + (1/32) = 13/192 of the cistern per minute.

    To find the time at which the cistern is just filled in 16 minutes, we multiply the combined rate by 16: (13/192) * 16 = 13/12 of the cistern.

    Since pipe P fills the cistern at a rate of 1/24 per minute, it would have filled (1/24) * 12 = 1/2 of the cistern in 12 minutes. Therefore, the first pipe should be turned off after 12 minutes.

    Rate this question:

  • 13. 

    A tank has a leak which would empty the completely filled tank in 10 hours. If the tank is full of water and a tap is opened which admits 4 litres of water per minute in the tank, the leak takes 15 hours to empty the tank. How many litres of water does the tank hold?   

    • A.

      2400 l

    • B.

      4500 l

    • C.

      1200 l

    • D.

      7200 l

    Correct Answer
    D. 7200 l
    Explanation
    Let's assume the capacity of the tank is x liters.
    The leak empties the completely filled tank in 10 hours, so the leak rate is x/10 liters per hour.
    When the tap is opened, it admits 4 liters of water per minute, which is 4 * 60 = 240 liters per hour.
    So, the net inflow rate when the tap is opened is 240 - x/10 liters per hour.
    Given that the leak takes 15 hours to empty the tank, we can set up the equation:
    x / (240 - x/10) = 15
    Solving this equation, we get x = 7200 liters.
    Therefore, the tank holds 7200 liters of water.

    Rate this question:

  • 14. 

    Pipe A can fill a tank in 4 hours and pipe B can fill it in 6 hours. If they are opened on alternate hours and if pipe A is opened first then in how many hours, the tank shall be full?   

    • A.

      4 (1/2)

    • B.

      4 (2/3)

    • C.

      3 (1/2)

    • D.

      3 (1/4)

    Correct Answer
    B. 4 (2/3)
    Explanation
    Pipe A can fill the tank in 4 hours, which means it fills 1/4 of the tank in 1 hour. Pipe B can fill the tank in 6 hours, which means it fills 1/6 of the tank in 1 hour. When they are opened alternately, in the first hour, pipe A fills 1/4 of the tank. In the second hour, pipe B fills 1/6 of the remaining tank, which is 3/4. In the third hour, pipe A fills 1/4 of the remaining tank, which is 1/2. In the fourth hour, pipe B fills 1/6 of the remaining tank, which is 1/3. Therefore, the tank shall be full in 4 (2/3) hours.

    Rate this question:

  • 15. 

    20 workers can finish a work in 30 days. After how many days should 5 workers leave the job so the work is completed in 35 days? 

    • A.

      10 days

    • B.

      15 days

    • C.

      20 days

    • D.

      25 days

    Correct Answer
    B. 15 days
    Explanation
    If 20 workers can finish a work in 30 days, it means that the total work requires 600 worker-days (20 workers * 30 days). To complete the work in 35 days, the remaining workers need to work for 35 days. If 5 workers leave the job, the remaining workers need to complete the remaining work in 35 days. Since the total work requires 600 worker-days, the remaining workers need to work for 595 days (600 worker-days - 5 worker-days). Therefore, the 5 workers should leave the job after 15 days (595 worker-days / 35 days).

    Rate this question:

  • 16. 

     A group of men decided to do a job in 8 days. But since 10 men dropped out every day, the job got completed at the end of the 12th day. How many men were there at the beginning?

    • A.

      165

    • B.

      175

    • C.

      80

    • D.

      None

    Correct Answer
    A. 165
    Explanation
    At the beginning, there were 165 men. Each day, 10 men dropped out, so after 12 days, there would be 120 men remaining. Since the job got completed at the end of the 12th day, it means that all the men who were present at the beginning were able to complete the job. Therefore, the correct answer is 165.

    Rate this question:

  • 17. 

    Pipe A can fill a tank in 10 hours and pipe B can empty the same tank in 15 hours. Find the time taken by the pipes together to fill the tank. 

    • A.

      Can never be filled

    • B.

      30 hours

    • C.

      15 hours

    • D.

      12.5 hours

    Correct Answer
    B. 30 hours
    Explanation
    Pipe A can fill the tank in 10 hours, which means it fills 1/10th of the tank in 1 hour. Pipe B can empty the tank in 15 hours, which means it empties 1/15th of the tank in 1 hour. When both pipes are working together, the net fill rate is (1/10) - (1/15) = 1/30th of the tank per hour. Therefore, it will take 30 hours for both pipes to fill the tank together.

    Rate this question:

  • 18. 

    'A' can complete a piece of work in 12 days. 'A' and 'B' together can complete the same piece of work in 8 days. In how many days can 'B' alone complete the same piece of work?

    • A.

      24 days

    • B.

      12 days

    • C.

      48 days

    • D.

      20 days

    Correct Answer
    A. 24 days
    Explanation
    In this question, we are given that 'A' can complete a piece of work in 12 days and 'A' and 'B' together can complete the same piece of work in 8 days. From this information, we can infer that in 1 day, 'A' completes 1/12th of the work and 'A' and 'B' together complete 1/8th of the work. To find out how many days 'B' alone can complete the work, we subtract the work done by 'A' in 1 day from the work done by 'A' and 'B' together in 1 day. So, 'B' alone completes 1/8th - 1/12th = 1/24th of the work in 1 day. Therefore, 'B' alone can complete the same piece of work in 24 days.

    Rate this question:

  • 19. 

    Fifty six men can complete a piece of work in 24 days. In how many days can 42 men complete the same piece of work?

    • A.

      18

    • B.

      32

    • C.

      98

    • D.

      48

    Correct Answer
    B. 32
    Explanation
    If 56 men can complete a piece of work in 24 days, it means that the work requires a total of 56*24 = 1344 man-days to be completed. To find out how many days 42 men will take to complete the same piece of work, we divide the total man-days required by the number of men, which gives us 1344/42 = 32 days. Therefore, 42 men can complete the work in 32 days.

    Rate this question:

  • 20. 

    A can finish a piece of work in 10 days. B can finish the same piece of work in 15 days. Together they can finish the same work in how many days?For the above question, we must assume the total work to be__

    • A.

      30 units

    • B.

      1 unit

    • C.

      Any variable say 'X'

    • D.

      15 units

    • E.

      Either '30 units' or '1 unit' only but not a variable

    • F.

      Any assumption is right

    Correct Answer
    F. Any assumption is right
    Explanation
    Assume any value and check the answer. The total time taken will always be 6 days.

    Rate this question:

Quiz Review Timeline +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 21, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Jun 26, 2017
    Quiz Created by
    Traininghosur123
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.