Construction Documents Technology Exam: Quiz!

Reviewed by Editorial Team
The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Morganrae91
M
Morganrae91
Community Contributor
Quizzes Created: 1 | Total Attempts: 7,088
| Attempts: 7,088 | Questions: 124
Please wait...
Question 1 / 124
0 %
0/100
Score 0/100
1. True or False: Zoning is an example of a land development regulation. 

Explanation

Zoning is indeed an example of a land development regulation. It refers to the process of dividing land into different zones or areas with specific regulations and restrictions regarding land use, building heights, density, and other factors. Zoning aims to promote orderly and efficient land development, protect property values, and ensure compatibility between different land uses within a community. It is commonly used by local governments to control and guide the growth and development of cities and towns.

Submit
Please wait...
About This Quiz
Construction Documents Technology Exam: Quiz! - Quiz

This Construction Documents Technology Exam evaluates key aspects of construction management, focusing on substitution requests, contract interpretation, industry standards, and project delays. It's designed for professionals seeking to validate their expertise in managing construction documents effectively.

2. What are the three parts of the SectionFormat?

Explanation

The correct answer is "All of the above" because the SectionFormat consists of three parts: General, Products, and Execution. Each part plays a crucial role in defining and organizing the content within a section. The General part provides an overview or introduction, the Products part focuses on the specific products or services being discussed, and the Execution part outlines the steps or actions to be taken. Therefore, selecting "All of the above" indicates that all three parts are included in the SectionFormat.

Submit
3. True or False: By executing the contract, the Contractor confirms that the contract time is reasonable.  

Explanation

By executing the contract, the Contractor confirms that they agree to the terms and conditions outlined in the contract, including the contract time. This implies that the Contractor believes the contract time is reasonable and feasible to complete the project within the specified timeframe. Therefore, the statement is true.

Submit
4. True or False: There is no difference between the construction schedule and the project schedule.

Explanation

The statement is false because there is a difference between the construction schedule and the project schedule. The construction schedule specifically focuses on the timeline and activities related to the construction phase of a project, while the project schedule encompasses the entire project from start to finish, including planning, design, procurement, construction, and closeout. The project schedule is a broader and more comprehensive document that includes all the necessary tasks and milestones for the successful completion of the project, while the construction schedule is a subset of the project schedule that only pertains to the construction activities.

Submit
5. Experienced owners may require project teams to utilize integrated project delivery based upon:

Explanation

Experienced owners may require project teams to utilize integrated project delivery for several reasons. Firstly, they may have had previous negative experiences with adversarial project team relationships, and integrating the team can help improve communication and collaboration. Secondly, they may desire a reduction in project claims and disputes, which can be achieved through a more collaborative approach. Additionally, they may want to utilize collaboratively-produced Building Information Modeling (BIM) as a facilities management asset, as it can provide valuable information for the long-term maintenance of the project. Lastly, they may expect to benefit from innovation stemming from the collaborative effort of the team. Therefore, all of the given reasons can be valid explanations for why experienced owners may require integrated project delivery.

Submit
6. Which of the following should be avoided in a specification?

Explanation

All of the options mentioned (articles, symbols, and abbreviations) should be avoided in a specification. Articles can make the specification ambiguous, symbols can be confusing or misinterpreted, and abbreviations can lead to misunderstandings. It is important to use clear and concise language in a specification to ensure that it is easily understood by all parties involved.

Submit
7. Use of master guide specifications:

Explanation

The use of master guide specifications encompasses all of the given statements. The quality of the update process is crucial as it ensures that the specifications are up to date and accurate. Knowledge of the contract conditions is necessary to tailor the specifications accordingly. Utilizing a commercially-produced specification library can provide a standardized and comprehensive approach. Lastly, practice knowledge is required to effectively create project specifications that meet the specific requirements and standards. Therefore, all of the above statements are valid explanations for the correct answer.

Submit
8. True or False: There being no contractual relationship between the A/E and the contractor, there is also no contractual relationship between the A/E and the subcontractors and suppliers.

Explanation

The statement is true because if there is no contractual relationship between the A/E (Architect/Engineer) and the contractor, it follows that there would also be no contractual relationship between the A/E and the subcontractors and suppliers. Without a contractual agreement, there would be no legal obligations or responsibilities between these parties.

Submit
9. Special warranties/guarantees can: 

Explanation

Special warranties/guarantees can be provided by the manufacturer, contractor, or installer. These warranties/guarantees can have different durations, meaning they can be longer or shorter than the correction period. Additionally, these warranties/guarantees often exclude coverage for abuse, misuse, and failure to maintain the product or service. Therefore, the correct answer is "All of the above."

Submit
10. Drawings prepared by the contractor, subcontractor, or material/equipment supplier that show how a particular aspect of the work is to be fabricated and installed, are called:

Explanation

Shop drawings are detailed drawings prepared by the contractor, subcontractor, or material/equipment supplier to show how a specific aspect of the work is to be fabricated and installed. These drawings provide specific information about dimensions, materials, and installation methods, helping to ensure that the work is carried out accurately and according to the design intent. Shop drawings are typically used in construction projects to coordinate and communicate between different parties involved in the construction process. They are an essential tool for ensuring the quality and accuracy of the final construction.

Submit
11. Which bond protects the owner from losing the benefit of an accepted bid? 

Explanation

A bid bond is a type of surety bond that protects the owner from financial loss if the bidder fails to fulfill their obligations after being awarded the contract. It ensures that the bidder will enter into a contract and provide the required performance and payment bonds if their bid is accepted. In other words, it guarantees that the owner will not lose the benefit of the accepted bid if the bidder backs out or fails to meet their contractual obligations.

Submit
12. An information organizing framework for the design and construction industry that assigns built environment data into 15 discrete, coordinated tables to facilitate the organization of project information and databases is known as: 

Explanation

OmniClass is an information organizing framework for the design and construction industry that categorizes built environment data into 15 coordinated tables. These tables help in organizing project information and databases efficiently. It provides a standardized system for classifying and organizing information related to construction projects, making it easier for professionals in the industry to communicate and collaborate effectively. OmniClass is widely used in the industry as a classification system and is recognized for its ability to streamline project management and improve data interoperability.

Submit
13. True or False: If a portion of the work is covered contrary to requirements specifically expressed in the Contract Documents, it must if requested by the A/E, be uncovered for examination and at the Contractors expense without change in the contract time.

Explanation

If a portion of the work is covered in a way that goes against the requirements stated in the contract documents, the architect/engineer (A/E) has the right to request that it be uncovered for examination. The contractor would be responsible for the expense of uncovering the work, and this would not result in a change in the contract time.

Submit
14. An information organizing framework for the A/E/C industry that assigns built environment data into 15 discrete, coordinated tables to facilitate the organization of project information and databases is known as:

Explanation

OmniClass is an information organizing framework for the A/E/C industry that categorizes built environment data into 15 coordinated tables. It is designed to facilitate the organization of project information and databases, making it easier to manage and access relevant data. Unlike Industry Foundation Classes (IFCs) and Building Information Model (BIM), which are also used in the A/E/C industry but have different purposes, OmniClass specifically focuses on providing a structured framework for organizing information. Therefore, OmniClass is the correct answer in this context.

Submit
15. True or False: Sustainability consultants can only be retained by the design team

Explanation

Sustainability consultants are not limited to being retained only by the design team. They can be hired by any organization or individual who wants to incorporate sustainable practices into their operations. Sustainability consultants provide guidance and expertise in areas such as energy efficiency, waste reduction, and environmental impact assessment. They work with various stakeholders, including architects, engineers, facility managers, and business owners, to develop and implement sustainable strategies. Therefore, the statement that sustainability consultants can only be retained by the design team is false.

Submit
16. True or False: The A/E may withhold certification for payment in whole or in part if in the A/E's opinion representations to Owner cannot be made concerning the progress of the work.

Explanation

The A/E (Architect/Engineer) has the authority to withhold certification for payment if they believe that they cannot make representations to the owner regarding the progress of the work. This means that if the A/E believes that the work is not progressing as it should be or if there are issues with the quality or completion of the work, they can choose to withhold certification for payment. This allows the A/E to ensure that the owner is not paying for work that is not up to standard or is not progressing as expected.

Submit
17. To be effective in communicating, specifications should be:

Explanation

To be effective in communicating, specifications should be clear, meaning they should be easily understandable and free from ambiguity. They should also be concise, providing information in a succinct and to-the-point manner. Additionally, specifications should be correct, ensuring that the information provided is accurate and without errors. Lastly, specifications should be complete, covering all necessary details and leaving no important information out. Therefore, the answer "Clear, concise, correct, and complete" encompasses all the essential qualities required for effective communication of specifications.

Submit
18. If the contractor is delayed in the progress of the Work by Owner, he should: 

Explanation

If the contractor is delayed in the progress of the work by the owner, it is appropriate for the contractor to write the architect/engineer requesting a change order granting an extension of time. This is because the contractor is not responsible for delays caused by the owner and may need additional time to complete the work due to the owner's actions. By requesting a change order, the contractor can formally document the delay and request an extension to the project timeline. This ensures that the contractor is not held accountable for delays that are beyond their control.

Submit
19. True or False: Shop drawings are not contract documents.

Explanation

Shop drawings are not contract documents because they are detailed drawings produced by the contractor, subcontractor, or supplier that show the specific installation and fabrication details of the project. While they are important for coordination and construction purposes, they are not considered part of the legal contract between the owner and the contractor. Contract documents typically include the agreement, general conditions, specifications, and drawings prepared by the architect or engineer. Shop drawings are considered supplementary to the contract documents and are used to provide more specific information about how certain elements of the project will be constructed.

Submit
20. True or False: The facility manager should not be involved in project closeout because the facility manager is not a party to the construction contract. 

Explanation

The statement is false because the facility manager should be involved in project closeout. While the facility manager may not be a party to the construction contract, they play a crucial role in ensuring that the project is completed successfully and that all necessary tasks are carried out during the closeout phase. The facility manager is responsible for overseeing the transition from construction to operations, ensuring that all systems are functioning properly, and addressing any outstanding issues or deficiencies before the project is considered complete.

Submit
21. As a result of the widely held misconception that a contractor's responsibility for defective work lasts only for the one-year guaranty period: 

Explanation

The correct answer is that EJCDC and AIA documents state "correction period" instead of guaranty period. This means that the contractor's responsibility for defective work extends beyond just the one-year guaranty period. The use of the term "correction period" implies that the contractor must correct any defects or issues with their work for a specific additional length of time, as stated in the Supplementary Conditions. This clarification helps to prevent any misconceptions or misunderstandings about the contractor's responsibilities and ensures that the owner can expect repairs or corrections even after the initial guaranty period has ended.

Submit
22. As a result of the widely held misconception that a contractor's responsibility for defective work lasts only for the one-year guaranty period:  

Explanation

The correct answer is that EJCDC and AIA documents state correction period instead of guaranty period. This means that according to these documents, the contractor's responsibility for defective work lasts for a specific period of time called the correction period, rather than a guaranty period. This indicates that the contractor is responsible for making any necessary repairs or corrections during this specified time frame.

Submit
23. Since he or she is most familiar with a product, the manufacturer's representative should:

Explanation

The manufacturer's representative should supply information to the specification writer because they have the most familiarity with the product. They can provide the necessary details and technical information that the specification writer may need to accurately describe the product in the specification section. This ensures that the specifications are accurate and meet the requirements of the product. Consulting the manufacturer's representative helps in avoiding any conflict of interest and ensures that the specification section is well-informed and comprehensive.

Submit
24. Marked-up or corrected contract drawings that indicate changes incorporated in the Work are:

Explanation

Record drawings are marked-up or corrected contract drawings that indicate changes incorporated in the work. They are typically created during the construction process to document any modifications or alterations made to the original contract drawings. These drawings serve as a record of the as-built conditions and are often used for future reference, maintenance, or renovation purposes. Unlike contract forms, closeout submittals, and as-builts, record drawings are not required for private work, but they are commonly used in public projects to ensure accuracy and compliance.

Submit
25. All of the following may be accomplished through issuing of a Change Order EXCEPT: 

Explanation

A Change Order is a written agreement between the owner and contractor that authorizes a change in the scope of work or other contract terms. It is used to document and approve changes to the original contract. A Change in Bid Date, however, does not involve a change in the scope of work or contract terms. It simply refers to a modification in the date by which bids must be submitted. Therefore, it is not accomplished through issuing a Change Order.

Submit
26. All of the following activities are associated with the project conception stage except which one?

Explanation

The project conception stage involves activities such as predesign, planning, and programming. Predesign refers to the initial phase of gathering information and conducting feasibility studies. Planning involves creating a roadmap and determining the resources required for the project. Programming involves defining the project's objectives and requirements. Commissioning, on the other hand, is associated with the project's implementation and refers to the process of ensuring that all systems and components are installed, tested, and functioning correctly. Therefore, commissioning is not typically associated with the project conception stage.

Submit
27. Integrated projects are distinguished by all of the following characteristics EXCEPT:

Explanation

This answer is correct because all of the other characteristics mentioned (trust-based collaboration, maximized efficiency, compensation structures supporting early engagement, and development of virtual project model) are distinguishing features of integrated projects. However, "just as needed" team involvement to reduce owner's pre-construction expenses does not necessarily align with the collaborative and integrated nature of these projects.

Submit
28. The parties to an owner/design-builder contract are::

Explanation

In an owner/design-builder contract, the parties involved are the owner and the design-builder. This means that the owner of the project and the entity responsible for both the design and construction of the project are the main parties in this type of contract. The owner/design-builder contract allows for a more streamlined and integrated approach to the project, as the design and construction aspects are handled by a single entity. This can lead to greater efficiency and cost savings for the owner. The other options provided in the question do not accurately represent the parties involved in an owner/design-builder contract.

Submit
29. The nationally-recognized California AIA "Integrated Project Delivery Guide" redefines the stages of a project to include which of the following: 

Explanation

The correct answer is "All of the above". The California AIA "Integrated Project Delivery Guide" includes all of the mentioned stages of a project, which are conceptualization, criteria design, detailed design, and implementation document. This guide redefines the traditional stages of a project and emphasizes the importance of integrating various aspects throughout the entire project lifecycle.

Submit
30. A unit price contract or contract portion is used when:

Explanation

A unit price contract or contract portion is used when the extent of work cannot be fully determined or where actual quantities cannot be accurately calculated. This type of contract allows for flexibility in pricing based on the actual quantities of work performed or materials used. It is particularly useful in situations where the scope of work may change or where there is uncertainty in the quantities involved. By using unit prices, the contractor and owner can agree on a fair and reasonable price for each unit of work, which can then be multiplied by the actual quantities to determine the total cost.

Submit
31. Lump Sum, Unit Price, or Cost-Plus-Fee constitute the basis of:

Explanation

The options Lump Sum, Unit Price, and Cost-Plus-Fee all refer to different methods of payment in a contract. Lump Sum refers to a fixed payment amount for the entire project, Unit Price refers to payment based on the quantity of units used or produced, and Cost-Plus-Fee refers to payment based on the actual cost of materials and labor plus an additional fee. Therefore, the correct answer is Payment.

Submit
32. Under the AIA A201 and EJCDC C-700, who provides property insurance covering the Work?

Explanation

According to the AIA A201 and EJCDC C-700, the owner is responsible for providing property insurance covering the work. This means that the owner is responsible for insuring the property during the construction process. The contractor's surety, contractor, financing agency, or any other party mentioned in the options is not responsible for providing this insurance.

Submit
33. True or False: The OmniClass construction specification system is based on the International Organization for Standards (ISO). 

Explanation

The statement is true. The OmniClass construction specification system is indeed based on the International Organization for Standards (ISO). This means that the system follows the guidelines and standards set by ISO, ensuring consistency and compatibility with other international standards.

Submit
34. Under the AIA A201 and the EJCDC C-700, who has the authority to stop the Work, if nonconforming Work fails to be corrected?

Explanation

According to the AIA A201 and the EJCDC C-700, the owner has the authority to stop the work if nonconforming work fails to be corrected. This means that if the work being done does not meet the required standards or specifications, the owner has the power to halt the project until the issues are resolved. The A/E (Architect/Engineer), contractor, and any other parties involved do not have the authority to stop the work in this situation. The owner is ultimately responsible for ensuring that the work meets the necessary standards and can take action to address any nonconforming work.

Submit
35. Under the AIA A201 and EJCDC C-700, who provides property insurance covering the Work? 

Explanation

According to the AIA A201 and EJCDC C-700, the owner is responsible for providing property insurance covering the work. This means that the owner is required to obtain insurance coverage to protect against any damage or loss that may occur during the construction process. The contractor's surety, contractor, financing agency, or any other party mentioned in the options is not responsible for providing this insurance.

Submit
36. Which of these types of dimensions are likely to be included on one drawing:

Explanation

All of the above types of dimensions are likely to be included on one drawing. Actual dimensions represent the precise measurements of the object being drawn, while nominal dimensions are approximate values used for general reference. Modular dimensions are standardized measurements that allow for easy assembly and interchangeability of components. Including all of these dimensions on a drawing ensures that all necessary information is provided for accurate manufacturing and assembly processes.

Submit
37. Marked up or corrected contract drawings that indicate changes incorporated in the Work are called:

Explanation

Record Drawings are marked up or corrected contract drawings that indicate changes incorporated in the work. These drawings are typically created during the construction process to document any modifications or deviations from the original contract drawings. They serve as a record of the actual construction and are often used for reference and future maintenance or renovation purposes.

Submit
38. Under AIA A201, who has the authority to stop the work, if nonconforming work fails to be corrected? 

Explanation

According to AIA A201, the owner has the authority to stop the work if nonconforming work fails to be corrected. This means that if the work being done does not meet the required standards or specifications, the owner has the power to halt the progress until the issues are resolved. The A/E (Architect/Engineer) and the contractor may also have some authority in this matter, but the ultimate decision-making power lies with the owner.

Submit
39. True or False: Under a single-prime contract, the owner has a contractual relationship with suppliers and subcontractors

Explanation

Under a single-prime contract, the owner does not have a contractual relationship with suppliers and subcontractors. In a single-prime contract, the owner only has a contractual relationship with the prime contractor, who is responsible for managing and coordinating all aspects of the project, including subcontractors and suppliers. The prime contractor is the one who enters into contracts with suppliers and subcontractors, not the owner. Therefore, the correct answer is false.

Submit
40. . One of the benefits of working as a team is not:

Explanation

Working as a team can lead to increased productivity, reduced project costs, and earlier project completion. However, it does not necessarily result in fewer meetings. In fact, working as a team often requires more frequent and regular meetings to ensure effective communication, coordination, and collaboration among team members. Meetings are essential for discussing progress, resolving issues, making decisions, and maintaining alignment within the team. Therefore, the statement "Fewer meetings" is not a benefit of working as a team.

Submit
41. True or False: AIA Design Phases include schematic design, design development, and construction documents.

Explanation

The AIA Design Phases, which stands for American Institute of Architects Design Phases, include schematic design, design development, and construction documents. These phases are a systematic approach to the design and construction process, allowing for a clear progression from initial concepts to detailed plans and specifications. Schematic design involves creating rough sketches and conceptual ideas, design development refines these ideas into more detailed plans, and construction documents are the final set of drawings and specifications that guide the actual construction process.

Submit
42. True or False: As a project proceeds through the project delivery process (time), the ability to influence the cost is high at the beginning, but decreases as the project advances through the various stages.

Explanation

As a project progresses through the project delivery process, the ability to influence the cost is high at the beginning but decreases as the project advances through the various stages. This is because during the initial stages, there is more flexibility to make changes and adjustments that can impact the cost. However, as the project moves forward and more resources and activities are committed, the options for cost control become more limited. Therefore, it is important to address cost considerations early in the project to maximize the ability to influence and manage costs effectively.

Submit
43. If the construction budget of a 50,000 square foot project is $5,000,000 based on $100 per square foot, it is an example of which method of preparing the budget? 

Explanation

The given scenario of a construction budget for a 50,000 square foot project being calculated based on $100 per square foot indicates the use of the "Cost per measured unit" method. In this method, the budget is prepared by determining the cost of each measured unit (in this case, the cost per square foot) and multiplying it by the quantity required (in this case, the total square footage of the project).

Submit
44. The mood that is recommended for specifications is:

Explanation

The imperative mood is recommended for specifications because it is a grammatical mood that expresses commands, requests, or instructions. Specifications typically provide detailed instructions or requirements for a particular task or project, and using the imperative mood helps to convey these instructions clearly and directly. It creates a sense of authority and urgency, making it easier for the reader to understand and follow the specifications accurately.

Submit
45. The following are the types of clauses that might be included in Supplementary Conditions EXCEPT: 

Explanation

The given answer is "Submittal requirements". This is because submittal requirements are not a type of clause that would typically be included in Supplementary Conditions. Supplementary Conditions usually include clauses related to project insurance requirements, liquidated damage amounts, and the tax exempt status of the owner. Submittal requirements, on the other hand, are typically included in the General Conditions or in separate submittal documents.

Submit
46. All of the following subjects are usually included in Supplementary Conditions EXCEPT

Explanation

Supplementary conditions are additional contract provisions that modify or supplement the general conditions of a construction contract. They typically address specific project requirements or conditions. Insurance requirements, liquidated damages, and tax exempt status of the owner are all common subjects that may be included in supplementary conditions. However, submittal requirements are not typically included in supplementary conditions. Submittal requirements are usually addressed in the contract documents or project specifications, rather than in supplementary conditions.

Submit
47. True or False: The A/E is required to determine the project delivery method

Explanation

The A/E (Architect/Engineer) is not required to determine the project delivery method. The project delivery method is typically determined by the owner or client in consultation with the A/E and other stakeholders. The A/E's role is to provide expertise and recommendations regarding the various delivery methods available, but the final decision rests with the owner or client. Therefore, the statement is false.

Submit
48. Which is true concerning MasterFormat?

Explanation

MasterFormat is a standardized system used in the construction industry to organize and classify information related to construction projects. It is used to establish the proper location of information within the sixteen divisions, which helps in efficient communication and coordination among various stakeholders. Additionally, it contains a complete listing of topics covered in each division, ensuring that all aspects of a project are properly addressed. Furthermore, MasterFormat includes a keyword index, making it easier to locate specific information. Therefore, all the given statements about MasterFormat are true.

Submit
49. Typical components of a project financial study include: 

Explanation

A project financial study typically includes various components such as assessing the owner's financial condition, analyzing the life cycle costs of the project, determining the value of existing facilities, evaluating the available funding options, and considering the timing of the project. Therefore, all of the options A to D above are correct and included in a typical project financial study.

Submit
50. The following are the types of clauses that might be included in Supplementary Conditions EXCEPT: 

Explanation

The given answer is "Submittal requirements". This is because the question asks for the types of clauses that might be included in Supplementary Conditions, and all the other options (project insurance requirements, liquidated damage amounts, and tax exempt status of owner) are examples of clauses that could be included in Supplementary Conditions. Submittal requirements, on the other hand, are typically included in the General Conditions or other contract documents, rather than in the Supplementary Conditions.

Submit
51. True or False: It is not uncommon for a governing agency to dictate the design and construction process of any of the project delivery methods by their own rules or regulations. 

Explanation

It is not uncommon for a governing agency to dictate the design and construction process of any project delivery method by their own rules or regulations. This is because governing agencies often have specific guidelines and requirements in place to ensure that projects meet certain standards in terms of safety, quality, and compliance with regulations. By dictating the design and construction process, the governing agency can ensure that these standards are met and that the project is carried out in a manner that aligns with their objectives and priorities.

Submit
52. The purpose of an objective needs assessment is to:

Explanation

An objective needs assessment serves multiple purposes. It helps in testing and validating goals by assessing the current state and identifying the gaps. It also helps determine the space requirements by analyzing the resources and facilities needed. Additionally, it documents the expected performance levels to ensure that the goals are met. It confirms the budget by evaluating the financial resources available. Lastly, it prioritizes needs vs. wants to ensure that the most essential requirements are addressed first. Therefore, the correct answer is "All of the above".

Submit
53. A typical site studies often include: 

Explanation

A typical site study includes various aspects such as environmental issues, hazardous material assessment, subsurface conditions analysis, archeological surveys, and consideration of other governments, particularly Native Peoples. Therefore, the correct answer is "All of the above."

Submit
54. A requirement set by authority, custom, or general consensus which is established as an accepted criterion is called a:

Explanation

An industry standard refers to a requirement that is established and accepted by a particular industry or field. It is not mandated by authority or law, but rather emerges from the consensus and practices of professionals within the industry. Industry standards serve as guidelines for best practices, quality control, and interoperability among different products or services within the industry. They are often developed by professional organizations or trade associations to ensure consistency, safety, and efficiency in the industry.

Submit
55. The contractual relationship governed by the Conditions of the Contract is between:

Explanation

The correct answer is Owner and contractor. This is because the Conditions of the Contract govern the contractual relationship between the owner of the project and the contractor hired to carry out the construction work. The owner is responsible for providing the necessary funds and specifications, while the contractor is responsible for executing the project according to the agreed terms and conditions. The architect/engineer may be involved in the project as a consultant or advisor, but the primary contractual relationship is between the owner and the contractor.

Submit
56. When outside consultants are responsible for the production of major portions of the project specifications:

Explanation

When outside consultants are responsible for the production of major portions of the project specifications, it is important to have one design team member who is responsible for overall specification coordination. This ensures that there is clear communication and coordination between the different consultants and helps to avoid any confusion or conflicts in the specifications. Having one person in charge of this coordination also helps to streamline the process and ensure that all the specifications are consistent and cohesive.

Submit
57. Resource materials should be: 

Explanation

Resource materials should be permanently retained and accessible in order to ensure that they can be easily accessed and referred to whenever needed. This is important for various reasons such as future reference, auditing purposes, or in case any issues arise that require reviewing the materials. By retaining and making them accessible, it ensures that the necessary information and documentation are readily available, promoting efficiency and effectiveness in managing the resources.

Submit
58. True or False: Acceptance of final payment constitutes a waiver of claims by the contractor, subcontractor, and material supplier. 

Explanation

Acceptance of final payment constitutes a waiver of claims by the contractor, subcontractor, and material supplier. This means that once the final payment is accepted, these parties cannot make any further claims or seek additional compensation for the work or materials provided. By accepting the final payment, they are essentially indicating that they are satisfied with the payment received and have no further issues or claims to raise.

Submit
59. Which of the following is not a management expertise that contractors bring to the project delivery process?

Explanation

Contractors bring various management expertise to the project delivery process, such as knowledge of factors that influence cost, time, and quality. They also have the ability to manage cash flow and project accounting, as well as manage multiple subcontractors and suppliers. Additionally, contractors have experience with managing a construction budget in a risk-based setting. However, identifying codes and regulations applicable to the design is not specifically mentioned as a management expertise that contractors bring to the project delivery process.

Submit
60. Product equivalency, effect on the other aspects of the project, and warranty are the major factors to be considered for:

Explanation

When considering substitution requests, product equivalency is important to ensure that the substitute product meets the same standards and requirements as the original product. The effect on other aspects of the project is also crucial to assess if the substitution will have any negative impacts on the project timeline, budget, or quality. Additionally, warranty should be considered to ensure that the substitute product is covered by a suitable warranty.

Submit
61. The Design stage of a project includes all of the following EXCEPT:

Explanation

The Design stage of a project includes various activities such as design development, schematic design, and outline specifications. Feasibility studies, on the other hand, are typically conducted before the Design stage. These studies assess the viability and potential success of a project, including factors such as cost, resources, and potential risks. Therefore, feasibility studies are not part of the Design stage, making them the correct answer.

Submit
62. Reference Drawings serve which purpose:

Explanation

Reference drawings serve the purpose of showing construction related to the work, but which is not included in the contract. These drawings provide additional information about the project that may be helpful for understanding the context of the work being done. They can include details about existing structures or elements that are not directly part of the contract but are relevant to the project. These drawings help ensure that all parties involved have a comprehensive understanding of the scope of work.

Submit
63. Contractual clauses in the Conditions of the Contract:

Explanation

The correct answer is "Are expanded upon by the provisions of Division 01." This means that the contractual clauses in the Conditions of the Contract provide a basic framework or foundation, but the specific details and additional information are provided in Division 01. Division 01 further explains and expands upon the contractual clauses to provide more specific guidance and instructions for the project.

Submit
64. Which is true regarding level two specification section:

Explanation

The correct answer is A and B only. This means that level two specification sections should provide the widest latitude in describing a unit of work and should contain the broadest categories of work. This suggests that these sections should be comprehensive and detailed, allowing for a thorough description of the work to be done.

Submit
65. Which of the following is considered as part of the specifications?

Explanation

Division 1 is considered as part of the specifications. The specifications in a construction project typically include detailed information about the materials, methods, and quality standards that must be followed. Division 1, also known as the General Requirements, is a part of the specifications that covers administrative and procedural requirements for the project. It includes information about the project schedule, permits, inspections, and other general conditions that need to be met.

Submit
66. Substitution requirements and procedures during bidding

Explanation

The correct answer is that substitution requirements and procedures during bidding are stated in the instructions to bidders. This means that the specific rules and guidelines for substitutions are outlined in the instructions that are provided to potential bidders. These instructions serve as a reference for bidders to understand the requirements and procedures they need to follow when submitting their bids and considering any potential substitutions. It is important for bidders to carefully review and adhere to these instructions in order to ensure compliance with the bidding process.

Submit
67. True or False: Systems, materials, and products are selected during the schematic design phase. 

Explanation

During the schematic design phase, systems, materials, and products are not selected. This phase focuses on developing the overall concept and layout of the project, including the arrangement of spaces, circulation, and basic functionality. The selection of specific systems, materials, and products usually occurs during the design development phase, where more detailed decisions are made based on the established concept from the schematic design phase. Therefore, the statement that systems, materials, and products are selected during the schematic design phase is false.

Submit
68. Outline Specifications aid in the design process for all of the following EXCEPT:

Explanation

Outline Specifications are a tool used in the design process to provide detailed information about the materials, products, and construction methods required for a project. They help in revising cost estimates, schedules, and conducting value engineering studies to optimize project costs and timelines. They also serve as a checklist for selecting products that meet the project requirements. However, they do not serve as the basis for subcontracts in fast track construction. Subcontracts are typically based on legal agreements and contracts that outline the scope of work, responsibilities, and terms between the main contractor and subcontractors.

Submit
69. Outline specifications aid in the design process for all of the following except which one? 

Explanation

Outline specifications are used in the design process for revising cost estimates and schedules, conducting value engineering studies, and creating a checklist for selecting products. However, they do not serve as the basis for subcontracts in fast track construction. This means that outline specifications are not used to define the specific requirements and details of subcontracted work in fast track construction projects.

Submit
70. An alternate becomes part of the contract documents:

Explanation

The correct answer is "When stipulated in the Owner/Contractor Agreement." This means that an alternate becomes part of the contract documents only if it is specifically mentioned and outlined in the agreement between the owner and the contractor. The other options, such as when bids are opened or when the owner makes a decision, may be important steps in the process but do not guarantee that the alternate will be included in the contract. The recommendation of the architect/engineer (A/E) may also be considered, but ultimately it is the agreement between the owner and contractor that determines whether the alternate becomes part of the contract.

Submit
71. An alternate becomes part of the contract documents: 

Explanation

The correct answer is "When stipulated in the owner/contractor agreement." This means that an alternate becomes part of the contract documents only when it is specifically mentioned and agreed upon in the owner/contractor agreement. This agreement is a legally binding contract between the owner and the contractor that outlines the terms and conditions of the project. Therefore, if the inclusion of an alternate is not stipulated in this agreement, it will not be considered as part of the contract documents.

Submit
72. Submittal requirements for Facility Services Divisions 21 through 28 are specified in:

Explanation

The correct answer is Division 01 Section "Submittal Procedures". This is because the question is asking for the specific location where the submittal requirements for Facility Services Divisions 21 through 28 are specified. The other options mentioned, such as the first section in each respective division, Supplementary Conditions, and Section 01 12 00 Summary of Multiple Contracts, do not specifically mention the submittal requirements for these divisions. Therefore, Division 01 Section "Submittal Procedures" is the most appropriate answer.

Submit
73. The correct title for Division 10 is:

Explanation

The correct title for Division 10 is "Specialties" because Division 10 in construction refers to the category of specialty items and products that are not classified under other divisions. These specialty items include things like toilet accessories, partitions, fire protection equipment, and other miscellaneous construction materials that are not covered by the other divisions. Therefore, "Specialties" is the appropriate title for Division 10.

Submit
74. The Design Stage includes all of the following EXCEPT:

Explanation

The Design Stage includes activities such as reviewing the owner's program, schedule, and budget, as well as developing the design and creating schematic designs. However, it does not include Project Conception. Project Conception refers to the initial idea or concept for the project, which typically takes place before the Design Stage begins.

Submit
75. What information is found within Division 13 in the MasterFormat System?

Explanation

Division 13 in the MasterFormat System contains information about Special Construction. This division includes any unique or specialized construction elements that do not fit within the other divisions. It covers items such as pre-engineered buildings, swimming pools, domes, and other non-standard construction methods or materials.

Submit
76. The Contractor's superintendent:

Explanation

The correct answer is "All of the above". This means that all of the statements mentioned in the question are true for the Contractor's superintendent. The superintendent cannot be changed without the Owner's consent, and any communication given by the superintendent is binding, just as if it were given by the Contractor.

Submit
77. When interpreting contract documents, Architect/Engineer should:

Explanation

The Architect/Engineer should show no partiality to the Owner or Contractor when interpreting contract documents because their role is to be impartial and ensure fairness in the construction process. By not favoring one party over the other, they can maintain objectivity and ensure that the project is executed in accordance with the contract terms and the original design intent. This helps to protect the client's best interests and also safeguards the Architect/Engineer from potential liabilities that may arise from showing favoritism.

Submit
78. Facility managers should perform a postoccupancy evaluation how long after initial occupancy?

Explanation

Performing a postoccupancy evaluation three to six months after initial occupancy allows facility managers to gather sufficient data and feedback on the facility's performance and functionality. This timeframe allows occupants to settle into the space and identify any issues or areas for improvement. It also provides enough time for any initial problems to be addressed and resolved before conducting the evaluation. Performing the evaluation at this point ensures that any necessary adjustments can be made early on, leading to a more efficient and effective facility in the long run.

Submit
79. Which of the following is the proper sequence for an Addendum as illustrated in the PDPG?

Explanation

The proper sequence for an Addendum as illustrated in the PDPG is to first make changes to previous Addenda, then make changes to Procurement Requirements, followed by changes to Agreements and other contract forms, and finally make changes to specifications and drawings. This sequence ensures that any changes to previous addenda are addressed first, followed by changes to procurement requirements, and then changes to the agreement and other contract forms. Finally, any changes to specifications and drawings are made.

Submit
80. True or False: A punch list is generated by the A/E just prior to Substantial Completion. 

Explanation

A punch list is not generated by the A/E (Architect/Engineer) just prior to Substantial Completion. A punch list is typically created by the contractor or construction manager to document any remaining work or deficiencies that need to be addressed before the project can be considered complete. It is usually compiled towards the end of the construction process and is used as a checklist for the final inspection and completion of the project.

Submit
81. Which of the following would be appropriate to be included in the “Information Available to Bidders”?

Explanation

Geo-technical data is relevant to be included in the "Information Available to Bidders" because it provides crucial information about the soil and rock conditions at the site where the project will be constructed. This data helps bidders assess the feasibility and potential challenges of the project, determine appropriate construction methods, and accurately estimate costs and timelines. By including geo-technical data in the information available to bidders, it ensures that bidders have access to important information that can inform their decision-making and enable them to submit competitive and informed bids.

Submit
82. The following are all advantages gained by using standard agreement forms EXCEPT:

Explanation

Standard agreement forms do not accommodate choice from a wide variety of standard contract conditions. Instead, they offer a set of predetermined terms and conditions that parties can use without making significant changes. The other advantages mentioned in the options are all benefits of using standard agreement forms. Parties' familiarity with the forms helps streamline the negotiation process, uniformity of terminology ensures clarity and consistency, legal precedents provide guidance on interpreting the documents, and recognized customs result from the longstanding use of these forms.

Submit
83. A limitation of the design-build project delivery method is that the owner is less involved in the project design, including for example material selection

Explanation

The statement is true because in the design-build project delivery method, the owner has less involvement in the project design. This means that decisions regarding material selection, among other design aspects, are primarily made by the design-build team rather than the owner. This can be seen as a limitation because it reduces the owner's control and input in the design process, potentially leading to a project that may not fully align with the owner's preferences or requirements.

Submit
84. According to the BEES model, life cycle analysis (LCA) is characterized by all of the following EXCEPT:

Explanation

The BEES model focuses on providing estimates of the cumulative environmental impacts resulting from all stages of a product life cycle over a 50-year period. It also supports the selection of products with the lowest total environmental impact by considering questions regarding the materials and impacts related to the six stages of the product life cycle. However, it does not specifically address market analysis of demand for sustainable products.

Submit
85. The goal of the project is defined by the PDPG as:

Explanation

The goal of the project, as defined by the PDPG, is to deliver the facility to the owner. This means that the project should be completed and handed over to the owner within the agreed timeframe. It implies that all the necessary construction work and tasks should be completed efficiently and effectively. The focus is on ensuring that the facility is ready for use and meets the requirements and expectations of the owner.

Submit
86. All of the following are AIA Instruments of Change EXCEPT:

Explanation

The given question asks for an exception among the listed options, which are AIA Instruments of Change. A Field Order is not considered an AIA Instrument of Change.

Submit
87. All of the following are articles in PART 1, GENERAL EXCEPT:

Explanation

not-available-via-ai

Submit
88. True or False: The primary construction project team components are the Owner Team, Design Team, Contractor Team, Supplier Team, and the authorities having jurisdiction. 

Explanation

The given statement is false because the primary construction project team components are the Owner Team, Design Team, Contractor Team, and Supplier Team. The authorities having jurisdiction are not considered as a primary construction project team component.

Submit
89. Which of the following would be included in Available Information?

Explanation

The Available Information refers to the information that is accessible and can be used for decision-making purposes. In this context, the Environmental Impact Statement would be included in the Available Information as it provides crucial details about the potential environmental effects of the project. This statement helps stakeholders understand the project's impact on the environment and make informed decisions regarding its implementation.

Submit
90. Bidding Requirements:

Explanation

The correct answer is "Both A and B". This means that bidding requirements are not enforceable during the administration of the contract and they should not repeat Division 1. This suggests that the bidding requirements are separate from the contract administration and should not be repeated in the contract documents.

Submit
91. An affirmation of fact or promise made by the seller to the buyer that relates to the goods and becomes a part of the basis of the bargain creates . . .

Explanation

An express warranty is created when the seller affirms a fact or promise about the goods being sold, and this affirmation becomes a part of the basis of the bargain between the buyer and the seller. This means that the buyer can rely on this affirmation or promise as a guarantee of the quality, condition, or performance of the goods. Unlike implied warranties, which are automatically provided by law, an express warranty is specifically stated by the seller and can be written or spoken. Therefore, the correct answer is an express warranty.

Submit
92. All of the following are Articles in Part 3 Execution EXCEPT: 

Explanation

In Part 3 Execution, the focus is on carrying out or implementing a plan or process. The other options listed - Examination, Application, and System Startup - all involve taking action or performing tasks related to executing a plan. However, Fabrication refers to the act of creating or constructing something, which is not directly related to the execution of a plan. Therefore, Fabrication is the correct answer as it does not fit the category of Articles in Part 3 Execution.

Submit
93. Under the AIA A201, who has the responsibility to inspect the Work to determine if it is in proper condition to receive subsequent work?

Explanation

According to the AIA A201, the responsibility to inspect the work and determine if it is in proper condition to receive subsequent work lies with the Contractor. This means that it is the Contractor's duty to ensure that the work is completed correctly and is ready for the next phase of the project. The A/E, Owner, and Installing subcontractor may have their own inspections and responsibilities, but the ultimate responsibility for inspecting the work falls on the Contractor.

Submit
94. Under AIA A201, who has the responsibility to pay sales, consumer, use and similar taxes for the work provided?

Explanation

According to AIA A201, the responsibility to pay sales, consumer, use, and similar taxes for the work provided lies with the Contractor. This means that it is the Contractor's obligation to handle and pay any applicable taxes related to the work they have performed. The A/E (Architect/Engineer), Owner, and Installing subcontractor are not responsible for these taxes under AIA A201.

Submit
95. Objectives of a good maintenance program include all of the following except which one? 

Explanation



While implementing effective energy conservation practices is important, it is not directly related to the primary objectives of a good maintenance program. The main objectives typically focus on minimizing interruptions, failures of equipment, and facility structures that affect productivity, and selecting the best repair and replacement methods and materials. Energy conservation, while beneficial, is more aligned with operational efficiency and sustainability initiatives rather than core maintenance goals.
Submit
96. The goal of the ASTM sustainability standards, the EPA Energy Star program, and the NIST BEES program is to :

Explanation

The goal of the ASTM sustainability standards, the EPA Energy Star program, and the NIST BEES program is to provide a rational assessment of the environmental impact of building products. These programs aim to evaluate and measure the sustainability and environmental performance of building materials and products. By providing a standardized assessment, they enable consumers, architects, and builders to make informed decisions and choose products that have a lower environmental impact. This helps promote sustainable practices in the construction industry and contributes to reducing the overall environmental footprint of buildings.

Submit
97. The date of substantial completion is established by the: 

Explanation

The date of substantial completion is generally established by the A/E (Architect/Engineer). Substantial completion is a construction term indicating that a project has reached a stage where the owner can use it for its intended purpose, even though some minor tasks may remain. The architect or engineer overseeing the project typically determines when this stage is reached, based on their assessment of the construction's readiness and compliance with project specifications and regulations. While the contractor carries out the work, and the owner ultimately takes ownership, the A/E usually has the responsibility to certify when substantial completion has been achieved. This certification may involve inspections and coordination with authorities having jurisdiction to ensure all required permits and compliance have been met.

Submit
98. Which of the following is not a stage of the Facility Life Cycle?

Explanation

The correct answer is "Project permitting." The Facility Life Cycle consists of various stages involved in the development and management of a facility. These stages typically include project conception, design, procurement, construction, facility management, and project delivery. However, project permitting is not considered as a stage in the Facility Life Cycle. Project permitting refers to the process of obtaining the necessary permits and approvals from regulatory authorities before commencing construction or operation of a facility. While it is an important step in the overall project timeline, it is not considered a distinct stage within the Facility Life Cycle.

Submit
99. Which of the following is TRUE concerning application of integrated project delivery?

Explanation

The correct answer is team culture based upon problem resolution rather than determination of liability. This means that in integrated project delivery, the focus is on resolving issues and finding solutions rather than assigning blame or determining who is at fault. This promotes a collaborative and cooperative atmosphere where the team works together to overcome challenges and achieve the project's goals. This approach helps to reduce conflicts and arbitration expenses, as the team is more focused on problem-solving rather than engaging in legal disputes.

Submit
100. The following are TRUE concerning CSI's GreenFormat online product data resource EXCEPT:

Explanation

CSI does not validate and certify information contained in GreenFormat.

Submit
101. All of the following could be Articles in Part 1 of a specification EXCEPT:

Explanation

The other options listed (References, Action Submittals, Measurement and Payment) are commonly found in Part 1 of a specification, as they provide important information related to the project. However, Source Quality Control is typically addressed in Part 2 or later sections of a specification, as it pertains to the quality control processes for materials and products used in the project.

Submit
102. True or False: Record drawings and project manual provide adequate record documentation.

Explanation

Record drawings and project manuals do not provide adequate record documentation. While record drawings may provide visual documentation of the project, they may not capture all the necessary details and information. On the other hand, project manuals typically contain instructions and specifications for the project but may not include comprehensive documentation of the actual construction process. Therefore, additional documentation such as daily logs, progress reports, and change orders may be required to provide a more complete record of the project.

Submit
103. Which of the following is NOT defined as a contract modification by the PDPG?

Explanation

The PDPG defines a contract modification as a Change Order, Construction Change Directive/ Work Change Directive, and Architect's Supplemental Instruction/Field Order. However, it does not define an Addendum as a contract modification. Therefore, the correct answer is Addendum.

Submit
104. It is important for the long-term success of the facility's operations and maintenance that project closeout activities include all of the following except which one? 

Explanation

The receipt of the final punch list is not important for the long-term success of the facility's operations and maintenance. A punch list is a document that lists any incomplete or unsatisfactory work that needs to be addressed before the project is considered complete. While the completion of the punch list is important for the overall project closeout, it is not directly related to the long-term success of the facility's operations and maintenance. The other activities listed, such as start-up and load testing, demonstration for new operators, operational training if necessary, and commissioning, are all essential for ensuring the facility's long-term success.

Submit
105. The Uniform Location of Subject Matter jointly published by the EJCDC and AIA provides a recommended location of topics in all of the following except

Explanation

The Uniform Location of Subject Matter jointly published by the EJCDC and AIA provides a recommended location of topics in Supplementary Conditions, Division, and Agreement. However, it does not provide a recommended location for Drawings.

Submit
106. When is the CSI/CSC UniFormat most often used?

Explanation

The CSI/CSC UniFormat is most often used during project conception and schematic design. This format helps to organize information by materials and methods throughout the project life cycle. It is particularly useful in the early stages of a project when decisions about materials and methods need to be made. This format allows for better communication and coordination among project team members and helps to ensure that all necessary information is included in the project documentation.

Submit
107. True or False: Equipment and system review and training should occur immediately after substantial completion.

Explanation

Equipment and system review and training should not occur immediately after substantial completion. Instead, it should take place during the final stages of the project, closer to the actual completion date. This allows for any necessary adjustments or modifications to be made before the project is officially completed.

Submit
108. The dollar amounts of cash allowances are:

Explanation

The correct answer is "In Division 01". This means that the dollar amounts of cash allowances can be found in Division 01 of the project specifications. Division 01 typically includes general requirements and administrative information for the project. Therefore, it is likely that the specific details regarding cash allowances are provided in this section.

Submit
109. Green buildings are designed to reduce the overall impact of the built environment on human health and the natural environment by:

Explanation

Green buildings are designed to reduce the overall impact of the built environment on human health and the natural environment. This is achieved by efficiently using energy, water, and other resources, as well as protecting occupant health and improving employee productivity. The option "A and B only" correctly identifies the measures taken in green buildings to achieve these goals. Option "A and C only" is incorrect because it does not include the aspect of protecting occupant health and improving employee productivity, which is an important component of green building design.

Submit
110. The Supplementary Conditions must be carefully coordinated with all of the following EXCEPT:

Explanation

The Supplementary Conditions must be carefully coordinated with the General Conditions, Bidding Requirements, and Owner-Contractor Agreement. The Owner/Architect Agreement, however, does not need to be coordinated with the Supplementary Conditions. This is because the Owner/Architect Agreement primarily governs the relationship between the owner and the architect, whereas the Supplementary Conditions focus on additional project-specific requirements and conditions that supplement the main contract documents. Therefore, the Owner/Architect Agreement is not directly related to the coordination of the Supplementary Conditions.

Submit
111. Which of the following is not included in the quoted description of benefits that BIM brings to the design and construction process?

Explanation

The given correct answer is "Automated product characteristic/specification content coordination". This is not included in the quoted description of benefits that BIM brings to the design and construction process. The other options, such as opportunity for increased evaluation of design options, building components conflict identification and resolution, and BIM-driven product delivery scheduling, are all mentioned as benefits of BIM.

Submit
112. The following are TRUE about closed proprietary specifications EXCEPT: 

Explanation

Closed proprietary specifications refer to specifications that specify a particular manufacturer's product or brand name. These specifications typically include unique characteristics or features of the product. The A/E (architect/engineer) is responsible for coordinating the named product with other specification requirements. While multiple products may be named as options, closed proprietary specifications do not allow for substitutions without the owner's approval. Therefore, the correct answer is "Other products are allowed as substitutions upon approval of the owner."

Submit
113. Which of the following items should not be included in Section 01110?

Explanation

In Section 01110, which typically covers general requirements for the project, site traffic regulating during construction should not be included. This section usually focuses on the owner's responsibilities, contractor's responsibilities, and general project requirements. Site traffic regulation is typically covered under a separate section or specification that specifically addresses traffic control and safety measures during construction.

Submit
114. All of the following are examples of project soft costs except which one? 

Explanation

Soft costs refer to expenses that are not directly associated with the physical construction of a project. Relocation, commissioning, due diligence studies, and design fees are all examples of soft costs as they involve activities and services related to planning, coordination, and management of a project. However, topographical surveys are not considered soft costs because they are directly related to the physical aspects of a project, specifically the analysis and mapping of the land's surface features.

Submit
115. The general contract clauses that establish payment responsibilities are found in:

Explanation

The general contract clauses that establish payment responsibilities are typically found in the General Conditions. These are the standard terms and conditions that are included in most construction contracts. They outline the rights and obligations of both the contractor and the owner, including provisions related to payment. Division 01 General Requirements may also contain some payment-related clauses, but it is primarily focused on administrative and procedural requirements for the project. The Payment bond is a separate document that guarantees payment to subcontractors and suppliers, but it does not contain the actual payment responsibilities. Addenda are additional documents that modify or clarify the terms of the contract, but they do not typically establish payment responsibilities on their own.

Submit
116. Which of the following is NOT typically included in a set of construction drawings?

Explanation

Construction drawings, also known as blueprints, are technical documents used to guide the construction of a building or structure. They include detailed information about the project's design, dimensions, materials, and construction methods. While marketing brochures and renderings may be used to promote the project, they are not part of the formal construction documentation used by builders and contractors on site.

Submit
117. The following are true of reference standards, EXCEPT:

Explanation

Reference standards are documents that provide guidelines and specifications for various aspects of work. They are consensus documents developed by industry committees and are frequently incorporated into code requirements. They are included in specifications to avoid the need to reproduce lengthy requirements. However, reference standards are not meant to be relied upon by the specifier to describe the quality of work. The quality of work is typically described by other means, such as performance specifications or quality control measures.

Submit
118. Which of the following statements about Instructions for Procurement is true?

Explanation

Instructions for Procurement often use standard industry forms, such as those developed by organizations like AIA (American Institute of Architects) or FIDIC (International Federation of Consulting Engineers). These forms streamline the procurement process by providing a clear and consistent structure for bidding and contract information. While they may include attachments like the geotechnical report, they are not limited to private projects, and they are binding upon the Contractor once the contract is signed. Hence, option B is the correct answer.

Submit
119. True or False: GreenFormatTM is a web based searchable database where users can evaluate materials, products, and process, organized by UniformatTM . 

Explanation

GreenFormatTM is not a web-based searchable database organized by UniformatTM. Therefore, the correct answer is False.

Submit
120. True or False: The EPA's definition of a green building covers all three primary aspects of the built environment, siting, design and construction. 

Explanation

The EPA's definition of a green building does not cover all three primary aspects of the built environment, siting, design, and construction. The correct answer is False.

Submit
121. The document named "Available Information" is part of the:

Explanation

The document named "Available Information" is part of the Procurement Requirements. This document provides information that is relevant to the procurement process, such as details about the project, the bidding process, and any specific requirements that bidders need to meet. It is separate from the Instructions to Bidders, Contract Documents, and Specifications, which may contain different types of information related to the project. Therefore, the correct answer is Procurement Requirements.

Submit
122. In the CSI CDT program, construction document production is defined to be all of the following EXCEPT:

Explanation

The correct statement that does not align with the definition of construction document production in the CSI CDT program is "A process integral to the design phase of a project." This statement suggests that construction document production is an inherent part of the design phase, which is not accurate. In reality, construction document production is a distinct phase that comes after the design phase. During this phase, detailed documents are created based on finalized design decisions to guide the actual construction process. These documents include plans, specifications, schedules, and other essential information necessary for contractors to build the project according to the design intent. Therefore, construction document production is a separate activity from the design phase and involves its own set of tasks and objectives.

Submit
123. The Invitation to Bid/Advertisement for Bid includes all of the following EXCEPT:

Explanation

The Invitation to Bid/Advertisement for Bid includes all of the listed options except for "Details concerning bid security requirements." This means that the bid document will contain information about the right to reject bids and the governing laws and regulations, the bid opening date, time, and location, as well as the possibility of multiple prime contracts. However, it will not provide specific details about the bid security requirements.

Submit
124. In the specifications, the stated requirements address:

Explanation



Specifications in a construction contract are detailed documents that outline the requirements for various aspects of the project. They typically cover the responsibilities and expectations of all parties involved, including the owner, contractor, subcontractors, and architect. This ensures that everyone understands their roles and obligations, as well as the standards and materials to be used, methods of installation, and other critical details necessary for the successful completion of the project.
Submit
View My Results

Quiz Review Timeline (Updated): Oct 22, 2024 +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Oct 22, 2024
    Quiz Edited by
    ProProfs Editorial Team
  • Oct 24, 2016
    Quiz Created by
    Morganrae91
Cancel
  • All
    All (124)
  • Unanswered
    Unanswered ()
  • Answered
    Answered ()
True or False: Zoning is an example of a land development...
What are the three parts of the SectionFormat?
True or False: By executing the contract, the Contractor confirms that...
True or False: There is no difference between the construction...
Experienced owners may require project teams to utilize integrated...
Which of the following should be avoided in a specification?
Use of master guide specifications:
True or False: There being no contractual relationship between the A/E...
Special warranties/guarantees can: 
Drawings prepared by the contractor, subcontractor, or...
Which bond protects the owner from losing the benefit of an accepted...
An information organizing framework for the design and construction...
True or False: If a portion of the work is covered contrary to...
An information organizing framework for the A/E/C industry that...
True or False: Sustainability consultants can only be retained by the...
True or False: The A/E may withhold certification for payment in whole...
To be effective in communicating, specifications should be:
If the contractor is delayed in the progress of the Work by Owner, he...
True or False: Shop drawings are not contract documents.
True or False: The facility manager should not be involved in project...
As a result of the widely held misconception that a contractor's...
As a result of the widely held misconception that a contractor's...
Since he or she is most familiar with a product, the...
Marked-up or corrected contract drawings that indicate changes...
All of the following may be accomplished through issuing of a Change...
All of the following activities are associated with the project...
Integrated projects are distinguished by all of the following...
The parties to an owner/design-builder contract are::
The nationally-recognized California AIA "Integrated Project...
A unit price contract or contract portion is used when:
Lump Sum, Unit Price, or Cost-Plus-Fee constitute the basis of:
Under the AIA A201 and EJCDC C-700, who provides property insurance...
True or False: The OmniClass construction specification system is...
Under the AIA A201 and the EJCDC C-700, who has the authority to stop...
Under the AIA A201 and EJCDC C-700, who provides property insurance...
Which of these types of dimensions are likely to be included on one...
Marked up or corrected contract drawings that indicate changes...
Under AIA A201, who has the authority to stop the work, if...
True or False: Under a single-prime contract, the owner has a...
. One of the benefits of working as a team is not:
True or False: AIA Design Phases include schematic design, design...
True or False: As a project proceeds through the project delivery...
If the construction budget of a 50,000 square foot project is...
The mood that is recommended for specifications is:
The following are the types of clauses that might be included in...
All of the following subjects are usually included in Supplementary...
True or False: The A/E is required to determine the project delivery...
Which is true concerning MasterFormat?
Typical components of a project financial study include: 
The following are the types of clauses that might be included in...
True or False: It is not uncommon for a governing agency to dictate...
The purpose of an objective needs assessment is to:
A typical site studies often include: 
A requirement set by authority, custom, or general consensus which is...
The contractual relationship governed by the Conditions of the...
When outside consultants are responsible for the production of major...
Resource materials should be: 
True or False: Acceptance of final payment constitutes a waiver of...
Which of the following is not a management expertise that contractors...
Product equivalency, effect on the other aspects of the project, and...
The Design stage of a project includes all of the following EXCEPT:
Reference Drawings serve which purpose:
Contractual clauses in the Conditions of the Contract:
Which is true regarding level two specification section:
Which of the following is considered as part of the specifications?
Substitution requirements and procedures during bidding
True or False: Systems, materials, and products are selected during...
Outline Specifications aid in the design process for all of the...
Outline specifications aid in the design process for all of the...
An alternate becomes part of the contract documents:
An alternate becomes part of the contract documents: 
Submittal requirements for Facility Services Divisions 21 through 28...
The correct title for Division 10 is:
The Design Stage includes all of the following EXCEPT:
What information is found within Division 13 in the MasterFormat...
The Contractor's superintendent:
When interpreting contract documents, Architect/Engineer should:
Facility managers should perform a postoccupancy evaluation how long...
Which of the following is the proper sequence for an Addendum as...
True or False: A punch list is generated by the A/E just prior to...
Which of the following would be appropriate to be included in the...
The following are all advantages gained by using standard agreement...
A limitation of the design-build project delivery method is that the...
According to the BEES model, life cycle analysis (LCA) is...
The goal of the project is defined by the PDPG as:
All of the following are AIA Instruments of Change EXCEPT:
All of the following are articles in PART 1, GENERAL EXCEPT:
True or False: The primary construction project team components are...
Which of the following would be included in Available Information?
Bidding Requirements:
An affirmation of fact or promise made by the seller to the buyer that...
All of the following are Articles in Part 3 Execution EXCEPT: 
Under the AIA A201, who has the responsibility to inspect the Work to...
Under AIA A201, who has the responsibility to pay sales, consumer, use...
Objectives of a good maintenance program include all of the following...
The goal of the ASTM sustainability standards, the EPA Energy Star...
The date of substantial completion is established by the: 
Which of the following is not a stage of the Facility Life Cycle?
Which of the following is TRUE concerning application of integrated...
The following are TRUE concerning CSI's GreenFormat online product...
All of the following could be Articles in Part 1 of a specification...
True or False: Record drawings and project manual provide adequate...
Which of the following is NOT defined as a contract modification by...
It is important for the long-term success of the facility's operations...
The Uniform Location of Subject Matter jointly published by the EJCDC...
When is the CSI/CSC UniFormat most often used?
True or False: Equipment and system review and training should occur...
The dollar amounts of cash allowances are:
Green buildings are designed to reduce the overall impact of the built...
The Supplementary Conditions must be carefully coordinated with all of...
Which of the following is not included in the quoted description of...
The following are TRUE about closed proprietary specifications...
Which of the following items should not be included in Section 01110?
All of the following are examples of project soft costs except which...
The general contract clauses that establish payment responsibilities...
Which of the following is NOT typically included in a set of...
The following are true of reference standards, EXCEPT:
Which of the following statements about Instructions for Procurement...
True or False: GreenFormatTM is a web based searchable database where...
True or False: The EPA's definition of a green building covers all...
The document named "Available Information" is part of the:
In the CSI CDT program, construction document production is defined to...
The Invitation to Bid/Advertisement for Bid includes all of the...
In the specifications, the stated requirements address:
Alert!

Advertisement