All,
Please pay particular attention to the number of answers required for each question (i. E. "Choose 2"). On the actual exam, you will be reminded to choose the appropriate number of options, however in this practice exam if you do not choose the correct number of anwers, the question will be marked incorrect (for example, if you only select 1 See moreanswer rather than 2 that are required, the question will be marked as answered incorrectly, even if that 1 chosen answer was one of the correct options).
Good luck!
2
10
11
12
21
Rate this question:
The total plant and leaf area within a landscape
The environmental conditions specific to the landscape
The amount of water lost from a vegetated surface in units of water depth
The amount of water required to irrigate a species for a 24 hour period
Rate this question:
Yes
No
Not enough information
Rate this question:
LEED specifies high reflectivity surfaces should be cleaned at least every year
In sunny climates, window-shading devices will help mitigate glare from reflective roofing into the building
In the roof design, teams should consider including habitat for the animal and insect populations needed to pollinate the installed plantings
Properly designed green roofs do not require mowing or cutting
A vegetated roof can be installed as a complete system or as a modular system
Rate this question:
Greater, promote
Greater, inhibit
Less, promote
Less, inhibit
Rate this question:
The project achieves 1 point if at least 2 LEED APs are principal participants of the project team
The project achieves 1 point if at least 1 LEED Green Associate is the LEED Online project administrator
The project team earns 2 points if all of the principal participants of the project team are LEED APs
The project achieves 1 point if at least 1 LEED AP is a principal participant of the project team
Rate this question:
Developing an innovation in design strategy that focuses on a regional green building issue
Achieving credits that have been designated as regional priority credits
Achieving all of the credits in the sustainable sites category
Achieving credits that a project team decides are the most significant for their project's region
Rate this question:
Implementing hardscape materials with an SRI value of at least 18
Using an open-grid pavement system that is at least 25% pervious
Planting trees to provide shade
Provide shade from structures that have an SRI of at least 18
Rate this question:
Identify the climate zone
Calculate the performance rating
Determine the baseline system sizing
Identify the Energy Star Score for the project
Rate this question:
Use the average value of the 3 shifts
Use total number of all employees in 3 shifts
Use the median value of the 3 shifts
Use FTE of the shift with greatest number of employees
Rate this question:
NC
Schools
CS
NC and Schools
NC and CS
NC, Schools and CS
Rate this question:
Land clearing debris
Carpet
Excavated soil
Tiles containing asbestos
Interior walls painted with lead paint
Rate this question:
ASHRAE Advanced Energy Design Guide
ASHRAE 90.1-2007 Appendix G
Energy Star Target Finder
Core Performance Guide
ASHRAE 62.1-2007
Rate this question:
25%
30%
40%
95%
Rate this question:
Shared use (w/general public) of an auditorium, classroom, and parking facility
A contract with community for a commercial office and health clinic dedicated-use spaces in the building
Pedestrian access and approved student use of privately owned swimming pool and playing field
All of the above
Rate this question:
Measure of material’s ability to reject solar heat
Ratio of radiation emitted by a surface to radiation emitted by a black surface at the same temperature
Measure of the ability of a surface material to reflect sunlight (visible, infrared, and ultraviolet wavelengths)
Ability of a material to absorb sound, expressed as a fraction of incident sound
Rate this question:
Providing $2,300 worth of on-site renewable energy
Providing $1,500 worth of on-site renewable energy
Demonstrate energy cost savings of $5,000
Purchase $1,700 worth of electricity from renewable sources
Rate this question:
The air testing must be performed after the furniture is installed
3 sample locations are required for the project
Air samples must be collected within the breathing zone of 3 and 6 feet
Measurements must be taken during normal occupied hours
Rate this question:
Frequency of use / occupancy
Gender ratio
Building floor area
Types of water use fixtures
Water volume per fixture use
Rate this question:
Will be contracted to report results, findings and recommendations directly to the owner
Will review the Owners Project Requirements for project goals and expectations
Will review the Basis of Design documents for clarity and completeness, and consistency with the Owners Project Requirements
Is independent of the project's design and construction management team
Has documented commissioning authority experience for at least 1 building projects
Rate this question:
Meeting standards of ANSI/ASHRAE 62.1
Use of no refrigerants
Purchasing a one-year renewable energy contract to provide 25% of the building's electricity from renewable sources
Developing and incorporating commissioning requirements into construction documents
Rate this question:
May
June
July
September
Rate this question:
0
4
5
6
7
Rate this question:
Private offices
Lobby
Bathrooms
Retail floor
Bedrooms
Living rooms
Rate this question:
Undeveloped land with elevation equal to the 100 year flood plain
Developed land that is within 45 feet from stream
Developed site that is 110 feet from wetland
Undeveloped land with a plant identified under the threatened species list
Developed land that includes some areas of prime farmland
Right before move in
Within 1 month of occupancy
3 months of occupancy
6-18 months after occupancy
At 1 year of occupancy
Rate this question:
A project that complies with federal and state environmental laws, but not local environmental laws
A major renovation project that would like to certify floors 5-10
A project that includes in the LEED project boundary all contiguous land that supports normal building operations
A project with a gross floor area of 2,000 square feet and site area of 200,000 square feet
A project with a gross floor area of 900 square feet and site area of 9,000 square feet
Rate this question:
Climate zone, regional factor, density factor
Density factor, species factor, microclimate factor
Density factor, climate zone, evapotransiration factor
Species factor, maintenance factor, regional factor
Microclimate factor, efficiency factor, maintenance factor
Rate this question:
It does not vary and is always the same
USGBC Membership
When a team has previously registered a project, projects registered later are discounted
Varies based on the LEED Rating System and type of project
Rate this question:
0
1
2
3
Rate this question:
Reuse
Recycling
Incineration
Diverting to landfill
Both a and b
Both a and c
Rate this question:
2
4
6
8
Rate this question:
50%
75%
90%
95%
100%
Rate this question:
To encourage the use of local products
To maximize amount of pervious surfaces
To promote responsible use of Greenfield sites
To provide healthy outdoor spaces for building occupants
To conserve existing natural areas and promote biodiversity
Rate this question:
HVAC&R
Lighting and daylighting controls
Domestic hot water systems
Task-lighting systems
On-site renewable energy systems
Rate this question:
$15,000 Salvaged wood for doors
$38,000 FSC Pure countertops
$22,000 FSC Mixed for beams
$40,000 Non FSC certified new wood for veneers
$10,000 Reused wood for cabinets
Rate this question:
Cork flooring
Wool carpeting
Linoleum tiles
Sunflower seed countertops
Soy foam insulation
Ceramic wall tiles
Rate this question:
The new tenant
Project architect
Building owner
Project engineer
Rate this question:
Respond to all reviewer comments within 15 business days
Delete all documents submitted with the initial review
Clearly respond to each item where the reviewer has provided technical advice
Call the LEED reviewer to discuss the issues presented in the review comments
Upload any revised documentation to LEED Online
Rate this question:
Light exterior areas only for safety and comfort
Efficient task lights for all offices
Automatic controls for non-emergency interior lighting
Exterior openings to have automatically controlled closing mechanisms at night
Rate this question:
Is a contracted employee through the project design firm
Is not an employee or contractor of the project owner
Has documented commissioning authority experience on at least 1 other building project
Is not an employee of a contractor or construction manager holding construction contracts
Rate this question:
EAc2: Optimize Energy Performance
SSc4.4: Alternative Transportation - Parking Capacity
SSc5.1: Site Development: Maximize Open Space
SSc3: Brownfield Redevelopment
SSc6.1: Stormwater Design - Quantity
Rate this question:
Provide documentation of a comprehensive signage program in both the lobby and tenant spaces
Provide document of a comprehensive signage program and a project case study
Develop a video and a written case study to be displayed on the company website
Send a one-time newsletter to building tenants informing them of the on-going building tours highlighting the project's green building features
Rate this question:
Provide operable windows for all residences
Provide air sampling testing results for these floors
Install deck-to-deck partitions, spray foam insulation and separate ventilation
Conduct a blower door test in accordance with ASTM-779-03
Rate this question:
Full time employees
Building occupancy
Students, customers or visitors
Part time employees
Rate this question:
$29,059
$43,589
$50,853
$72,648
$101,707
Rate this question:
Interior entryway walls
3rd floor window assemblies and glazing
Decorative brick that was installed in the outside entrance
Existing foundation / slab on grade
Rate this question:
50% post-consumer, 0% pre-consumer
0% post-consumer, 25% pre-consumer
25% post-consumer, 0% pre-consumer
25% post-consumer, 25% pre-consumer
Rate this question:
Quiz Review Timeline (Updated): May 26, 2024 +
Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.