LEED AP Bd&c Practice Exam

Reviewed by Editorial Team
The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Yrgsustainabilit
Y
Yrgsustainabilit
Community Contributor
Quizzes Created: 3 | Total Attempts: 10,349
| Attempts: 240
SettingsSettings
Please wait...
  • 1/100 Questions

    What is ANSI/ASHRAE 62.1 standard used for? (Choose 1)

    • To determine the energy efficiency design baseline
    • For testing ventilation filters for removal efficiency
    • To determine minimum ventilation rates and acceptable indoor air quality
    • To specify minimum contaminant levels for Brownfield classification
Please wait...
LEED AP Bd&c Practice Exam - Quiz
About This Quiz

All,
Please pay particular attention to the number of answers required for each question (i. E. "Choose 2"). On the actual exam, you will be reminded to choose the appropriate number of options, however in this practice exam if you do not choose the correct number of anwers, the question will be marked incorrect (for example, if you only select 1 See moreanswer rather than 2 that are required, the question will be marked as answered incorrectly, even if that 1 chosen answer was one of the correct options).
Good luck!


Quiz Preview

  • 2. 

    A new office project will have 200 employees and anticipates an estimated 30 visitors / day. During peak periods, the building will be occupied by 210 occupants. The project team is trying to achieve SS Credit 4.2 Alternative Transportation: Bicycle Storage & Changing Rooms.  How many secure bicycle storage spaces will be required? 

    • 2

    • 10

    • 11

    • 12

    • 21

    Correct Answer
    A. 11
    Explanation
    The number of secure bicycle storage spaces required can be calculated by taking into account the number of employees, visitors, and peak occupancy. Since the project will have 200 employees, it is reasonable to assume that at least some of them will use bicycles. Additionally, with an estimated 30 visitors per day, it is possible that some of them may also use bicycles. Therefore, the total number of potential bicycle users can be calculated as 200 employees + 30 visitors = 230 potential bicycle users. Considering that the building will be occupied by 210 occupants during peak periods, it is safe to assume that not all potential bicycle users will be present at the same time. Therefore, it is reasonable to provide secure bicycle storage spaces for at least 11 bicycles to accommodate the potential demand.

    Rate this question:

  • 3. 

    What does evapotranspiration rate measure?

    • The total plant and leaf area within a landscape

    • The environmental conditions specific to the landscape

    • The amount of water lost from a vegetated surface in units of water depth

    • The amount of water required to irrigate a species for a 24 hour period

    Correct Answer
    A. The amount of water lost from a vegetated surface in units of water depth
    Explanation
    The evapotranspiration rate measures the amount of water lost from a vegetated surface in units of water depth. It is a measure of the combined processes of evaporation from the soil and transpiration from plants. This measurement is important in understanding the water cycle and managing water resources, as it helps determine the amount of water that needs to be replenished or irrigated in order to maintain a healthy vegetation cover.

    Rate this question:

  • 4. 

    A commercial office building with a footprint of 70,000 square feet has an overall site area of 200,000 square feet. The site is in an urban setting and the zoning requirement mandates a minimum of 20% of the net lot area must be public open space. The project design includes 15,000 square feet of pedestrian oriented hardscape and 18,000 square feet of vegetated open space. Does this project satisfy requirements for SS Credit 5.2 Site Development?

    • Yes

    • No

    • Not enough information

    Correct Answer
    A. Yes
    Explanation
    The project satisfies the requirements for SS Credit 5.2 Site Development because it includes 18,000 square feet of vegetated open space, which exceeds the minimum requirement of 20% of the net lot area. Additionally, it also includes 15,000 square feet of pedestrian-oriented hardscape, which contributes to the overall site development. Therefore, the project meets the criteria for SS Credit 5.2 Site Development.

    Rate this question:

  • 5. 

    All of the following statements are true of SS Credit 7.2 Heat Island Effect—Roof, EXCEPT:

    • LEED specifies high reflectivity surfaces should be cleaned at least every year

    • In sunny climates, window-shading devices will help mitigate glare from reflective roofing into the building

    • In the roof design, teams should consider including habitat for the animal and insect populations needed to pollinate the installed plantings

    • Properly designed green roofs do not require mowing or cutting

    • A vegetated roof can be installed as a complete system or as a modular system

    Correct Answer
    A. LEED specifies high reflectivity surfaces should be cleaned at least every year
    Explanation
    The given statement states that LEED specifies high reflectivity surfaces should be cleaned at least every year. However, this statement is not true for SS Credit 7.2 Heat Island Effect—Roof. Therefore, this statement is the correct answer for the question.

    Rate this question:

  • 6. 

    Impervious surfaces have a perviousness ______ than 50% and _____ runoff of water.

    • Greater, promote

    • Greater, inhibit

    • Less, promote

    • Less, inhibit

    Correct Answer
    A. Less, promote
    Explanation
    Impervious surfaces have a perviousness less than 50%, meaning they do not allow water to pass through easily. This lack of permeability inhibits the absorption of water into the ground, leading to increased runoff. Therefore, impervious surfaces promote the runoff of water.

    Rate this question:

  • 7. 

    Which of the following is true about ID Credit 2 LEED Accredited Professional? (Choose 1)

    • The project achieves 1 point if at least 2 LEED APs are principal participants of the project team

    • The project achieves 1 point if at least 1 LEED Green Associate is the LEED Online project administrator

    • The project team earns 2 points if all of the principal participants of the project team are LEED APs

    • The project achieves 1 point if at least 1 LEED AP is a principal participant of the project team

    Correct Answer
    A. The project achieves 1 point if at least 1 LEED AP is a principal participant of the project team
    Explanation
    The correct answer is that the project achieves 1 point if at least 1 LEED AP is a principal participant of the project team. This means that having at least one LEED AP involved in the project as a principal participant is sufficient to earn 1 point for ID Credit 2. It is not necessary for all principal participants to be LEED APs, and having more than one LEED AP does not earn additional points for this credit.

    Rate this question:

  • 8. 

    Regional Priority points are earned by: (Choose 1)

    • Developing an innovation in design strategy that focuses on a regional green building issue

    • Achieving credits that have been designated as regional priority credits

    • Achieving all of the credits in the sustainable sites category

    • Achieving credits that a project team decides are the most significant for their project's region

    Correct Answer
    A. Achieving credits that have been designated as regional priority credits
    Explanation
    Regional Priority points are earned by achieving credits that have been designated as regional priority credits. These credits are specific to a particular region and address important environmental issues or challenges faced by that region. By achieving these credits, a project team demonstrates their commitment to addressing regional sustainability concerns and earns additional points towards their green building certification.

    Rate this question:

  • 9. 

    The design team for a new construction project is aiming to earn one point  for SS Credit 7.1 Heat Island Effect – Non-Roof. The project site is 15,000 square feet with a 2,000 square feet of site hardscape. What strategy, if applied to 50% of the hardscape area, will allow the project team to achieve this credit? (Choose 1)

    • Implementing hardscape materials with an SRI value of at least 18

    • Using an open-grid pavement system that is at least 25% pervious

    • Planting trees to provide shade

    • Provide shade from structures that have an SRI of at least 18

    Correct Answer
    A. Planting trees to provide shade
    Explanation
    Planting trees to provide shade can help reduce the heat island effect on the project site. Trees provide natural shade, which can help lower the temperature of the hardscape area. This strategy can be applied to 50% of the hardscape area, allowing the project team to earn one point for SS Credit 7.1 Heat Island Effect - Non-Roof.

    Rate this question:

  • 10. 

    A project team is attempting to achieve 4 points for EA Credit 1 Optimize Energy Performance for a 15,000 square foot office building without using a building energy model.  What is the first task the project team must do? (Choose 1)

    • Identify the climate zone

    • Calculate the performance rating

    • Determine the baseline system sizing

    • Identify the Energy Star Score for the project

    Correct Answer
    A. Identify the climate zone
    Explanation
    The first task the project team must do is to identify the climate zone. This is because the climate zone will determine the specific requirements and strategies for optimizing energy performance in the office building. Without knowing the climate zone, it would be difficult for the project team to accurately calculate the performance rating, determine the baseline system sizing, or identify the Energy Star Score for the project.

    Rate this question:

  • 11. 

    A new manufacturing facility will have an employee shift schedule that includes three 8-hour shifts that do not overlap. The parking capacity does not exceed the minimum local zoning requirements. How would you calculate the number of required preferred carpool or vanpool parking spaces for SS Credit 4.4 Alternative Transportation: Parking Capacity?

    • Use the average value of the 3 shifts

    • Use total number of all employees in 3 shifts

    • Use the median value of the 3 shifts

    • Use FTE of the shift with greatest number of employees

    Correct Answer
    A. Use FTE of the shift with greatest number of employees
    Explanation
    To calculate the number of required preferred carpool or vanpool parking spaces for SS Credit 4.4 Alternative Transportation: Parking Capacity, you would use the FTE (Full-Time Equivalent) of the shift with the greatest number of employees. This means that you would consider the shift that has the most employees working during that time period. By using the FTE of this shift, you can determine the maximum number of parking spaces needed to accommodate the employees during that shift.

    Rate this question:

  • 12. 

    SS Prerequisite 2 Environmental Site Assessment applies to which building types under the LEED BD+C classification?

    • NC

    • Schools

    • CS

    • NC and Schools

    • NC and CS

    • NC, Schools and CS

    Correct Answer
    A. Schools
    Explanation
    The correct answer is Schools. The SS Prerequisite 2 Environmental Site Assessment applies specifically to schools under the LEED BD+C classification.

    Rate this question:

  • 13. 

    A recent major renovation project has just finished the demolition phase of the project and is calculating the product materials removed from the site as part of MR Credit 2 Construction Waste Management. If none of the products below are going to be reused or donated, which must be included in these calculations?

    • Land clearing debris

    • Carpet

    • Excavated soil

    • Tiles containing asbestos

    • Interior walls painted with lead paint

    Correct Answer
    A. Carpet
    Explanation
    Carpet must be included in the calculations because it is one of the products that are being removed from the construction site and will not be reused or donated. The question states that the project is calculating the product materials removed as part of MR Credit 2 Construction Waste Management, so all products that are not going to be reused or donated need to be included in the calculations.

    Rate this question:

  • 14. 

    What is the reference standard that defines the requirements for LEED energy modeling?

    • ASHRAE Advanced Energy Design Guide

    • ASHRAE 90.1-2007 Appendix G

    • Energy Star Target Finder

    • Core Performance Guide

    • ASHRAE 62.1-2007

    Correct Answer
    A. ASHRAE 90.1-2007 Appendix G
    Explanation
    ASHRAE 90.1-2007 Appendix G is the reference standard that defines the requirements for LEED energy modeling.

    Rate this question:

  • 15. 

    What is the overall % recycled content a project must earn in order to achieve an ID credit for exemplary performance under MR Credit 4 Recycled Content? 

    • 25%

    • 30%

    • 40%

    • 95%

    Correct Answer
    A. 30%
    Explanation
    In order to achieve an ID credit for exemplary performance under MR Credit 4 Recycled Content, a project must earn an overall % recycled content of 30%. This means that at least 30% of the materials used in the project must be made from recycled content.

    Rate this question:

  • 16. 

    A team plans to integrate SS Credit 10 Joint use of Facilities on a school project.  Which of the following would be acceptable LEED strategies in achieving this credit?

    • Shared use (w/general public) of an auditorium, classroom, and parking facility

    • A contract with community for a commercial office and health clinic dedicated-use spaces in the building

    • Pedestrian access and approved student use of privately owned swimming pool and playing field

    • All of the above

    Correct Answer
    A. All of the above
    Explanation
    All of the above options would be acceptable LEED strategies in achieving SS Credit 10 Joint use of Facilities on a school project. Shared use of facilities with the general public promotes community engagement and efficient use of resources. A contract with the community for dedicated-use spaces in the building encourages collaboration and integration. Pedestrian access and approved student use of privately owned facilities promote active transportation and utilization of existing resources.

    Rate this question:

  • 17. 

    Emissivity refers to: 

    • Measure of material’s ability to reject solar heat

    • Ratio of radiation emitted by a surface to radiation emitted by a black surface at the same temperature

    • Measure of the ability of a surface material to reflect sunlight (visible, infrared, and ultraviolet wavelengths)

    • Ability of a material to absorb sound, expressed as a fraction of incident sound

    Correct Answer
    A. Ratio of radiation emitted by a surface to radiation emitted by a black surface at the same temperature
    Explanation
    Emissivity refers to the ratio of radiation emitted by a surface to radiation emitted by a black surface at the same temperature. This means that it measures how efficiently a surface emits thermal radiation compared to a perfect black body. A higher emissivity value indicates that a surface emits more radiation, while a lower value indicates that it emits less radiation.

    Rate this question:

  • 18. 

    A project team is looking to pursue an ID credit on their new office building. The annual building energy cost for their 400,000 square foot project is $15,120. Which of the following tactics would earn credit for exemplary performance? (Choose 1)

    • Providing $2,300 worth of on-site renewable energy

    • Providing $1,500 worth of on-site renewable energy

    • Demonstrate energy cost savings of $5,000

    • Purchase $1,700 worth of electricity from renewable sources

    Correct Answer
    A. Providing $2,300 worth of on-site renewable energy
    Explanation
    Providing $2,300 worth of on-site renewable energy would earn credit for exemplary performance because it exceeds the minimum requirement for demonstrating commitment to renewable energy. This tactic shows that the project team is actively investing in sustainable energy sources, which aligns with the goal of reducing the environmental impact of the building.

    Rate this question:

  • 19. 

    A new office project is conducting an air quality test to demonstrate compliance with IEQ Credit 3.2 Construction IAQ Management Plan, Before Occupancy. The 65,000 square foot project runs under one ventilation system. All finishes are complete and have been installed, except for the movable furniture which is to be installed within the next 2 days. All of the following statements are true in regards to the project team's approach to meeting this credit EXCEPT: (Choose 1) 

    • The air testing must be performed after the furniture is installed

    • 3 sample locations are required for the project

    • Air samples must be collected within the breathing zone of 3 and 6 feet

    • Measurements must be taken during normal occupied hours

    Correct Answer
    A. The air testing must be performed after the furniture is installed
    Explanation
    The air testing does not need to be performed after the furniture is installed.

    Rate this question:

  • 20. 

    Which of the following does not play a role in determining the baseline for WE Prerequisite 1 Water Use Reduction? (Choose 1)

    • Frequency of use / occupancy

    • Gender ratio

    • Building floor area

    • Types of water use fixtures

    • Water volume per fixture use

    Correct Answer
    A. Building floor area
    Explanation
    The baseline for WE Prerequisite 1 Water Use Reduction is determined by factors such as the frequency of use/occupancy, types of water use fixtures, and water volume per fixture use. However, the building floor area does not play a role in determining the baseline for this prerequisite.

    Rate this question:

  • 21. 

    A project is pursing EA Prerequisite 1 Fundamental Commissioning of Building Energy Systems. In order for the project to meet the requirements, the team must designate a CxA who complies with all of the following EXCEPT: (Choose 1)

    • Will be contracted to report results, findings and recommendations directly to the owner

    • Will review the Owners Project Requirements for project goals and expectations

    • Will review the Basis of Design documents for clarity and completeness, and consistency with the Owners Project Requirements

    • Is independent of the project's design and construction management team

    • Has documented commissioning authority experience for at least 1 building projects

    Correct Answer
    A. Has documented commissioning authority experience for at least 1 building projects
    Explanation
    The correct answer is "Has documented commissioning authority experience for at least 1 building projects." The other options are all requirements that the CxA must comply with in order for the project to meet the prerequisites.

    Rate this question:

  • 22. 

    Points can be earned in the Energy & Atmosphere credit category by: (Choose 1)

    • Meeting standards of ANSI/ASHRAE 62.1

    • Use of no refrigerants

    • Purchasing a one-year renewable energy contract to provide 25% of the building's electricity from renewable sources

    • Developing and incorporating commissioning requirements into construction documents

    Correct Answer
    A. Use of no refrigerants
    Explanation
    Points can be earned in the Energy & Atmosphere credit category by using no refrigerants. This means that the building does not use any substances that contribute to the depletion of the ozone layer or have a high global warming potential. By avoiding the use of refrigerants, the building can reduce its environmental impact and contribute to a more sustainable and energy-efficient design.

    Rate this question:

  • 23. 

    For what month does LEED require you to use when determining the evapotranspiration rate?

    • May

    • June

    • July

    • September

    Correct Answer
    A. July
    Explanation
    LEED requires the use of July when determining the evapotranspiration rate. Evapotranspiration is the process by which water is transferred from the land to the atmosphere through evaporation from the soil and transpiration from plants. July is typically the month with the highest evapotranspiration rate due to its warmer temperatures and longer days. Therefore, using the evapotranspiration rate from July allows for more accurate calculations and considerations in sustainable building design.

    Rate this question:

  • 24. 

    A new development is being built on a .5 acre greenfield site. Within 1/2 mile of the site, basic services include 3 restaurants, a bank, 2 grocery stores and a post office. In addition, the development plans to have a coffee shop on the ground floor of the building. How many basic services can the project count towards SSc2 Community Connectivity?

    • 0

    • 4

    • 5

    • 6

    • 7

    Correct Answer
    A. 0
    Explanation
    The project can count 0 basic services towards SSc2 Community Connectivity because the coffee shop on the ground floor of the building is not considered a basic service.

    Rate this question:

  • 25. 

    A new multi-use project is planned and will include retail, office space and residential units. The project is pursuing IEQ Credit 8.1 Daylight and Views, Daylight. What area can be excluded from the calculations because they are not considered regularly occupied spaces? (Choose 2)

    • Private offices

    • Lobby

    • Bathrooms

    • Retail floor

    • Bedrooms

    • Living rooms

    Correct Answer(s)
    A. Lobby
    A. Bathrooms
    Explanation
    The lobby and bathrooms can be excluded from the calculations because they are not considered regularly occupied spaces. Regularly occupied spaces typically refer to areas where people spend a significant amount of time, such as private offices, bedrooms, and living rooms. The lobby is a transitional area and the bathrooms are typically used for short durations, so they are not considered as spaces where people regularly occupy.

    Rate this question:

  • 26. 

    In order to comply with SS Credit 1 Site Selection, which of the following site locations would be most appropriate to build a new multi-family development?

    • Undeveloped land with elevation equal to the 100 year flood plain

    • Developed land that is within 45 feet from stream

    • Developed site that is 110 feet from wetland

    • Undeveloped land with a plant identified under the threatened species list

    • Developed land that includes some areas of prime farmland

    Correct Answer
    A. Developed site that is 110 feet from wetland
  • 27. 

    A project team is developing a Thermal Occupant Survey in compliance with IEQ Credit 7.2 Thermal Comfort, Verification. When does the Survey need to be distributed and completed by the occupants?

    • Right before move in

    • Within 1 month of occupancy

    • 3 months of occupancy

    • 6-18 months after occupancy

    • At 1 year of occupancy

    Correct Answer
    A. 6-18 months after occupancy
    Explanation
    The Thermal Occupant Survey needs to be distributed and completed by the occupants 6-18 months after occupancy. This allows for a sufficient amount of time for the occupants to settle into the space and experience the thermal comfort conditions. By waiting 6-18 months, the survey results will be more accurate and reflective of the long-term thermal comfort performance of the building.

    Rate this question:

  • 28. 

    Which of the following projects would meet the LEED-NC Minimum Program Requirements? (Choose 1)

    • A project that complies with federal and state environmental laws, but not local environmental laws

    • A major renovation project that would like to certify floors 5-10

    • A project that includes in the LEED project boundary all contiguous land that supports normal building operations

    • A project with a gross floor area of 2,000 square feet and site area of 200,000 square feet

    • A project with a gross floor area of 900 square feet and site area of 9,000 square feet

    Correct Answer
    A. A project that includes in the LEED project boundary all contiguous land that supports normal building operations
    Explanation
    A project that includes in the LEED project boundary all contiguous land that supports normal building operations would meet the LEED-NC Minimum Program Requirements. This means that the project includes all the land that is directly connected to the building and is necessary for its normal operations. This ensures that the project takes into account the environmental impact of the entire site and not just the building itself.

    Rate this question:

  • 29. 

    A new multi-family project is implementing water efficient landscaping for the surrounding grounds. The plan currently includes 5,000 square feet of mixed vegetation and 2,000 square feet of pedestrian hardscape. In order to calculate the landscape coefficient to meet the requirements of WE Credit 1: Water Efficient Landscaping, what factors does the project team need to identify about the project's landscaping? (Choose 1)

    • Climate zone, regional factor, density factor

    • Density factor, species factor, microclimate factor

    • Density factor, climate zone, evapotransiration factor

    • Species factor, maintenance factor, regional factor

    • Microclimate factor, efficiency factor, maintenance factor

    Correct Answer
    A. Density factor, species factor, microclimate factor
    Explanation
    The project team needs to identify the density factor, species factor, and microclimate factor about the project's landscaping in order to calculate the landscape coefficient for water efficient landscaping.

    Rate this question:

  • 30. 

    When does a project registration fee vary? 

    • It does not vary and is always the same

    • USGBC Membership

    • When a team has previously registered a project, projects registered later are discounted

    • Varies based on the LEED Rating System and type of project

    Correct Answer
    A. USGBC Membership
    Explanation
    The project registration fee varies based on USGBC Membership.

    Rate this question:

  • 31. 

    A project team is trying to determine how many points they can achieve from their products containing rapidly renewable materials. The overall project materials budget is $7,295,000. Wool carpeting contributes $50,000 and cotton batt insulation contributes $90,000. In addition, sunflower seed countertops throughout the project contribute $32,000. How many points does this project achieve under MR Credit 6 Radidly Renewable Materials? 

    • 0

    • 1

    • 2

    • 3

    Correct Answer
    A. 0
    Explanation
    The project does not achieve any points under MR Credit 6 Radidly Renewable Materials because the total cost of the rapidly renewable materials used in the project is $50,000 + $90,000 + $32,000 = $172,000, which is less than the overall project materials budget of $7,295,000.

    Rate this question:

  • 32. 

    An example of waste diversion, as specified in MR Prerequsite 1 Storage and Collection of Recyclables, is:

    • Reuse

    • Recycling

    • Incineration

    • Diverting to landfill

    • Both a and b

    • Both a and c

    Correct Answer
    A. Both a and b
    Explanation
    The correct answer is "Both a and b." Waste diversion refers to the practice of diverting waste from the landfill and finding alternative uses for it. Reuse involves finding ways to use items again instead of throwing them away, while recycling involves processing waste materials to create new products. Both of these practices contribute to waste diversion by reducing the amount of waste that ends up in landfills. Incineration and diverting to landfill are not examples of waste diversion, as they involve disposing of waste rather than finding alternative uses for it.

    Rate this question:

  • 33. 

    How many credits do project teams have to choose from to achieve points for Regional Priority? (Choose 1)

    • 2

    • 4

    • 6

    • 8

    Correct Answer
    A. 6
    Explanation
    Project teams have to choose from 6 credits to achieve points for Regional Priority.

    Rate this question:

  • 34. 

    A new project is seeking an ID credit by achieving exemplary performance for MR Credit 2 Construction Waste Management. What is the percentage of waste that needs to be diverted to achieve this goal? 

    • 50%

    • 75%

    • 90%

    • 95%

    • 100%

    Correct Answer
    A. 95%
    Explanation
    To achieve exemplary performance for MR Credit 2 Construction Waste Management, the project needs to divert 95% of its waste. This means that only 5% of the waste generated during construction should end up in landfills or incinerators. By diverting such a high percentage of waste, the project demonstrates a commitment to reducing its environmental impact and promoting sustainable waste management practices.

    Rate this question:

  • 35. 

    The primary intent of SS Credit 5.1 Site Development – Protect or Restore Habitat is:

    • To encourage the use of local products

    • To maximize amount of pervious surfaces

    • To promote responsible use of Greenfield sites

    • To provide healthy outdoor spaces for building occupants

    • To conserve existing natural areas and promote biodiversity

    Correct Answer
    A. To conserve existing natural areas and promote biodiversity
    Explanation
    The primary intent of SS Credit 5.1 Site Development – Protect or Restore Habitat is to conserve existing natural areas and promote biodiversity. This credit is part of the LEED certification system, which focuses on sustainable building practices. By conserving natural areas and promoting biodiversity, the credit aims to protect and enhance the ecological value of the site. This can be achieved through measures such as preserving existing vegetation, creating wildlife habitats, and minimizing the impact of development on natural ecosystems.

    Rate this question:

  • 36. 

    LEED requires commissioning process activities be completed for all of the following energy-related systems on a project EXCEPT (choose 1)

    • HVAC&R

    • Lighting and daylighting controls

    • Domestic hot water systems

    • Task-lighting systems

    • On-site renewable energy systems

    Correct Answer
    A. Task-lighting systems
    Explanation
    LEED requires commissioning process activities to be completed for HVAC&R systems, lighting and daylighting controls, domestic hot water systems, and on-site renewable energy systems. However, it does not require commissioning for task-lighting systems.

    Rate this question:

  • 37. 

    Which of the following products would be included as part of the total wood cost for MR Credit 7 Certified Wood calculations? (Choose 3)

    • $15,000 Salvaged wood for doors

    • $38,000 FSC Pure countertops

    • $22,000 FSC Mixed for beams

    • $40,000 Non FSC certified new wood for veneers

    • $10,000 Reused wood for cabinets

    Correct Answer(s)
    A. $38,000 FSC Pure countertops
    A. $22,000 FSC Mixed for beams
    A. $40,000 Non FSC certified new wood for veneers
    Explanation
    The correct answer is $38,000 FSC Pure countertops, $22,000 FSC Mixed for beams, and $40,000 Non FSC certified new wood for veneers. These three products would be included in the total wood cost for MR Credit 7 Certified Wood calculations because they are all made from wood and contribute to the overall wood consumption of the project. The salvaged wood for doors, reused wood for cabinets, and FSC certified wood for countertops would not be included in the calculation because they are not part of the total wood cost.

    Rate this question:

  • 38. 

    Which of the following products would NOT contribute to MR Credit 6 Rapidly Renewable Materials? (Choose 1)

    • Cork flooring

    • Wool carpeting

    • Linoleum tiles

    • Sunflower seed countertops

    • Soy foam insulation

    • Ceramic wall tiles

    Correct Answer
    A. Ceramic wall tiles
    Explanation
    Ceramic wall tiles would not contribute to MR Credit 6 Rapidly Renewable Materials because they are not made from rapidly renewable materials. Rapidly renewable materials are those that can be harvested or replenished within a short period of time, typically less than 10 years. While cork flooring, wool carpeting, linoleum tiles, sunflower seed countertops, and soy foam insulation are all examples of materials that can be rapidly replenished, ceramic wall tiles are typically made from clay and other minerals that are not considered rapidly renewable.

    Rate this question:

  • 39. 

    SS Credit 9 Tenant Design and Construction Guidelines should be drafted with input from which team member(s)? (Choose 3)

    • The new tenant

    • Project architect

    • Building owner

    • Project engineer

    Correct Answer(s)
    A. Project architect
    A. Building owner
    A. Project engineer
    Explanation
    The Tenant Design and Construction Guidelines should be drafted with input from the project architect, building owner, and project engineer. The project architect is responsible for the design and layout of the space, ensuring it meets the tenant's needs and adheres to any building codes or regulations. The building owner has a vested interest in ensuring the guidelines align with their overall vision for the property. The project engineer provides technical expertise and insight into the feasibility and practicality of design choices. Together, these team members can collaborate to create comprehensive and effective guidelines for the tenant's design and construction process.

    Rate this question:

  • 40. 

    After submitting the Design Review for a project, a project team receives several clarification requests from the project reviewer. What should the project team do? (Choose 2)

    • Respond to all reviewer comments within 15 business days

    • Delete all documents submitted with the initial review

    • Clearly respond to each item where the reviewer has provided technical advice

    • Call the LEED reviewer to discuss the issues presented in the review comments

    • Upload any revised documentation to LEED Online

    Correct Answer(s)
    A. Clearly respond to each item where the reviewer has provided technical advice
    A. Upload any revised documentation to LEED Online
    Explanation
    The project team should clearly respond to each item where the reviewer has provided technical advice because this will help address any concerns or issues raised by the reviewer and demonstrate that the team has carefully considered and addressed the feedback. Additionally, the team should upload any revised documentation to LEED Online to ensure that the updated information is available for review and evaluation.

    Rate this question:

  • 41. 

    A team plans to incorporate light pollution reduction strategies in their office building project. Which of the following strategies is NOT a LEED-recognized strategy for SS Credit 8 Light Pollution Reduction on NC projects?

    • Light exterior areas only for safety and comfort

    • Efficient task lights for all offices

    • Automatic controls for non-emergency interior lighting

    • Exterior openings to have automatically controlled closing mechanisms at night

    Correct Answer
    A. Efficient task lights for all offices
    Explanation
    Efficient task lights for all offices is not a LEED-recognized strategy for SS Credit 8 Light Pollution Reduction on NC projects. The other options, such as light exterior areas only for safety and comfort, automatic controls for non-emergency interior lighting, and exterior openings with automatically controlled closing mechanisms at night, are recognized strategies for reducing light pollution.

    Rate this question:

  • 42. 

    The project owner of a 100,000 square foot retail center has asked the project team to hire the Commissioning Authority in order to achieve EA Credit 3 Enhanced Commissioning. The project team should choose a Commissioning Authority that: (Choose 1)

    • Is a contracted employee through the project design firm

    • Is not an employee or contractor of the project owner

    • Has documented commissioning authority experience on at least 1 other building project

    • Is not an employee of a contractor or construction manager holding construction contracts

    Correct Answer
    A. Is not an employee of a contractor or construction manager holding construction contracts
    Explanation
    The project team should choose a Commissioning Authority that is not an employee of a contractor or construction manager holding construction contracts because this ensures that the Commissioning Authority will provide an unbiased and independent assessment of the project. If the Commissioning Authority is employed by a contractor or construction manager, there may be a conflict of interest that could compromise the integrity and objectivity of the commissioning process. Therefore, selecting a Commissioning Authority who is not affiliated with any contractor or construction manager helps to ensure the effectiveness and credibility of the commissioning process.

    Rate this question:

  • 43. 

    A project team is installing a green roof on their urban office project. The team has designed the vegetated roof for 100% of the project roof area to achieve SS Credit 7.1 Heat Island Effect - Roof. Which of the following credits will this strategy NOT have an effect on? (Choose 2)

    • EAc2: Optimize Energy Performance

    • SSc4.4: Alternative Transportation - Parking Capacity

    • SSc5.1: Site Development: Maximize Open Space

    • SSc3: Brownfield Redevelopment

    • SSc6.1: Stormwater Design - Quantity

    Correct Answer(s)
    A. SSc4.4: Alternative Transportation - Parking Capacity
    A. SSc3: Brownfield Redevelopment
    Explanation
    Installing a green roof will not have an effect on the Alternative Transportation - Parking Capacity credit because it is focused on promoting alternative modes of transportation such as walking, biking, or public transportation, rather than the physical characteristics of the building. Additionally, it will not have an effect on the Brownfield Redevelopment credit, as this credit is focused on the remediation and reuse of contaminated sites, which is unrelated to the installation of a green roof.

    Rate this question:

  • 44. 

    A project is pursing an Innovation in Design point for a comprehensive green education plan. Which of the following strategies or combination of strategies could the project team use to achieve the ID point? (Choose 1)

    • Provide documentation of a comprehensive signage program in both the lobby and tenant spaces

    • Provide document of a comprehensive signage program and a project case study

    • Develop a video and a written case study to be displayed on the company website

    • Send a one-time newsletter to building tenants informing them of the on-going building tours highlighting the project's green building features

    Correct Answer
    A. Provide document of a comprehensive signage program and a project case study
    Explanation
    The project team can achieve the Innovation in Design point by providing documentation of a comprehensive signage program and a project case study. This strategy demonstrates a commitment to green education by showcasing the project's sustainable features through signage and providing a detailed case study that highlights the project's green building practices. This approach ensures that both visual and written materials are available to educate and inform building occupants and visitors about the project's sustainability efforts.

    Rate this question:

  • 45. 

    A new apartment complex is being built and will allow smoking on 2 of the middle floors. How should the project team demonstrate compliance with IEQ Prerequisite 2 Environmental Tobacco Smoke Control for the residences on these floors?(Choose 1)

    • Provide operable windows for all residences

    • Provide air sampling testing results for these floors

    • Install deck-to-deck partitions, spray foam insulation and separate ventilation

    • Conduct a blower door test in accordance with ASTM-779-03

    Correct Answer
    A. Conduct a blower door test in accordance with ASTM-779-03
    Explanation
    The project team should conduct a blower door test in accordance with ASTM-779-03 to demonstrate compliance with IEQ Prerequisite 2 Environmental Tobacco Smoke Control for the residences on the middle floors allowing smoking. This test measures the air tightness of the building envelope and helps identify any leaks or gaps that could allow the transfer of smoke between units. By conducting this test, the project team can ensure that the smoke from the designated smoking floors does not infiltrate the non-smoking floors, thus controlling environmental tobacco smoke.

    Rate this question:

  • 46. 

    Which of the following is NOT considered when calculating full-time equivalent (FTE)?

    • Full time employees

    • Building occupancy

    • Students, customers or visitors

    • Part time employees

    Correct Answer
    A. Building occupancy
    Explanation
    When calculating full-time equivalent (FTE), building occupancy is not considered. FTE is a measure used to determine the number of full-time employees that could be supported by the resources available. It takes into account the number of full-time and part-time employees, as well as students, customers, or visitors. However, building occupancy, which refers to the number of people occupying a building, is not directly related to the calculation of FTE.

    Rate this question:

  • 47. 

    A new bank project is implementing high energy efficiency strategies to support their goal to achieve 10 LEED points under EA Credit 1 Optimize Energy Performance. Process energy for the bank makes up 35% of the energy costs for the project. A whole building energy simulation resulted in $145,295 for the bank. What should the project team target as their design case energy cost savings in order to reach their EA Credit 1 Optimize Energy Performance goals?  

    • $29,059

    • $43,589

    • $50,853

    • $72,648

    • $101,707

    Correct Answer
    A. $43,589
    Explanation
    The project team should target $43,589 as their design case energy cost savings in order to reach their EA Credit 1 Optimize Energy Performance goals. This can be calculated by multiplying the total energy cost of $145,295 by the percentage of process energy for the bank (35%).

    Rate this question:

  • 48. 

    A project is undergoing major renovation that will include reusing much of building exterior walls and floors. Which of the project materials and areas below can be included in calculations for achieving MR Credit 1.1 Building Reuse, Maintain Existing Walls, Floors and Roof? (Choose 1)

    • Interior entryway walls

    • 3rd floor window assemblies and glazing

    • Decorative brick that was installed in the outside entrance

    • Existing foundation / slab on grade

    Correct Answer
    A. Existing foundation / slab on grade
    Explanation
    The correct answer is "existing foundation / slab on grade" because MR Credit 1.1 Building Reuse, Maintain Existing Walls, Floors and Roof focuses on reusing existing materials in the project. The foundation and slab on grade are part of the building structure and can be reused, contributing to the achievement of the credit. The other options mentioned, such as interior entryway walls, window assemblies, glazing, and decorative brick, are not part of the building's exterior walls and floors, and therefore cannot be included in the calculations for this credit.

    Rate this question:

  • 49. 

    What is the default recycled content value for steel?

    • 50% post-consumer, 0% pre-consumer

    • 0% post-consumer, 25% pre-consumer

    • 25% post-consumer, 0% pre-consumer

    • 25% post-consumer, 25% pre-consumer

    Correct Answer
    A. 25% post-consumer, 0% pre-consumer
    Explanation
    Steel has a default recycled content value of 25% post-consumer, which means that 25% of the steel used in production comes from recycled materials that were previously used by consumers. There is no mention of any pre-consumer recycled content value, so it is assumed to be 0%.

    Rate this question:

Quiz Review Timeline (Updated): May 26, 2024 +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • May 26, 2024
    Quiz Edited by
    ProProfs Editorial Team
  • Aug 19, 2011
    Quiz Created by
    Yrgsustainabilit
Back to Top Back to top
Advertisement