1.
The design team for a new construction project is aiming to earn one point for SS Credit 7.1 Heat Island Effect – Non-Roof. The project site is 15,000 square feet with a 2,000 square feet of site hardscape. What strategy, if applied to 50% of the hardscape area, will allow the project team to achieve this credit? (Choose 1)
Correct Answer
C. Planting trees to provide shade
Explanation
Planting trees to provide shade can help reduce the heat island effect on the project site. Trees provide natural shade, which can help lower the temperature of the hardscape area. This strategy can be applied to 50% of the hardscape area, allowing the project team to earn one point for SS Credit 7.1 Heat Island Effect - Non-Roof.
2.
A new office project will have 200 employees and anticipates an estimated 30 visitors / day. During peak periods, the building will be occupied by 210 occupants. The project team is trying to achieve SS Credit 4.2 Alternative Transportation: Bicycle Storage & Changing Rooms. How many secure bicycle storage spaces will be required?
Correct Answer
C. 11
Explanation
The number of secure bicycle storage spaces required can be calculated by taking into account the number of employees, visitors, and peak occupancy. Since the project will have 200 employees, it is reasonable to assume that at least some of them will use bicycles. Additionally, with an estimated 30 visitors per day, it is possible that some of them may also use bicycles. Therefore, the total number of potential bicycle users can be calculated as 200 employees + 30 visitors = 230 potential bicycle users. Considering that the building will be occupied by 210 occupants during peak periods, it is safe to assume that not all potential bicycle users will be present at the same time. Therefore, it is reasonable to provide secure bicycle storage spaces for at least 11 bicycles to accommodate the potential demand.
3.
A new development is being built on a .5 acre greenfield site. Within 1/2 mile of the site, basic services include 3 restaurants, a bank, 2 grocery stores and a post office. In addition, the development plans to have a coffee shop on the ground floor of the building. How many basic services can the project count towards SSc2 Community Connectivity?
Correct Answer
A. 0
Explanation
The project can count 0 basic services towards SSc2 Community Connectivity because the coffee shop on the ground floor of the building is not considered a basic service.
4.
In order to document a brownfield site under SS Credit 3 Brownfield Redevelopment, what documentation does the project team need to provide? (Choose 2)
Correct Answer(s)
A. Descriptions of site contamination and remediation efforts undertaken by the project
D. Confirmation from EPA office or state agency that site is declared a Brownfield
Explanation
The project team needs to provide descriptions of site contamination and remediation efforts undertaken by the project in order to document a brownfield site under SS Credit 3 Brownfield Redevelopment. Additionally, they need confirmation from the EPA office or state agency that the site is declared a Brownfield. These two pieces of documentation are necessary to demonstrate that the project has addressed and remediated any existing contamination on the brownfield site.
5.
A proposed office building will have 60 employees and a parking lot with 75 spaces. To achieve a LEED credit, the project team is implementing preferred parking for low-emitting and fuel-efficient vehicles. Which of the following vehicles would be able to park in these designated parking spaces, and how many preferred spaces would be required?
Correct Answer
D. Vehicles with a Green Score of 40, 4 preferred spaces
Explanation
The correct answer is "Vehicles with a Green Score of 40, 4 preferred spaces." This means that vehicles with a Green Score of 40 or higher would be able to park in the designated preferred parking spaces. Additionally, the project team would need to allocate 4 preferred spaces for these vehicles.
6.
A new manufacturing facility will have an employee shift schedule that includes three 8-hour shifts that do not overlap. The parking capacity does not exceed the minimum local zoning requirements. How would you calculate the number of required preferred carpool or vanpool parking spaces for SS Credit 4.4 Alternative Transportation: Parking Capacity?
Correct Answer
D. Use FTE of the shift with greatest number of employees
Explanation
To calculate the number of required preferred carpool or vanpool parking spaces for SS Credit 4.4 Alternative Transportation: Parking Capacity, you would use the FTE (Full-Time Equivalent) of the shift with the greatest number of employees. This means that you would consider the shift that has the most employees working during that time period. By using the FTE of this shift, you can determine the maximum number of parking spaces needed to accommodate the employees during that shift.
7.
Which of the following is NOT considered when calculating full-time equivalent (FTE)?
Correct Answer
B. Building occupancy
Explanation
When calculating full-time equivalent (FTE), building occupancy is not considered. FTE is a measure used to determine the number of full-time employees that could be supported by the resources available. It takes into account the number of full-time and part-time employees, as well as students, customers, or visitors. However, building occupancy, which refers to the number of people occupying a building, is not directly related to the calculation of FTE.
8.
A commercial office building with a footprint of 70,000 square feet has an overall site area of 200,000 square feet. The site is in an urban setting and the zoning requirement mandates a minimum of 20% of the net lot area must be public open space. The project design includes 15,000 square feet of pedestrian oriented hardscape and 18,000 square feet of vegetated open space. Does this project satisfy requirements for SS Credit 5.2 Site Development?
Correct Answer
A. Yes
Explanation
The project satisfies the requirements for SS Credit 5.2 Site Development because it includes 18,000 square feet of vegetated open space, which exceeds the minimum requirement of 20% of the net lot area. Additionally, it also includes 15,000 square feet of pedestrian-oriented hardscape, which contributes to the overall site development. Therefore, the project meets the criteria for SS Credit 5.2 Site Development.
9.
A new mixed-use building project is designed to have 200 FTE Staff, 25 Peak Transients, and 75 Residents. What is the least number of shower facilities the project will need to have to achieve SS Credit 4.2 Alternative Transportation Bicycle Storage and Changing Rooms?
Correct Answer
D. 1
Explanation
The project will need to have at least 1 shower facility to achieve SS Credit 4.2 Alternative Transportation Bicycle Storage and Changing Rooms. This is because the credit requires providing shower facilities for projects with 10 or more FTE staff and 25 or more peak transients. Since the project has 200 FTE staff and 25 peak transients, it meets the criteria for requiring shower facilities. Therefore, the least number of shower facilities needed is 1.
10.
A new office building wants to achieve 2 points under Alternative Transportation - Parking Capacity. Which of the following strategy combinations would help the project achieve these points? (Choose 2)
Correct Answer(s)
B. Provide no new parking
D. Meet and not exceed parking capacity per zoning requirements, and designate 5% preferred parking for carpools
Explanation
The correct answer is "Provide no new parking" and "Meet and not exceed parking capacity per zoning requirements, and designate 5% preferred parking for carpools." These strategies would help the project achieve the 2 points under Alternative Transportation - Parking Capacity. By not providing any new parking, the project encourages the use of alternative transportation methods. Additionally, by meeting and not exceeding the parking capacity per zoning requirements and designating 5% of the spaces as preferred parking for carpools, the project promotes carpooling and further reduces the reliance on single-occupancy vehicles.
11.
A new project is proposed for a 4 acre greenfield site that has an existing imperviousness of 35%. What are the strategies the project can implement to achieve SS Credit 6.1 Stormwater Design, Quantity Control? (Choose 2)
Correct Answer(s)
A. Implement a stream channel protection strategy that reduces erosion and includes quantity control
B. Ensure post-development peak discharge is less than or equal to pre-development peak discharge for the 1- and 2-year 24-hour design storms
Explanation
The project can implement a stream channel protection strategy that reduces erosion and includes quantity control to achieve SS Credit 6.1 Stormwater Design, Quantity Control. This strategy will help prevent erosion and control the quantity of stormwater runoff. Additionally, the project should ensure that the post-development peak discharge is less than or equal to the pre-development peak discharge for the 1- and 2-year 24-hour design storms. This will help manage the stormwater runoff and prevent any increase in peak discharge levels.
12.
All of the following statements are true of SS Credit 7.2 Heat Island Effect—Roof, EXCEPT:
Correct Answer
A. LEED specifies high reflectivity surfaces should be cleaned at least every year
Explanation
The given statement states that LEED specifies high reflectivity surfaces should be cleaned at least every year. However, this statement is not true for SS Credit 7.2 Heat Island Effect—Roof. Therefore, this statement is the correct answer for the question.
13.
Impervious surfaces have a perviousness ______ than 50% and _____ runoff of water.
Correct Answer
C. Less, promote
Explanation
Impervious surfaces have a perviousness less than 50%, meaning they do not allow water to pass through easily. This lack of permeability inhibits the absorption of water into the ground, leading to increased runoff. Therefore, impervious surfaces promote the runoff of water.
14.
The primary intent of SS Credit 5.1 Site Development – Protect or Restore Habitat is:
Correct Answer
E. To conserve existing natural areas and promote biodiversity
Explanation
The primary intent of SS Credit 5.1 Site Development – Protect or Restore Habitat is to conserve existing natural areas and promote biodiversity. This credit is part of the LEED certification system, which focuses on sustainable building practices. By conserving natural areas and promoting biodiversity, the credit aims to protect and enhance the ecological value of the site. This can be achieved through measures such as preserving existing vegetation, creating wildlife habitats, and minimizing the impact of development on natural ecosystems.
15.
The primary objectives of SS Prerequisite 1 Construction Activity Pollution Prevention are (Choose 3).
Correct Answer(s)
A. To prevent loss of soil during construction
C. To prevent sedimentation of receiving streams
D. To prevent pollution of air with particulate matter
Explanation
The primary objectives of SS Prerequisite 1 Construction Activity Pollution Prevention are to prevent loss of soil during construction, to prevent sedimentation of receiving streams, and to prevent pollution of air with particulate matter. These objectives aim to minimize the negative environmental impacts of construction activities by reducing soil erosion, protecting water quality, and preventing air pollution. Additionally, by preventing unnecessary construction waste, the objectives also promote sustainable construction practices and resource conservation.
16.
SS Prerequisite 2 Environmental Site Assessment applies to which building types under the LEED BD+C classification?
Correct Answer
B. Schools
Explanation
The correct answer is Schools. The SS Prerequisite 2 Environmental Site Assessment applies specifically to schools under the LEED BD+C classification.
17.
SS Credit 9 Tenant Design and Construction Guidelines should be drafted with input from which team member(s)? (Choose 3)
Correct Answer(s)
B. Project architect
C. Building owner
D. Project engineer
Explanation
The Tenant Design and Construction Guidelines should be drafted with input from the project architect, building owner, and project engineer. The project architect is responsible for the design and layout of the space, ensuring it meets the tenant's needs and adheres to any building codes or regulations. The building owner has a vested interest in ensuring the guidelines align with their overall vision for the property. The project engineer provides technical expertise and insight into the feasibility and practicality of design choices. Together, these team members can collaborate to create comprehensive and effective guidelines for the tenant's design and construction process.
18.
A team plans to integrate SS Credit 10 Joint use of Facilities on a school project. Which of the following would be acceptable LEED strategies in achieving this credit?
Correct Answer
D. All of the above
Explanation
All of the above options would be acceptable LEED strategies in achieving SS Credit 10 Joint use of Facilities on a school project. Shared use of facilities with the general public promotes community engagement and efficient use of resources. A contract with the community for dedicated-use spaces in the building encourages collaboration and integration. Pedestrian access and approved student use of privately owned facilities promote active transportation and utilization of existing resources.
19.
A team plans to incorporate light pollution reduction strategies in their office building project. Which of the following strategies is NOT a LEED-recognized strategy for SS Credit 8 Light Pollution Reduction on NC projects?
Correct Answer
B. Efficient task lights for all offices
Explanation
Efficient task lights for all offices is not a LEED-recognized strategy for SS Credit 8 Light Pollution Reduction on NC projects. The other options, such as light exterior areas only for safety and comfort, automatic controls for non-emergency interior lighting, and exterior openings with automatically controlled closing mechanisms at night, are recognized strategies for reducing light pollution.
20.
All of the following are true of SS Prerequisite 1 Construction Activity Pollution Prevention EXCEPT:
Correct Answer
E. All of the above are true of SS Prerequisite 1
Explanation
The correct answer states that all of the above options are true of SS Prerequisite 1. This means that each of the statements mentioned in the question is true for SS Prerequisite 1 Construction Activity Pollution Prevention. This includes the fact that intensely urban areas may only need to meet a few requirements, the ESC plan can be submitted as documentation, CGP extends compliance with NPDES stormwater regulations, and compliant documentation requires a description of corrective actions taken on-site.
21.
A project is pursuing EA Credit 2 On-Site Renewable Energy. Which of the steps below are part of the process to demonstrate compliance with the credit requirements? (Choose all that apply)
Correct Answer(s)
B. Calculate the energy generated from each on-site renewable energy source
C. Confirm that renewable energy systems are part of project scope
Explanation
The steps to demonstrate compliance with the credit requirements for pursuing EA Credit 2 On-Site Renewable Energy include calculating the energy generated from each on-site renewable energy source and confirming that renewable energy systems are part of the project scope. These steps are necessary to ensure that the project meets the requirements for on-site renewable energy and contributes to the overall goal of the credit.
22.
A project team plans to utilize passive design strategies and on-site renewable energy in order to reduce energy demand for an urban mixed-use high-rise project. Which strategies could be options the project can pursue to meet EA Credit 2: On-Site Renewable Energy? (Choose 3)
Correct Answer(s)
A. Mounted PV (pHotovoltaic) panels
D. System harvesting tidal power
F. Solar thermal panels
Explanation
The project team can pursue the installation of mounted PV (photovoltaic) panels, which generate electricity from sunlight, as an option to meet EA Credit 2: On-Site Renewable Energy. They can also consider implementing a system that harvests tidal power, which utilizes the energy from tides to generate electricity. Additionally, the project can incorporate solar thermal panels, which use sunlight to heat water or other fluids for various purposes. These strategies will help reduce the energy demand of the high-rise project by utilizing renewable energy sources.
23.
What is the reference standard that defines the requirements for LEED energy modeling?
Correct Answer
B. ASHRAE 90.1-2007 Appendix G
Explanation
ASHRAE 90.1-2007 Appendix G is the reference standard that defines the requirements for LEED energy modeling.
24.
A project is pursing EA Prerequisite 1 Fundamental Commissioning of Building Energy Systems. In order for the project to meet the requirements, the team must designate a CxA who complies with all of the following EXCEPT: (Choose 1)
Correct Answer
E. Has documented commissioning authority experience for at least 1 building projects
Explanation
The correct answer is "Has documented commissioning authority experience for at least 1 building projects." The other options are all requirements that the CxA must comply with in order for the project to meet the prerequisites.
25.
A new office project wants to achieve 3 points under EA Credit 5 Measurement and Verification, and implement an M&V plan to monitor their energy usage compared to the energy model completed during design. Which of the following are elements the project must consider as part of complying with the credit? (Choose 2)
Correct Answer(s)
B. Implement a M&V plan consistent with Option D: Calibrated Simulation Savings as specified by IPMVP or Option B: Energy Conservation Measure Isolation as specified by IPMVP
C. Provide a process for corrective action if energy savings are not achieved
Explanation
The project must consider implementing a Measurement and Verification (M&V) plan that is consistent with either Option D: Calibrated Simulation Savings or Option B: Energy Conservation Measure Isolation as specified by IPMVP. This plan will help monitor the project's energy usage compared to the energy model completed during design. Additionally, the project must provide a process for corrective action if energy savings are not achieved.
26.
Points can be earned in the Energy & Atmosphere credit category by: (Choose 1)
Correct Answer
B. Use of no refrigerants
Explanation
Points can be earned in the Energy & Atmosphere credit category by using no refrigerants. This means that the building does not use any substances that contribute to the depletion of the ozone layer or have a high global warming potential. By avoiding the use of refrigerants, the building can reduce its environmental impact and contribute to a more sustainable and energy-efficient design.
27.
The project owner of a 100,000 square foot retail center has asked the project team to hire the Commissioning Authority in order to achieve EA Credit 3 Enhanced Commissioning. The project team should choose a Commissioning Authority that: (Choose 1)
Correct Answer
D. Is not an employee of a contractor or construction manager holding construction contracts
Explanation
The project team should choose a Commissioning Authority that is not an employee of a contractor or construction manager holding construction contracts because this ensures that the Commissioning Authority will provide an unbiased and independent assessment of the project. If the Commissioning Authority is employed by a contractor or construction manager, there may be a conflict of interest that could compromise the integrity and objectivity of the commissioning process. Therefore, selecting a Commissioning Authority who is not affiliated with any contractor or construction manager helps to ensure the effectiveness and credibility of the commissioning process.
28.
Emissivity refers to:
Correct Answer
B. Ratio of radiation emitted by a surface to radiation emitted by a black surface at the same temperature
Explanation
Emissivity refers to the ratio of radiation emitted by a surface to radiation emitted by a black surface at the same temperature. This means that it measures how efficiently a surface emits thermal radiation compared to a perfect black body. A higher emissivity value indicates that a surface emits more radiation, while a lower value indicates that it emits less radiation.
29.
A project team is attempting to achieve 4 points for EA Credit 1 Optimize Energy Performance for a 15,000 square foot office building without using a building energy model. What is the first task the project team must do? (Choose 1)
Correct Answer
A. Identify the climate zone
Explanation
The first task the project team must do is to identify the climate zone. This is because the climate zone will determine the specific requirements and strategies for optimizing energy performance in the office building. Without knowing the climate zone, it would be difficult for the project team to accurately calculate the performance rating, determine the baseline system sizing, or identify the Energy Star Score for the project.
30.
The project is a 600,000 square foot speculative office building. According to the BOMA calculation, the core and shell is 20% of the building total square footage. Using the following table, determine the cost of required green power the project team must purchase to earn points for EA Credit 6 Green Power. Assume a quote from the REC providers of $.02/kWh.
Building Type
Median Electrical Intensity (kWh/sf-yr)
Food Service
28.7
Lodging
12.6
Office
11.7
Other
13.8
Correct Answer
B. $19,656
Explanation
Based on the given information, the project is a 600,000 square foot speculative office building. The core and shell of the building is 20% of the total square footage, which is 120,000 square feet. The cost of required green power can be determined by multiplying the median electrical intensity for office buildings (11.7 kWh/sf-yr) by the total square footage of the core and shell (120,000 square feet), and then multiplying that by the cost per kWh ($0.02). This calculation results in $19,656.
31.
A project team is looking to pursue an ID credit on their new office building. The annual building energy cost for their 400,000 square foot project is $15,120. Which of the following tactics would earn credit for exemplary performance? (Choose 1)
Correct Answer
A. Providing $2,300 worth of on-site renewable energy
Explanation
Providing $2,300 worth of on-site renewable energy would earn credit for exemplary performance because it exceeds the minimum requirement for demonstrating commitment to renewable energy. This tactic shows that the project team is actively investing in sustainable energy sources, which aligns with the goal of reducing the environmental impact of the building.
32.
Which of the following describes the intent of EA Prerequisite 3 Fundamental Refrigerant Management? (Choose 1)
Correct Answer
C. To reduce stratospHeric ozone depletion
Explanation
The intent of EA Prerequisite 3 Fundamental Refrigerant Management is to reduce stratospheric ozone depletion. This means that the goal of this prerequisite is to implement practices and strategies that minimize the release of ozone-depleting substances into the atmosphere, thereby reducing the negative impact on the ozone layer.
33.
LEED requires commissioning process activities be completed for all of the following energy-related systems on a project EXCEPT (choose 1)
Correct Answer
D. Task-lighting systems
Explanation
LEED requires commissioning process activities to be completed for HVAC&R systems, lighting and daylighting controls, domestic hot water systems, and on-site renewable energy systems. However, it does not require commissioning for task-lighting systems.
34.
Which of the following statements is true regarding fire suppression systems?
Correct Answer
B. Fire suppression systems must not contain CFCs, HFCs, or Halons in order to comply with EA Credit 4 Enhanced Refrigerant Management
35.
A new 95,000 square foot school is implementing energy efficiency strategies as part of their LEED certification strategy. A whole building energy simulation was performed and resulted in a baseline building performance of $202,134. What is the minimum improvement in building performance the school must demonstrate in order to meet EA Prerequisite 2 Minimum Energy Performance?
Correct Answer
B. $20,214
Explanation
The minimum improvement in building performance that the school must demonstrate in order to meet EA Prerequisite 2 Minimum Energy Performance is $20,214. This means that the school needs to show that they have reduced their building's energy consumption by at least this amount in order to meet the energy performance requirements for LEED certification.
36.
A new bank project is implementing high energy efficiency strategies to support their goal to achieve 10 LEED points under EA Credit 1 Optimize Energy Performance. Process energy for the bank makes up 35% of the energy costs for the project. A whole building energy simulation resulted in $145,295 for the bank. What should the project team target as their design case energy cost savings in order to reach their EA Credit 1 Optimize Energy Performance goals?
Correct Answer
B. $43,589
Explanation
The project team should target $43,589 as their design case energy cost savings in order to reach their EA Credit 1 Optimize Energy Performance goals. This can be calculated by multiplying the total energy cost of $145,295 by the percentage of process energy for the bank (35%).
37.
In order to comply with SS Credit 1 Site Selection, which of the following site locations would be most appropriate to build a new multi-family development?
Correct Answer
C. Developed site that is 110 feet from wetland
38.
What is ANSI/ASHRAE 62.1 standard used for? (Choose 1)
Correct Answer
C. To determine minimum ventilation rates and acceptable indoor air quality
Explanation
The ANSI/ASHRAE 62.1 standard is used to determine the minimum ventilation rates and acceptable indoor air quality. This standard provides guidelines and requirements for ventilation in buildings, ensuring that occupants have sufficient fresh air and that the indoor air quality is maintained at a satisfactory level. It helps to establish the minimum amount of outdoor air that needs to be supplied to a space, taking into consideration factors such as occupancy, building size, and activities conducted within the space. By following this standard, building owners and designers can ensure that the indoor environment is healthy and comfortable for occupants.
39.
When using natural ventilation to achieve IEQ Credit 2 Increased Ventilation, what percent of the occupied areas must be effectively ventilated?
Correct Answer
C. 90%
Explanation
To achieve IEQ Credit 2 Increased Ventilation using natural ventilation, 90% of the occupied areas must be effectively ventilated. This means that the majority of the areas where people are present should have a sufficient flow of fresh air to maintain good indoor air quality.
40.
Which of the following statements are true concerning IEQ Prerequisite 1 Minimum IAQ Performance? (Choose 2)
Correct Answer(s)
A. Local code can be used in lieu of ASHRAE when local code is more stringent
D. Implementation of this credit is based on 3 basic methods for ventilating buildings: mechanical, natural, and mixed-mode
Explanation
The first statement is true because if the local code has stricter requirements than ASHRAE, it can be used instead. The fourth statement is true because the implementation of the IAQ Prerequisite 1 is based on three methods of ventilating buildings: mechanical, natural, and mixed-mode.
41.
To comply with requirements of IEQ Prerequisite 3 Minimum Acoustical Performance, teams may need all of the following except:
Correct Answer
D. Window Surface Area
Explanation
To comply with the requirements of IEQ Prerequisite 3 Minimum Acoustical Performance, teams need to consider the square footage and cubic footage of learning spaces, sound absorption coefficients, and the surface area of each interior fixed element. However, the window surface area is not a factor that needs to be considered for this particular requirement.
42.
When considering IEQ Credit 1 Outdoor Air Delivery Monitoring in a congested urban area, project teams need to consider all of the following EXCEPT: (Choose 2)
Correct Answer(s)
A. Size of ventilation equipment
C. Building occupant survey
Explanation
When considering IEQ Credit 1 Outdoor Air Delivery Monitoring in a congested urban area, project teams need to consider the following: building ventilation type (natural or mechanical), number of building occupants, and time of day fluctuations. The size of ventilation equipment and building occupant survey are not factors that need to be considered in this context.
43.
To comply with IEQ Credit 4.1 Low Emitting Materials, Adhesives and Sealants without using the VOC Budget Method, what % of adhesive, sealants, and sealant primers must comply with South Coast Air Quality Management District (SCAQMD).
Correct Answer
E. 100
Explanation
To comply with IEQ Credit 4.1 Low Emitting Materials without using the VOC Budget Method, 100% of adhesive, sealants, and sealant primers must comply with the South Coast Air Quality Management District (SCAQMD) regulations. This means that all adhesive, sealants, and sealant primers used in the project must meet the low VOC requirements set by SCAQMD.
44.
Which of the following represents a measurement factor for IEQ Credit 9 Enhanced Acoustical Performance (choose 2).
Correct Answer(s)
A. A-weighted decibel
B. Sound transmission class
Explanation
The correct answer for this question is A-weighted decibel and Sound transmission class. These two factors are relevant to IEQ Credit 9 Enhanced Acoustical Performance. A-weighted decibel is a unit used to measure the loudness of sound, taking into account the sensitivity of the human ear. Sound transmission class (STC) is a rating system that measures how well a building partition, such as a wall or floor, can reduce sound transmission from one space to another. Both of these factors are important in assessing and improving the acoustical performance of a building.
45.
All of the following are true of IEQ Credit 7.2 Thermal Comfort - Verification EXCEPT:
Correct Answer
D. Residential projects are not eligible for this credit
Explanation
This credit requires surveying building occupants, the credit will result in high implementation costs, and the credit requires a permanent monitoring system for NC and CI projects are all true statements about IEQ Credit 7.2 Thermal Comfort - Verification. However, the statement "Residential projects are not eligible for this credit" is false. Residential projects are indeed eligible for this credit.
46.
A new apartment complex is being built and will allow smoking on 2 of the middle floors. How should the project team demonstrate compliance with IEQ Prerequisite 2 Environmental Tobacco Smoke Control for the residences on these floors?(Choose 1)
Correct Answer
D. Conduct a blower door test in accordance with ASTM-779-03
Explanation
The project team should conduct a blower door test in accordance with ASTM-779-03 to demonstrate compliance with IEQ Prerequisite 2 Environmental Tobacco Smoke Control for the residences on the middle floors allowing smoking. This test measures the air tightness of the building envelope and helps identify any leaks or gaps that could allow the transfer of smoke between units. By conducting this test, the project team can ensure that the smoke from the designated smoking floors does not infiltrate the non-smoking floors, thus controlling environmental tobacco smoke.
47.
A new office project is conducting an air quality test to demonstrate compliance with IEQ Credit 3.2 Construction IAQ Management Plan, Before Occupancy. The 65,000 square foot project runs under one ventilation system. All finishes are complete and have been installed, except for the movable furniture which is to be installed within the next 2 days. All of the following statements are true in regards to the project team's approach to meeting this credit EXCEPT: (Choose 1)
Correct Answer
A. The air testing must be performed after the furniture is installed
Explanation
The air testing does not need to be performed after the furniture is installed.
48.
A project team is developing a Thermal Occupant Survey in compliance with IEQ Credit 7.2 Thermal Comfort, Verification. When does the Survey need to be distributed and completed by the occupants?
Correct Answer
D. 6-18 months after occupancy
Explanation
The Thermal Occupant Survey needs to be distributed and completed by the occupants 6-18 months after occupancy. This allows for a sufficient amount of time for the occupants to settle into the space and experience the thermal comfort conditions. By waiting 6-18 months, the survey results will be more accurate and reflective of the long-term thermal comfort performance of the building.
49.
A new multi-use project is planned and will include retail, office space and residential units. The project is pursuing IEQ Credit 8.1 Daylight and Views, Daylight. What area can be excluded from the calculations because they are not considered regularly occupied spaces? (Choose 2)
Correct Answer(s)
B. Lobby
C. Bathrooms
Explanation
The lobby and bathrooms can be excluded from the calculations because they are not considered regularly occupied spaces. Regularly occupied spaces typically refer to areas where people spend a significant amount of time, such as private offices, bedrooms, and living rooms. The lobby is a transitional area and the bathrooms are typically used for short durations, so they are not considered as spaces where people regularly occupy.
50.
An office project consists of 65 workstations, 10 private offices and 5 conference rooms. In order to comply with IEQ Credit 6.1 Controllability of Systems, Lighting, which spaces must have lighting controls? (Choose 1)
Correct Answer
C. 90% of the total workstations and private offices, and all conference rooms
Explanation
In order to comply with IEQ Credit 6.1 Controllability of Systems, Lighting, the spaces that must have lighting controls are 90% of the total workstations and private offices, and all conference rooms.