LEED AP Bd+c Practice Exam

Reviewed by Editorial Team
The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Yrgsustainabilit
Y
Yrgsustainabilit
Community Contributor
Quizzes Created: 3 | Total Attempts: 10,349
| Attempts: 9,889
SettingsSettings
Please wait...
  • 1/100 Questions

    The primary intent of SS Credit 5.1 Site Development – Protect or Restore Habitat is:

    • To encourage the use of local products
    • To maximize amount of pervious surfaces
    • To promote responsible use of Greenfield sites
    • To provide healthy outdoor spaces for building occupants
    • To conserve existing natural areas and promote biodiversity
Please wait...
About This Quiz

All,
Please pay particular attention to the number of answers required for each question (i. E. "Choose 2"). On the actual exam, you will be reminded to choose the appropriate number of options, however in this practice exam if you do not choose the correct number of anwers, the question will be marked incorrect (for example, if you only select 1 See moreanswer rather than 2 that are required, the question will be marked as answered incorrectly, even if that 1 chosen answer was one of the correct options).
Good luck!

LEED AP Bd+c Practice Exam - Quiz

Quiz Preview

  • 2. 

    Which of the following is true about ID Credit 2 LEED Accredited Professional? (Choose 1)

    • The project achieves 1 point if at least 2 LEED APs are principal participants of the project team

    • The project achieves 1 point if at least 1 LEED Green Associate is the LEED Online project administrator

    • The project team earns 2 points if all of the principal participants of the project team are LEED APs

    • The project achieves 1 point if at least 1 LEED AP is a principal participant of the project team

    Correct Answer
    A. The project achieves 1 point if at least 1 LEED AP is a principal participant of the project team
    Explanation
    The correct answer is that the project achieves 1 point if at least 1 LEED AP is a principal participant of the project team. This means that in order to earn this credit, there needs to be at least one LEED Accredited Professional who is a key member of the project team. This ensures that there is someone with expertise in LEED principles and practices involved in the project.

    Rate this question:

  • 3. 

    What does evapotranspiration rate measure?

    • The total plant and leaf area within a landscape

    • The environmental conditions specific to the landscape

    • The amount of water lost from a vegetated surface in units of water depth

    • The amount of water required to irrigate a species for a 24 hour period

    Correct Answer
    A. The amount of water lost from a vegetated surface in units of water depth
    Explanation
    Evapotranspiration rate measures the amount of water lost from a vegetated surface in units of water depth. It takes into account both evaporation from the soil and transpiration from plants. This measurement is important for understanding water loss in ecosystems and can be used to estimate water requirements for irrigation and plant growth.

    Rate this question:

  • 4. 

    What is ANSI/ASHRAE 62.1 standard used for? (Choose 1)

    • To determine the energy efficiency design baseline

    • For testing ventilation filters for removal efficiency

    • To determine minimum ventilation rates and acceptable indoor air quality

    • To specify minimum contaminant levels for Brownfield classification

    Correct Answer
    A. To determine minimum ventilation rates and acceptable indoor air quality
    Explanation
    The ANSI/ASHRAE 62.1 standard is used to determine the minimum ventilation rates and acceptable indoor air quality. This standard provides guidelines and requirements for the design and operation of HVAC systems to ensure that a sufficient amount of outdoor air is provided to maintain good indoor air quality for occupants. It helps in preventing the buildup of pollutants and maintaining a healthy and comfortable indoor environment.

    Rate this question:

  • 5. 

    A new manufacturing facility will have an employee shift schedule that includes three 8-hour shifts that do not overlap. The parking capacity does not exceed the minimum local zoning requirements. How would you calculate the number of required preferred carpool or vanpool parking spaces for SS Credit 4.4 Alternative Transportation: Parking Capacity?

    • Use the average value of the 3 shifts

    • Use total number of all employees in 3 shifts

    • Use the median value of the 3 shifts

    • Use FTE of the shift with greatest number of employees

    Correct Answer
    A. Use FTE of the shift with greatest number of employees
    Explanation
    To calculate the number of required preferred carpool or vanpool parking spaces for SS Credit 4.4 Alternative Transportation: Parking Capacity, the most accurate approach is to use the FTE (Full-Time Equivalent) of the shift with the greatest number of employees. This ensures that the parking spaces are allocated based on the shift that has the highest demand for parking. Using the FTE takes into account both the number of employees and their working hours, providing a more comprehensive calculation for the required parking spaces.

    Rate this question:

  • 6. 

    An example of waste diversion, as specified in MR Prerequsite 1 Storage and Collection of Recyclables, is:

    • Reuse

    • Recycling

    • Incineration

    • Diverting to landfill

    • Both a and b

    • Both a and c

    Correct Answer
    A. Both a and b
    Explanation
    The correct answer is "Both a and b". Waste diversion refers to the practice of diverting waste away from landfills and incinerators by finding alternative uses for it. Reuse involves finding ways to use items again instead of throwing them away, while recycling involves processing waste materials to create new products. Both of these practices help to reduce the amount of waste that ends up in landfills or is incinerated, making them examples of waste diversion.

    Rate this question:

  • 7. 

    In order to comply with SS Credit 1 Site Selection, which of the following site locations would be most appropriate to build a new multi-family development?

    • Undeveloped land with elevation equal to the 100 year flood plain

    • Developed land that is within 45 feet from stream

    • Developed site that is 110 feet from wetland

    • Undeveloped land with a plant identified under the threatened species list

    • Developed land that includes some areas of prime farmland

    Correct Answer
    A. Developed site that is 110 feet from wetland
    Explanation
    Building a new multi-family development on a developed site that is 110 feet from a wetland would be the most appropriate choice to comply with SS Credit 1 Site Selection. This is because wetlands are important ecosystems that provide various ecological functions and benefits. By locating the development 110 feet away from the wetland, it helps to minimize potential impacts on the wetland and its associated wildlife and vegetation. This demonstrates a commitment to preserving and protecting the natural environment, which aligns with the goals of SS Credit 1 Site Selection.

    Rate this question:

  • 8. 

    A team plans to integrate SS Credit 10 Joint use of Facilities on a school project.  Which of the following would be acceptable LEED strategies in achieving this credit?

    • Shared use (w/general public) of an auditorium, classroom, and parking facility

    • A contract with community for a commercial office and health clinic dedicated-use spaces in the building

    • Pedestrian access and approved student use of privately owned swimming pool and playing field

    • All of the above

    Correct Answer
    A. All of the above
    Explanation
    All of the above options would be acceptable LEED strategies in achieving SS Credit 10 Joint use of Facilities on a school project. The credit encourages the shared use of facilities between the school and the community, promoting sustainability and efficient use of resources. Shared use of spaces such as an auditorium, classroom, and parking facility with the general public, having dedicated-use spaces for a commercial office and health clinic through a contract with the community, and allowing pedestrian access and approved student use of privately owned facilities like a swimming pool and playing field all align with the goals of this credit.

    Rate this question:

  • 9. 

    A project team is installing a green roof on their urban office project. The team has designed the vegetated roof for 100% of the project roof area to achieve SS Credit 7.1 Heat Island Effect - Roof. Which of the following credits will this strategy NOT have an effect on? (Choose 2)

    • EAc2: Optimize Energy Performance

    • SSc4.4: Alternative Transportation - Parking Capacity

    • SSc5.1: Site Development: Maximize Open Space

    • SSc3: Brownfield Redevelopment

    • SSc6.1: Stormwater Design - Quantity

    Correct Answer(s)
    A. SSc4.4: Alternative Transportation - Parking Capacity
    A. SSc3: Brownfield Redevelopment
    Explanation
    The installation of a green roof on the urban office project will not have an effect on the Alternative Transportation - Parking Capacity credit because it is focused on promoting alternative modes of transportation and reducing the need for parking spaces, which is unrelated to the green roof. Additionally, it will not have an effect on the Brownfield Redevelopment credit because this credit is focused on the remediation and redevelopment of contaminated or underutilized land, which is unrelated to the installation of a green roof.

    Rate this question:

  • 10. 

    Regional Priority points are earned by: (Choose 1)

    • Developing an innovation in design strategy that focuses on a regional green building issue

    • Achieving credits that have been designated as regional priority credits

    • Achieving all of the credits in the sustainable sites category

    • Achieving credits that a project team decides are the most significant for their project's region

    Correct Answer
    A. Achieving credits that have been designated as regional priority credits
    Explanation
    Regional Priority points are earned by achieving credits that have been designated as regional priority credits. These credits are specific to a particular region and address green building issues that are of particular importance in that region. By achieving these credits, a project team can earn additional points towards their green building certification. This approach ensures that projects are addressing the unique environmental challenges and priorities of their specific region.

    Rate this question:

  • 11. 

    LEED requires commissioning process activities be completed for all of the following energy-related systems on a project EXCEPT (choose 1)

    • HVAC&R

    • Lighting and daylighting controls

    • Domestic hot water systems

    • Task-lighting systems

    • On-site renewable energy systems

    Correct Answer
    A. Task-lighting systems
    Explanation
    LEED, which stands for Leadership in Energy and Environmental Design, requires commissioning process activities to be completed for all energy-related systems on a project except for task-lighting systems. This means that commissioning is required for HVAC&R, lighting and daylighting controls, domestic hot water systems, and on-site renewable energy systems. Task-lighting systems are exempt from this requirement.

    Rate this question:

  • 12. 

    Which of the following products would NOT contribute to MR Credit 6 Rapidly Renewable Materials? (Choose 1)

    • Cork flooring

    • Wool carpeting

    • Linoleum tiles

    • Sunflower seed countertops

    • Soy foam insulation

    • Ceramic wall tiles

    Correct Answer
    A. Ceramic wall tiles
    Explanation
    Ceramic wall tiles would not contribute to MR Credit 6 Rapidly Renewable Materials because they are not made from rapidly renewable materials. Rapidly renewable materials are those that can be harvested or replenished within a short period of time, typically less than 10 years. Ceramic wall tiles are typically made from clay and other minerals, which are not considered rapidly renewable.

    Rate this question:

  • 13. 

    Which of the following does not play a role in determining the baseline for WE Prerequisite 1 Water Use Reduction? (Choose 1)

    • Frequency of use / occupancy

    • Gender ratio

    • Building floor area

    • Types of water use fixtures

    • Water volume per fixture use

    Correct Answer
    A. Building floor area
    Explanation
    Building floor area does not play a role in determining the baseline for WE Prerequisite 1 Water Use Reduction. The baseline for water use reduction is determined based on factors such as the frequency of use/occupancy, types of water use fixtures, and water volume per fixture use. Building floor area is not directly related to water use and therefore does not affect the baseline calculation.

    Rate this question:

  • 14. 

    What is the reference standard that defines the requirements for LEED energy modeling?

    • ASHRAE Advanced Energy Design Guide

    • ASHRAE 90.1-2007 Appendix G

    • Energy Star Target Finder

    • Core Performance Guide

    • ASHRAE 62.1-2007

    Correct Answer
    A. ASHRAE 90.1-2007 Appendix G
    Explanation
    ASHRAE 90.1-2007 Appendix G is the reference standard that defines the requirements for LEED energy modeling. This appendix provides a detailed methodology for energy modeling and establishes the baseline energy performance requirements for buildings. It outlines the procedures and calculations needed to determine the energy cost budget and the energy cost budget compliance. LEED energy modeling must comply with the guidelines and requirements set forth in this standard.

    Rate this question:

  • 15. 

    A project team has designed the project building to provide daylighting for at least 75% of regularly occupied spaces. Which of the following credits could possibly be affected? (Choose 3)

    • IEQc8.2: Daylight & Views - Views

    • EAc1: Optimize Energy Performance

    • IEQp2: Environmental Tobacco Smoke (ETS) Control

    • IEQc2: Increased Ventilation

    • IEQc6.1: Controllability of Systems - Lighting

    Correct Answer(s)
    A. IEQc8.2: Daylight & Views - Views
    A. EAc1: Optimize Energy Performance
    A. IEQc6.1: Controllability of Systems - Lighting
    Explanation
    The project team's goal of providing daylighting for at least 75% of regularly occupied spaces directly relates to the IEQc8.2 credit, which focuses on providing occupants with access to views and daylight. Additionally, optimizing energy performance (EAc1) can be affected because incorporating daylighting can reduce the need for artificial lighting, leading to energy savings. Finally, the controllability of lighting systems (IEQc6.1) can be impacted as well, as the design of the project building would need to consider the integration of daylighting controls to maximize natural light while still providing occupant control over lighting levels.

    Rate this question:

  • 16. 

    Emissivity refers to: 

    • Measure of material’s ability to reject solar heat

    • Ratio of radiation emitted by a surface to radiation emitted by a black surface at the same temperature

    • Measure of the ability of a surface material to reflect sunlight (visible, infrared, and ultraviolet wavelengths)

    • Ability of a material to absorb sound, expressed as a fraction of incident sound

    Correct Answer
    A. Ratio of radiation emitted by a surface to radiation emitted by a black surface at the same temperature
    Explanation
    Emissivity refers to the ratio of radiation emitted by a surface to radiation emitted by a black surface at the same temperature. This means that it measures how efficiently a surface emits thermal radiation compared to a perfect black body. A higher emissivity value indicates that a surface is a good emitter of radiation, while a lower value indicates that it is a poor emitter.

    Rate this question:

  • 17. 

    For what month does LEED require you to use when determining the evapotranspiration rate?

    • May

    • June

    • July

    • September

    Correct Answer
    A. July
    Explanation
    LEED requires the use of July when determining the evapotranspiration rate. Evapotranspiration is the process by which water is transferred from the land to the atmosphere through evaporation from the soil and transpiration from plants. July is typically the month with the highest evapotranspiration rate, making it the most appropriate month to use for this calculation.

    Rate this question:

  • 18. 

    The design team for a new construction project is aiming to earn one point  for SS Credit 7.1 Heat Island Effect – Non-Roof. The project site is 15,000 square feet with a 2,000 square feet of site hardscape. What strategy, if applied to 50% of the hardscape area, will allow the project team to achieve this credit? (Choose 1)

    • Implementing hardscape materials with an SRI value of at least 18

    • Using an open-grid pavement system that is at least 25% pervious

    • Planting trees to provide shade

    • Provide shade from structures that have an SRI of at least 18

    Correct Answer
    A. Planting trees to provide shade
    Explanation
    Planting trees to provide shade can help reduce the heat island effect on the site. Trees provide shade, which can help lower the temperature of the hardscape area. By planting trees on 50% of the hardscape area, the project team can achieve the credit for SS Credit 7.1 Heat Island Effect - Non-Roof. This strategy helps to mitigate the heat island effect by reducing the amount of heat absorbed by the hardscape, thus contributing to a more sustainable and environmentally friendly design.

    Rate this question:

  • 19. 

    SS Credit 9 Tenant Design and Construction Guidelines should be drafted with input from which team member(s)? (Choose 3)

    • The new tenant

    • Project architect

    • Building owner

    • Project engineer

    Correct Answer(s)
    A. Project architect
    A. Building owner
    A. Project engineer
    Explanation
    The Tenant Design and Construction Guidelines should be drafted with input from the project architect, building owner, and project engineer. The project architect is responsible for designing the project and ensuring that it meets the tenant's needs. The building owner has a vested interest in the design and construction process as they will ultimately own the building. The project engineer provides technical expertise and ensures that the design is structurally sound and meets all necessary codes and regulations.

    Rate this question:

  • 20. 

    A recent major renovation project has just finished the demolition phase of the project and is calculating the product materials removed from the site as part of MR Credit 2 Construction Waste Management. If none of the products below are going to be reused or donated, which must be included in these calculations?

    • Land clearing debris

    • Carpet

    • Excavated soil

    • Tiles containing asbestos

    • Interior walls painted with lead paint

    Correct Answer
    A. Carpet
    Explanation
    In calculating the product materials removed from the site as part of MR Credit 2 Construction Waste Management, the carpet must be included in these calculations if none of the products are going to be reused or donated. This means that if the carpet is not going to be reused or donated, it should be considered as part of the waste generated during the demolition phase of the project.

    Rate this question:

  • 21. 

    A project team is developing a Thermal Occupant Survey in compliance with IEQ Credit 7.2 Thermal Comfort, Verification. When does the Survey need to be distributed and completed by the occupants?

    • Right before move in

    • Within 1 month of occupancy

    • 3 months of occupancy

    • 6-18 months after occupancy

    • At 1 year of occupancy

    Correct Answer
    A. 6-18 months after occupancy
    Explanation
    The Thermal Occupant Survey needs to be distributed and completed by the occupants 6-18 months after occupancy. This allows for a sufficient amount of time for the occupants to settle into the space and experience different seasons and weather conditions, which can affect their thermal comfort. By waiting until this time period, the survey can provide a more accurate and comprehensive understanding of the occupants' thermal comfort levels in the long term.

    Rate this question:

  • 22. 

    Which of the options below would NOT be considered applicable nonpotable water sources in determining strategies to meet requirements for WE Credit 2 Innovative Wastewater Treatment? (Choose 1)

    • Rainwater

    • Graywater

    • Cooling system condensate

    • Municipal treated wastewater

    • Water from stream just outside LEED project boundary

    Correct Answer
    A. Water from stream just outside LEED project boundary
    Explanation
    Water from a stream just outside the LEED project boundary would not be considered an applicable nonpotable water source because it is not within the project boundary and therefore cannot be easily accessed or managed by the project team. The other options listed - rainwater, graywater, cooling system condensate, and municipal treated wastewater - are all potential sources of nonpotable water that can be utilized for innovative wastewater treatment strategies.

    Rate this question:

  • 23. 

    A project is undergoing major renovation that will include reusing much of building exterior walls and floors. Which of the project materials and areas below can be included in calculations for achieving MR Credit 1.1 Building Reuse, Maintain Existing Walls, Floors and Roof? (Choose 1)

    • Interior entryway walls

    • 3rd floor window assemblies and glazing

    • Decorative brick that was installed in the outside entrance

    • Existing foundation / slab on grade

    Correct Answer
    A. Existing foundation / slab on grade
    Explanation
    The correct answer is "existing foundation / slab on grade" because MR Credit 1.1 Building Reuse, Maintain Existing Walls, Floors and Roof focuses on reusing existing building elements. The foundation and slab on grade are part of the building structure and can be reused in the renovation project. The other options, such as interior entryway walls, window assemblies, glazing, and decorative brick, are not specifically mentioned as eligible for inclusion in the calculations for this credit.

    Rate this question:

  • 24. 

    A project is pursing EA Prerequisite 1 Fundamental Commissioning of Building Energy Systems. In order for the project to meet the requirements, the team must designate a CxA who complies with all of the following EXCEPT: (Choose 1)

    • Will be contracted to report results, findings and recommendations directly to the owner

    • Will review the Owners Project Requirements for project goals and expectations

    • Will review the Basis of Design documents for clarity and completeness, and consistency with the Owners Project Requirements

    • Is independent of the project's design and construction management team

    • Has documented commissioning authority experience for at least 1 building projects

    Correct Answer
    A. Has documented commissioning authority experience for at least 1 building projects
    Explanation
    The correct answer is "Has documented commissioning authority experience for at least 1 building projects." The other options describe the requirements that the CxA must comply with, such as reporting directly to the owner, reviewing project goals and expectations, reviewing design documents, and being independent of the design and construction management team. However, the CxA does not necessarily need to have experience with at least 1 building project.

    Rate this question:

  • 25. 

    To comply with IEQ Credit 4.1 Low Emitting Materials, Adhesives and Sealants without using the VOC Budget Method, what % of adhesive, sealants, and sealant primers must comply with South Coast Air Quality Management District (SCAQMD).

    • 10

    • 30

    • 50

    • 95

    • 100

    Correct Answer
    A. 100
    Explanation
    To comply with IEQ Credit 4.1 Low Emitting Materials without using the VOC Budget Method, all adhesive, sealants, and sealant primers must comply with the South Coast Air Quality Management District (SCAQMD) standards. This means that 100% of these materials must meet the requirements set by SCAQMD.

    Rate this question:

  • 26. 

    An office project consists of 65 workstations, 10 private offices and 5 conference rooms. In order to comply with IEQ Credit 6.1 Controllability of Systems, Lighting, which spaces must have lighting controls? (Choose 1) 

    • All conference rooms and private offices

    • 90% of the workstations and all conference rooms

    • 90% of the total workstations and private offices, and all conference rooms

    • 50% of the total workstations, private offices and conference rooms

    • All of the workstations and private offices, and 90% of the conference rooms

    Correct Answer
    A. 90% of the total workstations and private offices, and all conference rooms
    Explanation
    In order to comply with IEQ Credit 6.1 Controllability of Systems, Lighting, 90% of the total workstations and private offices, and all conference rooms must have lighting controls.

    Rate this question:

  • 27. 

    The project owner of a 100,000 square foot retail center has asked the project team to hire the Commissioning Authority in order to achieve EA Credit 3 Enhanced Commissioning. The project team should choose a Commissioning Authority that: (Choose 1)

    • Is a contracted employee through the project design firm

    • Is not an employee or contractor of the project owner

    • Has documented commissioning authority experience on at least 1 other building project

    • Is not an employee of a contractor or construction manager holding construction contracts

    Correct Answer
    A. Is not an employee of a contractor or construction manager holding construction contracts
    Explanation
    The project team should choose a Commissioning Authority that is not an employee of a contractor or construction manager holding construction contracts because this ensures that the Commissioning Authority will have an unbiased perspective and will not have any conflicts of interest. They will be able to provide an independent evaluation of the project and ensure that the commissioning process is carried out effectively.

    Rate this question:

  • 28. 

    SS Prerequisite 2 Environmental Site Assessment applies to which building types under the LEED BD+C classification?

    • NC

    • Schools

    • CS

    • NC and Schools

    • NC and CS

    • NC, Schools and CS

    Correct Answer
    A. Schools
    Explanation
    The correct answer is Schools.

    Rate this question:

  • 29. 

    Which of the following projects would meet the LEED-NC Minimum Program Requirements? (Choose 1)

    • A project that complies with federal and state environmental laws, but not local environmental laws

    • A major renovation project that would like to certify floors 5-10

    • A project that includes in the LEED project boundary all contiguous land that supports normal building operations

    • A project with a gross floor area of 2,000 square feet and site area of 200,000 square feet

    • A project with a gross floor area of 900 square feet and site area of 9,000 square feet

    Correct Answer
    A. A project that includes in the LEED project boundary all contiguous land that supports normal building operations
    Explanation
    A project that includes in the LEED project boundary all contiguous land that supports normal building operations would meet the LEED-NC Minimum Program Requirements. This means that the project would consider and include all the land that is directly connected to and necessary for the functioning of the building. This requirement ensures that the project takes into account the environmental impact and sustainability of the entire site, rather than just focusing on the building itself.

    Rate this question:

  • 30. 

    A project team is looking to pursue an ID credit on their new office building. The annual building energy cost for their 400,000 square foot project is $15,120. Which of the following tactics would earn credit for exemplary performance? (Choose 1)

    • Providing $2,300 worth of on-site renewable energy

    • Providing $1,500 worth of on-site renewable energy

    • Demonstrate energy cost savings of $5,000

    • Purchase $1,700 worth of electricity from renewable sources

    Correct Answer
    A. Providing $2,300 worth of on-site renewable energy
    Explanation
    Providing $2,300 worth of on-site renewable energy would earn credit for exemplary performance because it exceeds the annual building energy cost of $15,120. This demonstrates a significant investment in renewable energy, which aligns with the goal of reducing the building's environmental impact and promoting sustainability.

    Rate this question:

  • 31. 

    A new 95,000 square foot school is implementing energy efficiency strategies as part of their LEED certification strategy. A whole building energy simulation was performed and resulted in a baseline building performance of $202,134. What is the minimum improvement in building performance the school must demonstrate in order to meet EA Prerequisite 2 Minimum Energy Performance?

    • $20,214 

    • $10,107

    • $40,427

    • $50,534

    Correct Answer
    A. $10,107
    Explanation
    In order to determine the minimum improvement in building performance, we need to calculate 5% of the baseline building performance:Baseline Building Performance = $202,134
    5% of Baseline Building Performance = 0.05 * $202,134Calculating this gives:$10,107Therefore, the correct answer is:
    $10,107

    Rate this question:

  • 32. 

    A new multi-family project is implementing water efficient landscaping for the surrounding grounds. The plan currently includes 5,000 square feet of mixed vegetation and 2,000 square feet of pedestrian hardscape. In order to calculate the landscape coefficient to meet the requirements of WE Credit 1: Water Efficient Landscaping, what factors does the project team need to identify about the project's landscaping? (Choose 1)

    • Climate zone, regional factor, density factor

    • Density factor, species factor, microclimate factor

    • Density factor, climate zone, evapotransiration factor

    • Species factor, maintenance factor, regional factor

    • Microclimate factor, efficiency factor, maintenance factor

    Correct Answer
    A. Density factor, species factor, microclimate factor
    Explanation
    The project team needs to identify the density factor, species factor, and microclimate factor about the project's landscaping in order to calculate the landscape coefficient for water efficient landscaping.

    Rate this question:

  • 33. 

    MR Prerequisite1 Storage and Collection of Recyclables does NOT require collection of which solid waste types below? (Choose 2)

    • Glass

    • Metals

    • Food scraps / compost

    • Cardboard

    • Wood

    • Plastic

    Correct Answer(s)
    A. Food scraps / compost
    A. Wood
    Explanation
    The MR Prerequisite1 Storage and Collection of Recyclables does not require the collection of food scraps/compost and wood as solid waste types. This means that the prerequisite does not mandate the separate collection and storage of these waste types for recycling purposes. However, it does require the collection of glass, metals, cardboard, and plastic as part of the storage and collection of recyclables.

    Rate this question:

  • 34. 

    The primary objectives of SS Prerequisite 1 Construction Activity Pollution Prevention are (Choose 3).

    • To prevent loss of soil during construction

    • To reduce construction transportation pollution

    • To prevent sedimentation of receiving streams

    • To prevent pollution of air with particulate matter

    • To prevent unnecessary construction waste

    Correct Answer(s)
    A. To prevent loss of soil during construction
    A. To prevent sedimentation of receiving streams
    A. To prevent pollution of air with particulate matter
    Explanation
    The primary objectives of SS Prerequisite 1 Construction Activity Pollution Prevention are to prevent loss of soil during construction, to prevent sedimentation of receiving streams, and to prevent pollution of air with particulate matter. These objectives aim to minimize the negative environmental impacts of construction activities by addressing issues such as erosion, water pollution, and air pollution.

    Rate this question:

  • 35. 

    Which of the following statements are true concerning IEQ Prerequisite 1 Minimum IAQ Performance? (Choose 2)

    • Local code can be used in lieu of ASHRAE when local code is more stringent

    • Local code can be used in lieu of ASHRAE when local code is less stringent

    • Teams must provide appropriately located designated smoking areas outside the building away from building entrances, operable windows, and ventilation systems

    • Implementation of this credit is based on 3 basic methods for ventilating buildings: mechanical, natural, and mixed-mode

    • The purpose of this prerequisite is to limit the exposure of building occupants to Environmental Tobacco Smoke, or secondhand smoke

    Correct Answer(s)
    A. Local code can be used in lieu of ASHRAE when local code is more stringent
    A. Implementation of this credit is based on 3 basic methods for ventilating buildings: mechanical, natural, and mixed-mode
    Explanation
    The first statement is true because if the local code is more stringent than ASHRAE, it can be used as a substitute. The second statement is true because if the local code is less stringent than ASHRAE, it can also be used as a substitute. These two statements explain the conditions under which local code can be used instead of ASHRAE.

    Rate this question:

  • 36. 

    Which of the following products would be included as part of the total wood cost for MR Credit 7 Certified Wood calculations? (Choose 3)

    • $15,000 Salvaged wood for doors

    • $38,000 FSC Pure countertops

    • $22,000 FSC Mixed for beams

    • $40,000 Non FSC certified new wood for veneers

    • $10,000 Reused wood for cabinets

    Correct Answer(s)
    A. $38,000 FSC Pure countertops
    A. $22,000 FSC Mixed for beams
    A. $40,000 Non FSC certified new wood for veneers
    Explanation
    The correct answer is $38,000 FSC Pure countertops, $22,000 FSC Mixed for beams, and $40,000 Non FSC certified new wood for veneers. These three products would be included as part of the total wood cost for MR Credit 7 Certified Wood calculations because they all involve the use of wood. The FSC Pure countertops and FSC Mixed beams are certified wood products, which meet specific sustainability criteria. The Non FSC certified new wood for veneers is also included because it is a wood product, even though it is not certified.

    Rate this question:

  • 37. 

    A new office project will have 200 employees and anticipates an estimated 30 visitors / day. During peak periods, the building will be occupied by 210 occupants. The project team is trying to achieve SS Credit 4.2 Alternative Transportation: Bicycle Storage & Changing Rooms.  How many secure bicycle storage spaces will be required? 

    • 2

    • 10

    • 11

    • 12

    • 21

    Correct Answer
    A. 11
    Explanation
    The correct answer is 11 because the project team is trying to achieve SS Credit 4.2 Alternative Transportation: Bicycle Storage & Changing Rooms. This credit requires providing secure bicycle storage spaces for a certain percentage of occupants. Since the building will be occupied by 210 occupants during peak periods, the team needs to provide secure bicycle storage spaces for 5% of the occupants, which is 11 spaces.

    Rate this question:

  • 38. 

    Impervious surfaces have a perviousness ______ than 50% and _____ runoff of water.

    • Greater, promote

    • Greater, inhibit

    • Less, promote

    • Less, inhibit

    Correct Answer
    A. Less, promote
    Explanation
    Impervious surfaces have a perviousness less than 50%, meaning they allow less water to pass through. This, in turn, promotes runoff of water, as less water is able to infiltrate into the ground.

    Rate this question:

  • 39. 

    Which of the following represents a measurement factor for IEQ Credit 9 Enhanced Acoustical Performance (choose 2).

    • A-weighted decibel

    • Sound transmission class

    • Interior climate factor

    • Insulation factor

    Correct Answer(s)
    A. A-weighted decibel
    A. Sound transmission class
    Explanation
    The question is asking for two measurement factors for IEQ Credit 9 Enhanced Acoustical Performance. The correct answers are A-weighted decibel and Sound transmission class. A-weighted decibel is a unit used to measure the loudness of sound, taking into account the sensitivity of the human ear to different frequencies. Sound transmission class (STC) is a rating system that measures how well a building partition reduces sound transmission from one space to another. Both of these factors are important in assessing and improving the acoustical performance of a building.

    Rate this question:

  • 40. 

    A project team earns an Innovation in Design point for an innovative strategy on a previous project. The project team would like to submit the same innovative strategy for an ID point on a current project. Which of the following statements is true? (Choose 2)

    • The precedent set by the previous project means that the current project will achieve the ID point

    • The project team must structure the innovative strategy to be appropriate for the current project's context in order to achieve the ID point

    • The project team must submit a CIR to see if the ID point will be achieved

    • Although a precedent was set by the previous project, the current project will not necessarily achieve the ID point

    • The current project will not achieve the ID point for using the same innovative strategy, because it is no longer innovative

    Correct Answer(s)
    A. The project team must structure the innovative strategy to be appropriate for the current project's context in order to achieve the ID point
    A. Although a precedent was set by the previous project, the current project will not necessarily achieve the ID point
    Explanation
    The correct answer is that the project team must structure the innovative strategy to be appropriate for the current project's context in order to achieve the ID point, and although a precedent was set by the previous project, the current project will not necessarily achieve the ID point. This means that even though the team has previously earned an ID point for the innovative strategy, they cannot assume that they will automatically earn it again on the current project. They need to adapt and tailor the strategy to fit the specific context and requirements of the current project in order to achieve the ID point.

    Rate this question:

  • 41. 

    Points can be earned in the Energy & Atmosphere credit category by: (Choose 1)

    • Meeting standards of ANSI/ASHRAE 62.1

    • Use of no refrigerants

    • Purchasing a one-year renewable energy contract to provide 25% of the building's electricity from renewable sources

    • Developing and incorporating commissioning requirements into construction documents

    Correct Answer
    A. Use of no refrigerants
    Explanation
    Points can be earned in the Energy & Atmosphere credit category by using no refrigerants. This means that the building does not use any substances that deplete the ozone layer or contribute to global warming. By avoiding the use of refrigerants, the building can reduce its environmental impact and contribute to a more sustainable and energy-efficient design.

    Rate this question:

  • 42. 

    A new multi-use project is planned and will include retail, office space and residential units. The project is pursuing IEQ Credit 8.1 Daylight and Views, Daylight. What area can be excluded from the calculations because they are not considered regularly occupied spaces? (Choose 2)

    • Private offices

    • Lobby

    • Bathrooms

    • Retail floor

    • Bedrooms

    • Living rooms

    Correct Answer(s)
    A. Lobby
    A. Bathrooms
    Explanation
    The lobby and bathrooms can be excluded from the calculations because they are not considered regularly occupied spaces. These areas are typically used for brief periods of time and are not intended for extended periods of occupancy. Therefore, they do not need to be included when determining the daylight and views requirements for regularly occupied spaces in the multi-use project.

    Rate this question:

  • 43. 

    When does a project registration fee vary? 

    • It does not vary and is always the same

    • USGBC Membership

    • When a team has previously registered a project, projects registered later are discounted

    • Varies based on the LEED Rating System and type of project

    Correct Answer
    A. USGBC Membership
    Explanation
    The project registration fee varies based on USGBC membership. This means that if a project is registered by a member of the USGBC, the registration fee may be different compared to non-members. The fee could be higher or lower depending on the membership status.

    Rate this question:

  • 44. 

    A project team is trying to determine how many points they can achieve from their products containing rapidly renewable materials. The overall project materials budget is $7,295,000. Wool carpeting contributes $50,000 and cotton batt insulation contributes $90,000. In addition, sunflower seed countertops throughout the project contribute $32,000. How many points does this project achieve under MR Credit 6 Radidly Renewable Materials? 

    • 0

    • 1

    • 2

    • 3

    Correct Answer
    A. 0
    Explanation
    The project does not achieve any points under MR Credit 6 Radidly Renewable Materials because the total cost of the rapidly renewable materials used in the project is $50,000 + $90,000 + $32,000 = $172,000, which is less than the required threshold for earning points.

    Rate this question:

  • 45. 

    A proposed office building will have 60 employees and a parking lot with 75 spaces. To achieve a LEED credit, the project team is implementing preferred parking for low-emitting and fuel-efficient vehicles.  Which of the following vehicles would be able to park in these designated parking spaces, and how many preferred spaces would be required? 

    • Vehicles with a Green Score of 20, 3 preferred spaces

    • Vehicles with a Green Score of 20, 4 preferred spaces

    • Vehicles having a Green Score of 40, 3 preferred spaces

    • Vehicles with a Green Score of 40, 4 preferred spaces

    Correct Answer
    A. Vehicles with a Green Score of 40, 4 preferred spaces
    Explanation
    Based on the information given, the project team is implementing preferred parking for low-emitting and fuel-efficient vehicles. The vehicles that would be able to park in these designated parking spaces are those with a Green Score of 40. Additionally, the project team would require 4 preferred spaces for these vehicles.

    Rate this question:

  • 46. 

    A team plans to incorporate light pollution reduction strategies in their office building project. Which of the following strategies is NOT a LEED-recognized strategy for SS Credit 8 Light Pollution Reduction on NC projects?

    • Light exterior areas only for safety and comfort

    • Efficient task lights for all offices

    • Automatic controls for non-emergency interior lighting

    • Exterior openings to have automatically controlled closing mechanisms at night

    Correct Answer
    A. Efficient task lights for all offices
  • 47. 

    WE Credit 1 Water Efficient Landscaping requires determination of the landscape coefficient KL which indicates the volume of water lost via evapotraspiration and varies with the plant species, microclimate, and planting density.  Based on their site & location, a project team specifies:
    • High species factor for trees, average for turf grass.
    • Average density factor for trees, average for turf grass.
    • Low microclimate factor for trees , high for turf grass.
    Vegetation type Species Factor (ks) Density Factor (kd) Microclimate factor (kmc) Low Avg. High Low Avg. High Low Avg. High Trees .2 .5 .9 .5 1.0 1.3 .5 1.0 1.4 Shrubs .2 .5 .7 .5 1.0 1.1 .5 1.0 1.3 Groundcover .2 .5 .7 .5 1.0 1.1 .5 1.0 1.2 Mixed trees, shrubs, groundcover .2 .5 .9 .6 1.1 1.3 .5 1.0 1.4 Turf grass .6 .7 .8 .6 1.0 1.0 .8 1.0 1.2 Determine the landscape coefficient using these three characteristics for trees on the project site.

    • 5.3

    • 2.4

    • 0.45

    • 0.38

    • None of the above

    Correct Answer
    A. 0.45
    Explanation
    The landscape coefficient for trees on the project site is determined by taking the average of the species factor, density factor, and microclimate factor for trees. Looking at the table, the average values for these factors are 0.5, 1.0, and 1.0 respectively. Taking the average of these values gives us 0.5, which is not the correct answer. However, if we look closely at the table, we can see that the correct values for the species factor, density factor, and microclimate factor for trees are 0.2, 0.5, and 0.5 respectively. Taking the average of these values gives us 0.4, which is not one of the given answer choices. Therefore, the correct answer is "None of the above".

    Rate this question:

  • 48. 

    A project team is attempting to achieve 4 points for EA Credit 1 Optimize Energy Performance for a 15,000 square foot office building without using a building energy model.  What is the first task the project team must do? (Choose 1)

    • Identify the climate zone

    • Calculate the performance rating

    • Determine the baseline system sizing

    • Identify the Energy Star Score for the project

    Correct Answer
    A. Identify the climate zone
    Explanation
    The first task the project team must do is to identify the climate zone. This is important because the climate zone will determine the specific energy requirements and considerations for the building. By identifying the climate zone, the project team can then proceed to develop strategies and measures to optimize energy performance in accordance with the specific climate conditions of the location.

    Rate this question:

  • 49. 

    A new office building wants to achieve 2 points under Alternative Transportation - Parking Capacity.  Which of the following strategy combinations would help the project achieve these points? (Choose 2)

    • Meet and not exceed parking capacity per zoning requirements, and designate 3% of the spaces as preferred parking for carpools

    • Provide no new parking

    • Maximize parking capacity to meet FTE, and designate 5% of the spaces as preferred parking for carpools

    • Meet and not exceed parking capacity per zoning requirements, and designate 5% preferred parking for carpools

    • Meet and not exceed parking capacity per zoning requirements, and designate 5% of FTE as preferred parking for carpools

    Correct Answer(s)
    A. Provide no new parking
    A. Meet and not exceed parking capacity per zoning requirements, and designate 5% preferred parking for carpools
    Explanation
    The correct answer is "Provide no new parking" and "Meet and not exceed parking capacity per zoning requirements, and designate 5% preferred parking for carpools." These strategies would help the project achieve the 2 points under Alternative Transportation - Parking Capacity. By not providing any new parking, the project encourages alternative modes of transportation. Meeting and not exceeding parking capacity per zoning requirements ensures that the project complies with regulations while still promoting sustainable transportation options. Designating 5% of the parking spaces as preferred parking for carpools further incentivizes carpooling and reduces single-occupancy vehicle use.

    Rate this question:

Quiz Review Timeline (Updated): Jan 15, 2025 +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Jan 15, 2025
    Quiz Edited by
    ProProfs Editorial Team
  • Apr 13, 2012
    Quiz Created by
    Yrgsustainabilit
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.