Building Laws Trivia Questions! Quiz

Approved & Edited by ProProfs Editorial Team
The editorial team at ProProfs Quizzes consists of a select group of subject experts, trivia writers, and quiz masters who have authored over 10,000 quizzes taken by more than 100 million users. This team includes our in-house seasoned quiz moderators and subject matter experts. Our editorial experts, spread across the world, are rigorously trained using our comprehensive guidelines to ensure that you receive the highest quality quizzes.
Learn about Our Editorial Process
| By MYLZ101
M
MYLZ101
Community Contributor
Quizzes Created: 7 | Total Attempts: 21,725
Questions: 12 | Attempts: 267

SettingsSettingsSettings
Building Laws Trivia Questions! Quiz - Quiz


What do you know about building laws? How much do you think you know to pass this quiz? Building laws are the rules and regulations made by town planning authorities covering the requirements of the building, safeguarding the safety of the public through open spaces. The rules control the activity of the building. Building laws are technically called building codes. Taking on this quiz will help you learn more about building laws.


Questions and Answers
  • 1. 

    At the time scheduled for bid opening, a contractor comes rushing into the room three minutes late with his bid.  You have not begun to open the bids.  What should you do?

    • A.

      Refuse to accept the bid, stating that the deadline has passed.

    • B.

      Ask if there are no objections from the other bidders to accept the bid since none has been opened yet.

    • C.

      Accept the bid with prejudice.

    • D.

      Accept the bid since none has been opened but make a mental note to look on it with disfavor when you are evaluating it.

    Correct Answer
    B. Ask if there are no objections from the other bidders to accept the bid since none has been opened yet.
    Explanation
    The correct answer is to ask if there are no objections from the other bidders to accept the bid since none has been opened yet. This is the most fair and reasonable course of action, as the bid has not been opened and the contractor arrived only three minutes late. By asking for objections from other bidders, it ensures that everyone has an equal opportunity and avoids any potential bias or prejudice in accepting the bid.

    Rate this question:

  • 2. 

    Which of the following is not generally true about bidding?

    • A.

      Bidding procedure mist be clearly and extensively outlined in the instructions to bidders because there are so many variations of the procedures.

    • B.

      Bidding is nearly always necessary for public works or government projects.

    • C.

      Open bidding usually presents more problem than other type.

    • D.

      Competitive bidding takes more than negotiation but can result in a lower construction cost.

    Correct Answer
    A. Bidding procedure mist be clearly and extensively outlined in the instructions to bidders because there are so many variations of the procedures.
    Explanation
    The statement "Bidding procedure must be clearly and extensively outlined in the instructions to bidders because there are so many variations of the procedures" is generally true about bidding. This is because bidding procedures can vary depending on the specific project and industry, so it is important to provide clear instructions to bidders to ensure fairness and transparency in the bidding process. By outlining the procedures extensively, it helps to avoid confusion and ensures that all bidders have a clear understanding of the requirements and expectations.

    Rate this question:

  • 3. 

    A performance bond is designed to:

    • A.

      Ensure that the sub contractor complete the work.

    • B.

      Guarantee that the contractor will finish on time.

    • C.

      Cover any possible liens that may be filed on the building.

    • D.

      Protect the owner by having a third party responsible for completing the work if the contractor does not.

    Correct Answer
    D. Protect the owner by having a third party responsible for completing the work if the contractor does not.
    Explanation
    A performance bond is a type of insurance that protects the owner of a project by ensuring that the work will be completed even if the contractor fails to do so. It provides a guarantee that a third party will step in and complete the work if the contractor is unable or unwilling to fulfill their obligations. This protects the owner from financial loss and delays in the project.

    Rate this question:

  • 4. 

    If the lowest bid came in 20 percent over your client’s construction budget, what would be the best advice you could give your client?

    • A.

      That you revise the design at no cost to reduce the construction cost.

    • B.

      That the project be bid out again using another list of contractor.

    • C.

      That you and the client work to revise the scope of the project to reduce cost.

    • D.

      That all the deduct alternates be accepted to reduce the bid, and that the client authorize a slight increase in construction cost to bring the two together.

    Correct Answer
    C. That you and the client work to revise the scope of the project to reduce cost.
    Explanation
    The best advice to give the client when the lowest bid is over the construction budget is to work together and revise the scope of the project to reduce costs. This means reevaluating the project requirements and finding areas where adjustments can be made without compromising the overall quality or functionality. By revising the scope, the client can potentially eliminate or modify certain features or specifications that are driving up costs, allowing the project to be completed within the budget. This approach ensures that the client's needs are met while also keeping the project financially feasible.

    Rate this question:

  • 5. 

    What variable affects the bid the most?

    • A.

      Contractor’s profit margin

    • B.

      Influence of the construction marketplace

    • C.

      Labor and materials

    • D.

      Sub contractor’s bid

    Correct Answer
    C. Labor and materials
    Explanation
    Labor and materials have the most significant impact on the bid. This is because the cost of labor and materials directly affects the overall cost of the project. The availability and pricing of labor and materials can vary depending on factors such as market conditions, supply and demand, and location. Therefore, any changes in the cost of labor and materials will directly impact the bid amount. On the other hand, the contractor's profit margin, the influence of the construction marketplace, and the sub contractor's bid may also have an influence on the bid, but their impact is generally not as significant as labor and materials.

    Rate this question:

  • 6. 

    In what order should the following activities take place during project closeout?                I. Preparation of the final certificate of payment    II. Punch list    III Issuance of the certificate of substantial completion     IV. notification by the contractor that the project is ready for final inspection     V. Receipt of the consent of surety.

    • A.

      II, III, V, IV, then I

    • B.

      II, IV, III, V, then I

    • C.

      IV, II, V, I, then III

    • D.

      IV, V, II, III, then I

    Correct Answer
    B. II, IV, III, V, then I
    Explanation
    The correct order for the activities during project closeout is as follows: first, the punch list is completed (II), then the contractor notifies that the project is ready for final inspection (IV), next the certificate of substantial completion is issued (III), followed by the receipt of the consent of surety (V), and finally, the preparation of the final certificate of payment (I).

    Rate this question:

  • 7. 

    Substantial completion indicates that:

    • A.

      The owner can make use of the work for the intended purpose and the requirements of the contract documents have been fulfilled.

    • B.

      The contractor has completed correcting punch list items.

    • C.

      The final certificate for payment is issued by the Architect and all documentation has been delivered to the owner.

    • D.

      All of the above.

    Correct Answer
    A. The owner can make use of the work for the intended purpose and the requirements of the contract documents have been fulfilled.
    Explanation
    Substantial completion refers to the point at which the owner can start using the completed work for its intended purpose. It also signifies that all the requirements mentioned in the contract documents have been met. This means that the contractor has finished all the necessary corrections and punch list items, and the architect has issued the final certificate for payment. Therefore, the correct answer is that all of the above conditions are satisfied when substantial completion is achieved.

    Rate this question:

  • 8. 

    During the periodic visit to the site, the Architect notices what appears to be an undersized variable air volume box being installed.  What should the Architect do?

    • A.

      Notify the mechanical engineer to look at the situation during the next site visit by the engineer. Note the observation on a field report.

    • B.

      Find the contractor and stop work on the installation until the size of the unit can be verified by the mechanical engineer and compared against the contract documents.

    • C.

      Notify the owner in writing that the work is not proceeding according to the contract documents. Arrange a meeting with the mechanical engineer to resolve the situation.

    • D.

      Notify the contractor that the equipment may be undersized and have the contactor check on it. Ask the mechanical engineer to verify the size of the unit against the specifications and report to the Architect.

    Correct Answer
    D. Notify the contractor that the equipment may be undersized and have the contactor check on it. Ask the mechanical engineer to verify the size of the unit against the specifications and report to the Architect.
    Explanation
    The architect should notify the contractor that the equipment may be undersized and ask them to check on it. They should also request the mechanical engineer to verify the size of the unit against the specifications and report back to the architect. This approach ensures that the contractor is made aware of the potential issue and takes responsibility for checking the equipment. Additionally, involving the mechanical engineer will provide an expert opinion on whether the unit is indeed undersized.

    Rate this question:

  • 9. 

    An Architect would use this instrument if the building department required additional exit signs beyond those shown on the approved plans when the project is 90 percent completed?

    • A.

      Order for minor change

    • B.

      Addendum

    • C.

      Change order

    • D.

      Construction change directive

    Correct Answer
    C. Change order
    Explanation
    In this scenario, an architect would use a change order if the building department required additional exit signs beyond those shown on the approved plans when the project is 90 percent completed. A change order is a document that outlines modifications or additions to the original contract, specifying the scope of work, cost, and timeline adjustments. It is used to formalize changes in the project's requirements or design, ensuring that all parties involved are aware of and agree to the alterations.

    Rate this question:

  • 10. 

    The contractor is solely responsible for:                       I. field reports to the owner     II. field test     III. scaffolding     IV. reviewing claims of the sub contractor                     V. reviewing shop drawings

    • A.

      . I, II, and III

    • B.

      II and III

    • C.

      II, III, and IV

    • D.

      III and V

    Correct Answer
    B. II and III
    Explanation
    The contractor is solely responsible for field tests and scaffolding. This means that the contractor is responsible for conducting tests on site to ensure that the construction meets the required standards and specifications. Additionally, the contractor is responsible for providing and maintaining the scaffolding necessary for the construction process. The other options, including I, IV, and V, are not mentioned as the contractor's sole responsibility.

    Rate this question:

  • 11. 

    Which of the following is NOT true about submittals?

    • A.

      The Architect must review them prior to checking by the contractor.

    • B.

      The contractor id ultimately responsible for the accuracy of dimensions and quantities.

    • C.

      They are not considered part of the contract documents.

    • D.

      The contractor can reject them and request resubmission.

    Correct Answer
    A. The Architect must review them prior to checking by the contractor.
    Explanation
    The statement "the Architect must review them prior to checking by the contractor" is NOT true about submittals. In the submittal process, the contractor is responsible for reviewing and checking the submittals for accuracy before submitting them to the architect for review. The architect then reviews the submittals to ensure compliance with the contract documents.

    Rate this question:

  • 12. 

    If a contractor makes a claim for additional money due to extra work caused by unforeseen circumstances, the Architect must respond within:

    • A.

      5 days

    • B.

      7 days

    • C.

      10 days

    • D.

      Not until supporting data are submitted.

    Correct Answer
    C. 10 days
    Explanation
    The Architect must respond within 10 days when a contractor makes a claim for additional money due to extra work caused by unforeseen circumstances. This time frame allows the Architect sufficient time to review the claim and make a decision on whether to approve or deny it. It ensures that the contractor receives a timely response and can proceed accordingly with their work.

    Rate this question:

Quiz Review Timeline +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 21, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • May 29, 2011
    Quiz Created by
    MYLZ101
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.