AP - Riesgos Quiz

Reviewed by Editorial Team
The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Leonelfulcheri
L
Leonelfulcheri
Community Contributor
Quizzes Created: 1 | Total Attempts: 137
| Attempts: 137 | Questions: 23 | Updated: Jul 22, 2024
Please wait...
Question 1 / 24
🏆 Rank #--
Score 0/100

1. Cuál de los siguientes no es un factor en la evaluación de riesgos del proyecto

Explanation

Los premios de los seguros no son un factor en la evaluación de riesgos del proyecto. La evaluación de riesgos del proyecto se centra en identificar y analizar los eventos de riesgo, determinar la probabilidad de que ocurran y evaluar el impacto financiero que podrían tener en el proyecto. Los premios de los seguros se refieren a los pagos que se hacen a las compañías de seguros para obtener cobertura y protección contra posibles pérdidas, pero no están directamente relacionados con la evaluación de riesgos del proyecto.

Submit
Please wait...
About This Quiz
AP - Riesgos Quiz - Quiz

.

2.

What first name or nickname would you like us to use?

You may optionally provide this to label your report, leaderboard, or certificate.

2. El equipo de gestión de riesgos en un proyecto de software ha decidido, debido a lapérdida de un recurso clave ,tercerizar este trabajo de alto riesgo tecnológico. Este es unejemplo de ?

Explanation

This scenario exemplifies the concept of transferring the risk. The management team, faced with the loss of a key resource, has decided to outsource the high-risk technological work to another party. By doing so, they are transferring the responsibility and potential negative outcomes of the risk to the external entity. This allows the management team to reduce their exposure to the risk and potentially mitigate any negative consequences that may arise from the loss of the key resource.

Submit

3. Cuál de los siguientes es un enunciado falso sobre riesgos en proyecto?

Explanation

The correct answer is "Un riego puede tener solamente un efecto negativo sobre el proyecto." This statement is false because risks can have both positive and negative effects on a project. Some risks may present opportunities or benefits for the project, while others may pose threats or negative impacts. Therefore, it is important to consider both the positive and negative aspects of risks when managing them in a project.

Submit

4. El deseo individual de enfrentar un riesgo puede determinarse por:

Explanation

La aceptación del riesgo se refiere a la disposición de una persona para enfrentar o asumir un riesgo determinado. Esta decisión puede basarse en diversos factores, como la tolerancia al riesgo, la confianza en las habilidades propias, la percepción de la importancia o beneficios potenciales de asumir el riesgo, entre otros. En resumen, la aceptación del riesgo es una medida del deseo individual de enfrentar una situación o actividad arriesgada.

Submit

5. Cuál de las siguientes no es una técnica utilizada en el proceso de identificación deriesgos?

Explanation

La navegación en la web no es una técnica utilizada en el proceso de identificación de riesgos. Las otras tres opciones mencionadas son técnicas comunes utilizadas en este proceso. La tormenta de ideas se utiliza para generar ideas y posibles riesgos, la técnica de Delphi implica la colaboración de expertos para llegar a un consenso sobre los riesgos, y el análisis FODA (Fortalezas, Oportunidades, Debilidades y Amenazas) se utiliza para evaluar los riesgos en relación con el entorno interno y externo de una organización. La navegación en la web no está directamente relacionada con la identificación de riesgos.

Submit

6. Si un proyecto tiene una probabiidad del 60 por ciento de obtener una ganancia de $100.000 y 40 por ciento de probabilidad de tener una pérdida de $ 100.000 el valormonetario esperado para el proyecto es:

Explanation

The expected monetary value for the project is $20,000 in profit. This is calculated by multiplying the probability of each outcome by its respective monetary value and summing them up. In this case, there is a 60% chance of a $100,000 profit and a 40% chance of a $100,000 loss. Therefore, the expected monetary value is (0.6 * $100,000) + (0.4 * -$100,000) = $60,000 - $40,000 = $20,000 profit.

Submit

7. Un contratista se ha atrasado en 30 días. Cómo se llama el proceso de determinar cómoeste evento afectará al cronograma del proyecto?

Explanation

The correct answer is "Evaluación del riesgo". In this context, the contractor's delay of 30 days represents a risk to the project schedule. Evaluating the risk involves assessing the potential impact of this delay on the project schedule and determining the appropriate actions to address it. This process helps in understanding the level of risk associated with the delay and allows for informed decision-making regarding the project's timeline.

Submit

8. Cuál de las siguientes es una afirmación valida sobre análisis SWOT (FODA)?

Explanation

El análisis SWOT (FODA) es una técnica utilizada para identificar y evaluar las fortalezas, debilidades, oportunidades y amenazas de una organización o proyecto. No se refiere al análisis de alcance, trabajo, alternativas y tiempos, ni se utiliza para planificar la respuesta a riesgos o realizar análisis cuantitativo de riesgos. Su objetivo principal es proporcionar una visión general de la situación actual y futura, y ayudar a tomar decisiones estratégicas basadas en esta evaluación.

Submit

9. Cuál de las siguientes no es una respuesta de riesgos válida?

Explanation

La respuesta "Rechazar" no es una respuesta de riesgos válida porque no aborda el riesgo de ninguna manera. Aceptar, mitigar y evitar son enfoques válidos para abordar los riesgos, ya sea aceptándolos como parte del proceso, tomando medidas para reducir su impacto o evitándolos por completo. Sin embargo, rechazar simplemente significa negar o no hacer frente al riesgo, lo cual no es una estrategia efectiva para gestionar los riesgos en un proyecto o situación.

Submit

10. El desarrollo de respuestas ante los riesgos pretende:

Explanation

The development of responses to risks aims to formulate strategies for dealing with adverse events. This means that it involves creating plans and actions to mitigate or address potential risks that may arise during a project. It is not about simply identifying risks or quantifying them, but rather about coming up with effective strategies to handle and minimize the impact of these risks.

Submit

11. Usted está gestionando un proyecto donde se realiza la instalación de servidores en unlugar físico propenso a sufrir desastres naturales como huracanes e inundaciones. Ustedentonces decide instalar algunos servidores en otra ciudad como back up en caso de existiralguno de estos fenómenos naturales. Este es un ejemplo de ?

Explanation

Installing backup servers in another city to protect against natural disasters is an example of mitigating the risk. Mitigating the risk involves taking proactive measures to reduce the impact or likelihood of a risk occurring. In this case, by installing servers in a different location, the project manager is reducing the risk of data loss or service disruption in the event of a natural disaster.

Submit

12. La característica principal de la técnica Delphi es:

Explanation

The main characteristic of the Delphi technique is that it relies on the intuitive opinions of experts. This means that instead of using historical information or a hierarchical analysis process, the Delphi technique gathers input from a group of experts who provide their subjective opinions and judgments. These opinions are then aggregated and analyzed to reach a consensus or make a decision.

Submit

13. El análisis MonteCarlo le da:

Explanation

The Monte Carlo analysis provides an indication of the risk involved in a project. This analysis involves simulating multiple scenarios and considering various factors to determine the likelihood of different outcomes. By conducting a Monte Carlo analysis, project managers can identify potential risks and uncertainties that may impact the success of the project. This information allows them to make informed decisions and develop appropriate risk management strategies to mitigate potential issues.

Submit

14. Usted está en el proceso de evaluar la probabilidad e impacto de un riesgo usando elvalor esperado. Este es un ejemplo de que de lo siguiente?

Explanation

The given correct answer, "Análisis cuantitativo de riesgos" (Quantitative risk analysis), is the most appropriate option because it involves evaluating the probability and impact of a risk using expected value. This process uses numerical data and calculations to quantitatively assess the risks and their potential impact on a project or organization. It helps in making informed decisions by providing a quantitative understanding of the risks involved.

Submit

15. La herramienta generalmente usada para la planificación de la gestión de riesgos es:

Explanation

La herramienta generalmente usada para la planificación de la gestión de riesgos es la reuniones de planificación. Estas reuniones permiten a los miembros del equipo discutir y analizar los posibles riesgos asociados con un proyecto o actividad. Durante estas reuniones, se pueden identificar y evaluar los riesgos, así como desarrollar estrategias y planes de acción para mitigarlos. Las reuniones de planificación también brindan la oportunidad de asignar responsabilidades y establecer plazos para la gestión de riesgos. En resumen, las reuniones de planificación son una herramienta efectiva para abordar y gestionar los riesgos de manera proactiva.

Submit

16. Cuál de los siguientes es un enunciado correcto sobre riesgos secundarios

Explanation

This statement correctly identifies secondary risks as those that result from the response to identified risks. Secondary risks are the potential risks that arise as a result of implementing risk mitigation strategies or actions. When addressing identified risks, it is important to consider the potential for new risks to emerge during the risk management process. These secondary risks need to be assessed and managed accordingly to ensure the overall effectiveness of the risk management plan.

Submit

17. Cuál de los siguientes enunciados sobre riesgos es falso?

Explanation

The statement that "El análisis cuantitativo puede ser realizado solamente sobre riesgos sobre los cuáles ya se ha realizado el análisis cualitativo" is false. The quantitative analysis can be performed independently of the qualitative analysis. While the qualitative analysis assesses the impact and likelihood of risks qualitatively, the quantitative analysis uses numerical data and models to assess the impact and likelihood of risks quantitatively. Therefore, the quantitative analysis can be performed without first conducting the qualitative analysis.

Submit

18. En cuál de las siguientes fases se tiene mayor influencia para manejar riesgos?:

Explanation

The conceptual phase has the greatest influence in managing risks because it is during this phase that the overall project goals, objectives, and requirements are defined. By thoroughly analyzing and identifying potential risks at this stage, effective risk management strategies can be developed and implemented throughout the project lifecycle. This allows for proactive risk mitigation and helps ensure that potential risks are addressed and minimized before they can have a significant impact on the project's success.

Submit

19. El registro de riesgos no es una entrada de cuál de los siguientes procesos?

Explanation

El registro de riesgos no es una entrada del proceso de Identificación de riesgos, ya que el registro de riesgos es una salida de este proceso. La identificación de riesgos implica la identificación y documentación de los riesgos que podrían afectar al proyecto, mientras que el registro de riesgos es el documento que contiene la lista de todos los riesgos identificados, junto con su descripción, categorización y otras características relevantes. Por lo tanto, el registro de riesgos se utiliza como entrada en otros procesos, como el análisis cualitativo y cuantitativo de riesgos, y la planificación de la respuesta a los riesgos.

Submit

20. Basándose en la siguiente información cual es la reserva de fondos de contingencia parael proyecto?

Explanation

Based on the provided information, the reserve fund for the project is $117,150.

Submit

21. Si un evento tiene 90% de probabilidad de ocurrir y la consecuencia será $10.000 , querepresenta la cifra de $9.000?

Explanation

The correct answer is "Valor monetario esperado." In this scenario, the "Valor monetario esperado" represents the expected monetary value of the event. It is calculated by multiplying the probability of the event occurring (90%) by the consequence or monetary value associated with it ($10,000). In this case, the expected monetary value would be $9,000 (90% of $10,000). This represents the average amount of money that can be expected from the event, taking into account the probability of its occurrence.

Submit

22. Cuantificación de riesgos incluye:

Explanation

La cuantificación de riesgos implica evaluar la probabilidad e impacto de los eventos potenciales. Esto implica analizar la posibilidad de que ocurran ciertos eventos y el grado de impacto que tendrían en el proyecto o en la organización. Al evaluar la probabilidad e impacto, se puede determinar qué eventos son más probables de ocurrir y cuáles tendrían un mayor impacto, lo que permite priorizar los riesgos y tomar medidas adecuadas para mitigarlos.

Submit

23. Cuál de las siguientes no es una salida del análisis cualitativo de riesgos?

Explanation

The correct answer is "Una lista priorizada de los riesgos basada en el efecto total de cada riesgo en el conjunto los objetivos del proyecto". This is not a output of qualitative risk analysis because qualitative risk analysis focuses on assessing the probability and impact of risks on specific project objectives, not on the overall effect of each risk on the project's goals. The other options, such as a prioritized list of risks for a specific project objective based on the probability and impact matrix, a watchlist of low priority risks, and a list of trends in the analysis results, are all valid outputs of qualitative risk analysis.

Submit
×
Saved
Thank you for your feedback!
View My Results
Cancel
  • All
    All (23)
  • Unanswered
    Unanswered ()
  • Answered
    Answered ()
Cuál de los siguientes no es un factor en la evaluación...
El equipo de gestión de riesgos en un proyecto de software ha...
Cuál de los siguientes es un enunciado falso sobre riesgos en...
El deseo individual de enfrentar un riesgo puede determinarse por:
Cuál de las siguientes no es una técnica utilizada en el...
Si un proyecto tiene una probabiidad del 60 por ciento de obtener una...
Un contratista se ha atrasado en 30 días. Cómo se llama...
Cuál de las siguientes es una afirmación valida sobre...
Cuál de las siguientes no es una respuesta de riesgos...
El desarrollo de respuestas ante los riesgos pretende:
Usted está gestionando un proyecto donde se realiza la...
La característica principal de la técnica Delphi es:
El análisis MonteCarlo le da:
Usted está en el proceso de evaluar la probabilidad e impacto...
La herramienta generalmente usada para la planificación de la...
Cuál de los siguientes es un enunciado correcto sobre riesgos...
Cuál de los siguientes enunciados sobre riesgos es falso?
En cuál de las siguientes fases se tiene mayor influencia para...
El registro de riesgos no es una entrada de cuál de los...
Basándose en la siguiente información cual es la reserva...
Si un evento tiene 90% de probabilidad de ocurrir y la consecuencia...
Cuantificación de riesgos incluye:
Cuál de las siguientes no es una salida del análisis...
play-Mute sad happy unanswered_answer up-hover down-hover success oval cancel Check box square blue
Alert!