200 PMP Exam Practice Questions (V1) - Pmi Pmbok Exam Prep (4th Edition)

Reviewed by Editorial Team
The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Pepito
P
Pepito
Community Contributor
Quizzes Created: 1 | Total Attempts: 336
| Attempts: 336 | Questions: 23 | Updated: Mar 21, 2025
Please wait...
Question 1 / 24
🏆 Rank #--
Score 0/100

1.          Select the BEST definition of portfolio according to PMBOK:

Explanation

The correct answer defines a portfolio as a collection of projects or programs and other work that are grouped together to facilitate effective management of that work to meet strategic business objectives. This definition emphasizes the purpose of a portfolio, which is to manage multiple projects and work together to achieve strategic business goals.

Submit
Please wait...
About This Quiz
200 PMP Exam Practice Questions (V1) - Pmi Pmbok Exam Prep (4th Edition) - Quiz

Author/Owner: Sherry HohmannPMP Exam Practice Questions (Ch 1-3) : PMI PMBOK Exam Prep(4th Edition)

2.

What first name or nickname would you like us to use?

You may optionally provide this to label your report, leaderboard, or certificate.

2. Select the BEST answer regarding programs according to PMBOK:

Explanation

(PMBOK P.9, CH 1)

Submit

3. Project governance provides a comprehensive, consistent method of controlling the project and ensuring its success.  The project governance approach should be described in the _________________________.

Explanation

(PMBOK P. 20, CH 2)

Submit

4. A phase can only start once the previous phase is complete occurs in the following relationship:

Explanation

(PMBOK P. 21, CH 2)

Submit

5. The following are all considered projects by PMBOK with the exception of:

Explanation

(PMBOK P.12, CH 1)

Submit

6. Cost and staffing levels are the highest during which phase of the project life cycle:

Explanation

(PMBOK P.16, CH 2)

Submit

7. .      Select the BEST definition of progressive elaboration according to PMBOK:

Explanation

Progressive elaboration, according to PMBOK, refers to continuously improving and detailing a plan as more detailed and specific information and more accurate estimates become available. This means that as the project progresses, the plan is refined and adjusted based on new information and estimates. This allows for flexibility and adaptability in the project management process, ensuring that the plan is continuously updated to reflect the evolving needs and requirements of the project.

Submit

8. All of the following are considered enterprise environmental factors by PMBOK except:

Explanation

(PMBOK P.14, CH 1)

Submit

9. A project phase is generally concluded and formally closed with a ______________________________________.

Explanation

(PMBOK P. 20, CH 2)

Submit

10. A PMO (Project Management Office) is an organizational body or entity assigned variously responsibilities related to the centralized and coordinated management of those projects under its domain.  The responsibilities of a PMO include:

Explanation

(PMBOK P.11, CH 1)

Submit

11. The cost of changes and correcting errors typically:

Explanation

(PMBOK P.17, CH 2)

Submit

12. All of the following are ways the PMO supports project managers except:

Explanation

(PMBOK P.11, CH 1)

Submit

13. As a project manager, it is important to balance competing project constraints.  Which of the following is NOT a constraint in managing a project?

Explanation

The correct answer is "Initiating, planning, executing, monitoring and controlling, and closing." This is because these are actually the key phases or processes involved in managing a project, rather than constraints. Constraints in project management typically refer to factors such as time, cost, scope, quality, and resources that may limit or impact the project's success.

Submit

14. The ability to influence the final characteristics of the project’s product, without significantly impacting cost, is:

Explanation

(PMBOK P. 17, CH 2)

Submit

15. Project life cycle occurs in _____ or _____ phases of a product life cycle.

Explanation

(PMBOK P.18, CH 2)

Submit

16. The following is TRUE regarding portfolios according to PMBOK:

Explanation

Portfolios, according to PMBOK, are a group of related projects managed in a coordinated way to obtain benefits and control that cannot be achieved by managing them individually. They are overseen by an organizational body or entity that is responsible for the centralized and coordinated management of these projects. This body is delegated the authority to act as a stakeholder and key decision maker at the beginning of each project. However, it is important to note that the projects or programs within a portfolio may not necessarily be interdependent or directly related to each other.

Submit

17. When phases are sequential, the close of a phase ends with some form of transfer or handoff of the work product produced as the phase deliverable.  This phase end represents a natural point to reassess the effort underway and to change or terminate the project if necessary.  These points are referred to as:

Explanation

(PMBOK P. 19, CH 2)

Submit

18. Cost and staffing levels are the lowest during which phase of the project life cycle:

Explanation

(PMBOK P.16, CH 2)

Submit

19. A relationship where only one phase is planned at any given time and the planning for the next is carried out as work progresses on the current phase and deliverables is the following:

Explanation

(PMBOK P. 22, CH 2)

Submit

20. .      Select the BEST definition of progressive elaboration according to PMBOK:

Explanation

Progressive elaboration, according to PMBOK, refers to the process of continuously refining and expanding project details and plans as more information becomes available. It involves iteratively developing the project scope, schedule, budget, and risk management strategies over time. This allows for a more accurate and comprehensive understanding of the project as it progresses, enabling better decision-making and reducing uncertainties.

Submit

21. Identifying stakeholders and understanding their relative degree of influence on a project is critical.  Failure to do so can ___________________________________.

Explanation

(PMBOK P. 24, CH 2)

Submit

22. The following are all types of phase-to-phase relationships EXCEPT:

Explanation

(PMBOK P. 21, CH 2)

Submit

23. Projects vary in size and complexity.  No matter how large or small, simple or complex, all projects can be mapped to the following life cycle structure:

Explanation

(PMBOK P. 16, CH 2)

Submit
×
Saved
Thank you for your feedback!
View My Results
Cancel
  • All
    All (23)
  • Unanswered
    Unanswered ()
  • Answered
    Answered ()
         Select the BEST definition ...
Select the BEST answer regarding programs according to PMBOK:
Project governance provides a comprehensive, ...
A phase can only start once the previous phase is ...
The following are all considered projects by PMBOK ...
Cost and staffing levels are the highest during which ...
.      Select the BEST definition ...
All of the following are considered enterprise ...
A project phase is generally concluded and formally ...
A PMO (Project Management Office) is an organizational ...
The cost of changes and correcting errors typically:
All of the following are ways the PMO supports project ...
As a project manager, it is important to balance ...
The ability to influence the final characteristics of ...
Project life cycle occurs in _____ or _____ phases of ...
The following is TRUE regarding portfolios according to PMBOK:
When phases are sequential, the close of a phase ends ...
Cost and staffing levels are the lowest during which ...
A relationship where only one phase is planned at any ...
.      Select the BEST definition ...
Identifying stakeholders and understanding their ...
The following are all types of phase-to-phase relationships EXCEPT:
Projects vary in size and complexity.  No matter how large or...
play-Mute sad happy unanswered_answer up-hover down-hover success oval cancel Check box square blue
Alert!